Five dimensions to consider
When we think about contracts, the deck names five essential dimensions: the structure, meaning who will do what; the payment or remuneration method; how contractors will be selected; how risk is allocated; and how disputes will be resolved.
The contract
- StructureWho will do what?
- PaymentHow will the contractor be paid?
- SelectionHow will contractors be selected?
- RiskWhich party will handle which risk?
- Dispute resolutionHow will disagreements be resolved?
Structure: who will do what?
Contract structure defines how responsibilities and obligations are distributed among the parties. Will one party be accountable for delivering the whole project, or will several share responsibility across phases or components? Will one main contractor manage everything from design to execution, or will there be separate contractors for engineering, procurement, and construction? And how much scope does each contractor get: a narrow, specialized portion, or a broader package?
- Choosing between a single entity and a multi-prime model directly affects project risk, coordination effort, and accountability.
- A well-designed structure supports clear ownership, effective collaboration, and smoother execution.
Payment: fixed price or reimbursable
The deck presents two primary payment models. In a fixed price contract, a total lump sum is agreed at the outset, whatever time or cost the work actually takes. In a reimbursable contract, the contractor is paid for the actual costs incurred or quantities installed, often with an added fee or percentage for profit.
- Fixed price gives the owner cost certainty, but places more risk on the contractor, who must deliver within the fixed amount.
- Reimbursable offers flexibility when the scope is uncertain or likely to evolve, but needs more oversight to control expenses and can cost the owner more.
- The choice depends on project complexity, scope clarity, and the risk tolerance of both parties.
Fixed price
- Price
- A total lump sum agreed at the outset
- The owner gains
- Cost certainty
- More cost risk sits with
- The contractor, who must deliver within the fixed amount
- Fits
- Clear, stable scope
Reimbursable
- Price
- Actual costs incurred or quantities installed, often plus a fee
- The owner gains
- Flexibility when scope is uncertain or evolving
- More cost risk sits with
- The owner, who needs more oversight to control expenses
- Fits
- Scope that is uncertain or likely to evolve
Selection: how contractors are chosen
The owner first decides whether the contract needs prequalification, which makes sure only contractors with the necessary experience, financial capacity, and technical capability are eligible to bid. It then decides whether sole sourcing is allowed, and whether to issue an open invitation to the market or limit bidding to a shortlist.
- Sole sourcing awards the contract directly to a specific contractor without competitive bidding, which may suit specialized or urgent projects.
- An open invitation goes to the broader market; limited bidding goes only to pre-identified or invited contractors.
- The choice depends on market conditions, project complexity, and the need for confidentiality or speed.
- The right approach attracts qualified bidders and keeps procurement fair, transparent, and efficient.
Risk: which party handles which risk?
The slide on this dimension is titled Risk Transfer. It uses the Project Management Institute’s definition from its PMBOK guide, cited on the slide as the 2008 edition: project risk is an uncertain event or condition that, if it materializes, impacts at least one project objective. Those objectives typically include scope, schedule, cost, and quality.
- Risks can have one or more causes, such as project requirements, assumptions, constraints, or existing project conditions.
- Risks can lead to positive as well as negative outcomes.
- Risk conditions, such as inadequate project management or dependence on external parties beyond your control, add to the risk.
- An essential dimension of contracting is deciding which party will handle which risk.
- CauseA permit is required
- Risk eventThe permit takes longer than anticipated
- ConsequenceCost, schedule, or quality is affected
- CauseLimited personnel are assigned
- Risk eventToo few people to complete the tasks
- ConsequenceCost, schedule, or quality is affected
Dispute resolution: how disagreements are handled
Every contract carries the potential for disagreement, so the contract itself should define how disputes will be resolved, starting with early identification and resolution at project level.
- Will disputes go first through negotiation or mediation? The deck calls these the preferred amicable and cost-effective settlement methods.
- In mediation, a neutral third party facilitates discussion between the parties to reach a mutually acceptable solution.
- If amicable efforts fail, the contract should state whether arbitration or litigation follows, and name the jurisdiction and governing law.
- Not every contract uses every step. Each contract sets out its own mechanism.
- A clearly defined process helps avoid delays, reduce legal costs, and preserve working relationships.
- Amicable settlement firstNegotiation or mediationPreferred as amicable and cost-effective. In mediation, a neutral third party facilitates.
- If amicable efforts failArbitration or litigationAs the contract specifies, with the jurisdiction and governing law named.
Each contract defines its own mechanism; not every contract uses every method.
All of them are connected
Structure, payment, selection, risk, and dispute resolution are distinct, but they are connected: each decision influences the others. When deciding what goes into a contract, the deck lists six questions to answer.
- What is being purchased?
- How complete is the statement of work?
- How much effort and expertise can the buyer devote to managing the seller?
- Does the buyer want to offer the seller incentives?
- What are the conditions in the marketplace or economy?
- What are the industry standards for the type of contract used?
Key ideaAnswering these questions together helps make the contract effective, balanced, and suited to the project’s goals and operational realities.
Key takeaways
- Structure answers who will do what; the choice between a single entity and a multi-prime model changes risk, coordination, and accountability.
- Fixed price gives the owner cost certainty; reimbursable gives flexibility but needs more oversight.
- Selection covers prequalification, sole sourcing, and open or limited bidding.
- Risk is uncertainty that affects scope, schedule, cost, or quality, and the contract decides who carries it.
- The contract should define its own dispute process, including the governing law and jurisdiction.
- The five dimensions are connected, so decide them together.