Contracts and communication are different lines
The deck’s delivery diagrams draw two kinds of relationship: contractual relationships, where two parties hold a contract with each other, and communicational relationships, where they work together without one. The design-build diagram adds a third, the internal relationship between functions inside one entity. In each diagram, the question is who holds a contract with whom.
Traditional delivery: design-bid-build
The traditional delivery method is design-bid-build. The owner, which may be public or private, an individual, a company, or a joint venture, hires an architect/engineer, usually referred to as the consultant, and a general contractor or multiple prime contractors. The general contractor then contracts with subcontractors.
- Contractual relationship
- Communication relationship
Key ideaThere is no contractual relationship between the general contractor, the builder, and the architect/engineer. Each has its own contract with the owner, and between themselves they only communicate.
Design-build
In design-build, the owner contracts both design and construction to a single entity. The deck calls it a less common delivery method. The design-build entity holds the design function and the construction function internally, and it hires the subcontractors.
- In the interest of schedule, the owner contracts one entity to provide the design and to construct the project according to that design.
- Owners choose design-build to skip the bidding period between engineering and construction.
- The contract may be negotiated with a single design-builder or result from competitive proposals, and selection can rest on low price or on value criteria such as experience, staff, and bonding capacity.
- The entity can be a design-build firm, or a joint venture of a design firm and a construction firm formed for this specific project.
Design-build entity
- Contractual relationship
- Internal relationship
Key ideaDue diligence is expected from owners on every project, but the deck says the measures taken under design-build contracts should be more stringent.
Read with careThe notes introduce design-build by saying that owner-led delivery and design-bid-build have already been covered, but no earlier slide covers owner-led delivery.
Professional construction management
In a professional CM contract, the owner hires a construction manager to oversee the work of different trade contractors. A trade contractor focuses on one discipline, such as electrical, mechanical, or civil work. Before construction begins, the owner hires both a design firm and a construction management firm, based on their qualifications.
- Contractual relationship
- Communication relationship
Key ideaUnder a CM contract, there is no contractual relationship between the construction manager and the architect/engineer.
What the construction manager does
The owner is in a trusting relationship with the construction manager, a professional or firm trained in managing construction processes.
- It assists in developing bid documents and in selecting design and construction firms.
- It oversees and supervises project construction.
- It is generally interposed between the owner and some or all of the other participants.
- It controls the flow of information among all parties.
- It acts as facilitator and mediator in conflicts.
Agency CM
The first form of CM contract is agency CM. The agency construction manager works for a fixed fee, acts as the owner’s agent, and extends the owner’s internal capabilities in carrying out traditional owner responsibilities.
- Its level of service can range from on-call advice to full project management.
- In some cases the owner hires it before design begins, and it may help select and contract the designer, or might even be the designer.
CM at risk
Under CM at risk, the construction manager bears the risk of cost and schedule predictability, and the contractual relationships run between the CM and the trade contractors. The arrangement significantly increases the owner’s delegation of control and risk. It is popular with owners of private projects.
- CM at risk typically contracts with the owner in two stages.
- First, the CM manages and undertakes services during the conceptual and preliminary design phases, working with the design professional.
- When design is complete, the owner and the CM agree on a price and schedule for completing the construction work.
- Because it must agree the guaranteed maximum price with the owner, the CM usually has a larger role in the design phases.
- Stage 1 · during designDesign-phase servicesThe CM manages and undertakes services in conceptual and preliminary design, with the design professional.
- Stage 2 · design completePrice and schedule agreedOwner and CM agree the construction price and schedule, usually as a guaranteed maximum price (GMP).
- ConstructionThe CM carries the riskIt holds the trade contracts and bears the risk of cost and schedule predictability.
Key ideaGMP stands for guaranteed maximum price. The CM usually guarantees to complete the project within this budget, which gives the owner security that the project will be built within budget.
Agency CM and CM at risk compared
Both are forms of professional construction management. They differ in who carries the risk and how the price is committed.
| Agency CM | CM at risk | |
|---|---|---|
| Role | The owner’s agent, extending the owner’s own capabilities | Bears the risk of cost and schedule predictability, and holds the contracts with the trade contractors |
| Price | Works for a fixed fee | Usually guarantees a maximum price (GMP) |
| Service and timing | From on-call advice to full project management; sometimes hired before design begins | Two stages: design-phase services, then a construction price and schedule once design is complete |
| Effect on the owner | Extends what the owner can do itself | Significantly increases the owner’s delegation of control and risk |
Key takeaways
- In design-bid-build, the owner holds separate contracts with the architect/engineer and the general contractor, who only communicate with each other.
- In design-build, one entity designs and builds, which can remove the bidding period between engineering and construction.
- A professional construction manager oversees trade contractors, controls the flow of information, and mediates conflicts, with no contract with the architect/engineer.
- Agency CM works for a fixed fee as an extension of the owner.
- CM at risk holds the trade contracts and usually guarantees a maximum price.