Reimbursable contracts
Reimbursable contracts pay the contractor for the actual costs incurred during the work, along with an additional fee or profit. They are commonly used when the full scope of work isn’t clearly defined at the outset, or when flexibility is needed. The deck divides them into two main types: time and material, and cost reimbursable.
- Both types offer flexibility, but they shift more financial risk to the client.
- Strong cost control and oversight are essential to manage that risk and avoid overruns.
- Reimbursable contracts
- Time and material (T&M)Per hour or per item; the total is unknown
- Cost reimbursableAllowable costs, usually plus a fee
- CostNo fee
- Cost plus fixed fee (CPFF)Fee fixed before work begins
- Cost plus incentive fee (CPIF)Target cost and fee; savings and overruns shared
- Cost plus award fee (CPAF)Base fee plus a performance award
- Cost plus fee, or percentage of costThe fee grows with cost
Read with careSlide 59 says reimbursable contracts pay costs plus a fee or profit, but the cost contract on slide 67 pays no fee. Slide 59 also places time and material under reimbursable contracts, while slide 61 says it has elements of both fixed price and cost-reimbursable contracts.
Time and material (T&M)
In a time and material contract, the buyer pays on a per-hour or per-item basis. These contracts are frequently used for service efforts whose level of effort cannot be defined when the contract is awarded. A time and material contract has elements of a fixed price contract, in the fixed price per hour, and of a cost-reimbursable contract, in the material costs and the fact that the total cost is unknown.
- Its terms and conditions are typically simpler, allowing quick negotiation so that work can begin sooner.
- It suits short-term or evolving scopes, but needs close monitoring to control costs.
Deck exampleContract = $100 per hour plus expenses or materials at cost. Or: $100 per hour plus materials at $5 per linear meter of wood.
The not-to-exceed clause
To make sure costs do not rise above the budget, the buyer may add a Not to Exceed clause to a time and material contract. The clause limits the total amount the buyer is required to pay.
Key ideaA time and material contract fixes the rate, not the total. A not-to-exceed clause is how the buyer puts a ceiling on the total.
Cost reimbursable contracts
A cost reimbursable contract is used when the exact scope of work is uncertain, so costs cannot be estimated accurately enough to use a fixed price contract. The buyer pays the seller’s allowable incurred costs, to the extent prescribed in the contract. Such contracts typically add a fee or award to allow for the seller’s profit.
- They are common in complex or high-risk projects, such as research and development or early-stage construction.
- The deck lists six types: cost, cost plus fixed fee, cost plus incentive fee, cost plus award fee, cost plus fee, and cost plus percentage of cost. It teaches the last two together.
Cost contract
In a cost contract, the seller receives no fee. It is reimbursed for its costs but makes no profit. The deck says this is appropriate for work performed by nonprofit organizations.
Deck exampleContract = the cost of work and materials. There is no profit: the seller is reimbursed, but earns nothing more.
Cost plus fixed fee (CPFF)
A cost plus fixed fee contract pays the seller’s actual costs plus a negotiated fee that is fixed before work begins. The fee is the seller’s profit, usually a percentage of the estimated cost. Because the fee does not vary with actual costs, the seller has no incentive to increase or inflate costs.
Deck exampleContract = cost plus a fee of $100,000.
Cost plus incentive fee (CPIF)
In a cost plus incentive fee contract, the seller is paid its actual costs plus a fee based on specific performance objectives stated in the contract. An original estimate of the total cost is made, called the target cost, and a fee for the work is set, called the target fee.
- If the actual cost is less than the target cost, the seller gets a percentage of the savings.
- If the actual cost exceeds the target cost, the seller shares the overrun with the buyer.
Read with careThe example on the incentive fee slide repeats the award fee example word for word: cost plus a base fee plus an award for meeting buyer-specified criteria, with a maximum award of $50,000. Only the notes describe target cost, target fee, and sharing, so the lesson teaches the notes.
Cost plus award fee (CPAF)
In a cost plus award fee contract, the buyer pays the costs and a base fee, plus an award, a bonus, based on performance determined in advance. It is a type of incentive contract, and the procedures for deciding the award must be in place in advance to avoid subjective judgement.
Deck exampleContract = cost plus a base fee plus an award for meeting buyer-specified performance criteria. The maximum award available is $50,000.
Read with careThe notes compare this contract with cost plus incentive fee and say the incentive is “a potential penalty with no possibility of a penalty,” which contradicts itself. The rest of the slide describes the award as a bonus.
Cost plus fee, or cost plus percentage of cost
This contract requires the buyer to pay all costs plus a percentage of those costs as the fee. The deck states that it is not allowed in the United States for federal acquisitions or procurements under the federal acquisition regulations, and that it is bad for buyers everywhere.
Deck exampleContract = cost plus 10 percent of costs as fee.
Key ideaBecause the fee is a percentage of cost, the seller earns more as the project costs more. The fee grows with cost instead of rewarding control of it.
The cost-reimbursable forms compared
Every form reimburses allowable costs. They differ in what the seller earns on top, and in how that shapes the seller’s interest in cost.
| Contract | Buyer pays | Seller’s profit | What the deck stresses |
|---|---|---|---|
| Cost | Costs of work and materials | None | Appropriate for work by nonprofit organizations |
| Cost plus fixed fee (CPFF) | Actual costs plus a fee fixed before work begins | The fixed fee, for example $100,000 | The fee does not vary, so there is no incentive to inflate costs |
| Cost plus incentive fee (CPIF) | Actual costs plus a fee tied to performance objectives | A target fee, adjusted by sharing savings or overruns | Target cost and target fee are set at the start |
| Cost plus award fee (CPAF) | Costs plus a base fee plus a performance award | Base fee plus an award, for example up to $50,000 | The award procedure must be set in advance |
| Cost plus percentage of cost | All costs plus a percentage of costs, for example 10% | Grows as costs grow | Not allowed for US federal acquisitions; bad for buyers everywhere |
Key takeaways
- Reimbursable contracts pay actual costs and suit unclear or evolving scope, but they shift financial risk to the buyer.
- Time and material fixes a rate per hour or item while the total stays unknown, so a not-to-exceed clause can cap it.
- Cost reimbursable contracts pay allowable costs, usually plus a fee or award.
- CPFF fixes the fee, CPIF shares savings and overruns against a target cost, and CPAF adds an award decided by a procedure set in advance.
- Cost plus percentage of cost lets the fee grow with cost, and the deck calls it bad for buyers everywhere.