A contract is a project-management mechanism
Read as a whole, the Week 4 deck treats the contract as the place where a project’s working relationships are decided. This page is a study-guide synthesis of the seven lessons and adds no new facts. In those terms, a contract defines six things.
- Who does the work The parties and the contract structure: a single entity or multi-prime, and how much scope each holds.
- What they must deliver The scope, set out in a statement of work clear enough to price and to check.
- How they are paid Fixed price or reimbursable, and the fee, incentive, or award on top.
- Who owns which risk Risk allocation, ideally to the party best able to manage it.
- How performance is managed Oversight by the owner, its representative, and financiers, plus incentives and award procedures agreed in advance.
- What happens when views diverge The dispute resolution clause: amicable steps first, then arbitration or litigation under a named law and jurisdiction.
From objectives to outcome
The deck’s six contracting questions tie these decisions together: what is being purchased, how complete the statement of work is, how much the buyer can manage the seller, whether to offer incentives, the market, and industry standards. One way to hold the whole week in mind is as a chain of decisions, each shaping the next.
- Project objectivesWhat is being purchased?
- ScopeHow complete is the statement of work? · Lesson 3
- Contract structureWho will do what? · Lessons 1, 2 and 5
- Payment modelFixed price or reimbursable · Lessons 3 and 4
- Risk allocationWhich party handles which risk? · Lessons 2 and 6
- ExecutionOwners, contractors, suppliers, and representatives at work · Lesson 1
- Performance, change, and dispute managementOversight, incentives, and the dispute clause · Lessons 3, 4 and 7
- Project outcomeThe asset or service the owner takes possession of
Quick reference
Use these four groups for revision. Each line links to the lesson section that teaches it.
Contract family
- Fixed price
- Defined, stable scope; cost predictability for the buyer; the seller absorbs overruns.
- Time and material
- Level of effort unknown; a fixed rate but an unknown total, capped with a not-to-exceed clause.
- Cost reimbursable
- Uncertain scope and cost; the buyer pays allowable costs, usually plus a fee or award.
Project delivery
- Design-bid-build
- The owner contracts the architect/engineer and the general contractor separately; they only communicate.
- Design-build
- One entity designs and builds, which can skip the bidding period between engineering and construction.
- Agency CM
- A fixed fee; the owner’s agent, extending the owner’s own capabilities.
- CM at risk
- The CM holds the trade contracts and usually guarantees a maximum price (GMP).
Dispute resolution
- Negotiation
- The parties settle it themselves; the simplest and fastest method.
- Mediation
- A neutral facilitator with no power to impose a decision.
- Arbitration
- A private tribunal hears both sides and delivers a binding decision.
- Litigation
- The formal court route: often lengthy, expensive, and public.
PPP models
- BOT
- Design, finance, and build, operate for a set period, then transfer to the public sector.
- DBFO
- The private firm handles nearly every aspect except ownership.
- LDO
- Lease an existing facility, upgrade it, and operate it with revenue sharing.
- Concession
- The right to operate and maintain infrastructure for a specific time.