Projects have multiple parties
Projects typically involve several key entities, each playing a distinct role in making execution succeed. The deck names six: owners, contractors, financiers, subject matter experts or consultants, suppliers, and the owner’s representative. Together they form an interconnected network, each contributing to the project through defined roles, responsibilities, and collaboration.
The project
- OwnersTake possession of the result, fund the project, and set its objectives.
- ContractorsCarry out the work to scope and schedule; paid by the owner.
- FinanciersLend the capital; expect repayment and keep oversight.
- Consultants and SMEsAdvise on technical, contractual, or financial matters; do not execute.
- SuppliersProvide materials, equipment, or services, usually for part of the scope.
- Owner’s representativeActs for the owner to oversee execution; does not replace it.
Owners
The owner is the entity that will ultimately take possession of the asset or product once the project is completed. It is also the funder, so the financial resources come from the owner. Even when a bank or other external institution provides financing, the organization executing the project with that borrowed money is still the owner.
- Owners lead the front end of the project, especially planning and initiation, and their decisions shape its scope, objectives, and strategic direction.
- Their involvement should not end there. Owners should stay engaged through planning, execution, monitoring, and closure.
- Continuous engagement keeps the project aligned with the owner’s goals, supports timely decisions and accountability, and helps protect value and prevent delays.
Key ideaOwnership is not simply about financing. The owner is the organization for which the project is ultimately being delivered, and it takes possession of the result even when a lender provides the money.
Contractors
Contractors execute the project, turning plans into reality through construction, installation, or other deliverables. They are paid by the owner, but they do not own the project or its final outcomes. Depending on the contract, a contractor may be responsible for the whole scope or only part of it, and may be involved in every phase or only some, such as construction or commissioning.
- The deck is direct about motive: contractors are there to make money out of the project, and that goal shapes how they manage time, cost, and resources.
- So owners and project teams must clearly define expectations, monitor performance, and uphold quality standards.
- Recognizing that contractors have different priorities improves contract management and aligns project goals with commercial realities.
| Owner | Contractor | |
|---|---|---|
| Relationship to the result | Takes possession of the asset or product | Does not own the project or its outcomes |
| Money | Funds the project, even with borrowed money | Is paid by the owner |
| Scope | Its decisions shape scope, objectives, and direction | May execute all or only part of the scope |
| Phases | Leads the front end and stays engaged through closure | May be involved in all or only some phases |
| Interest | Goal alignment, value, and accountability | Profit from the project |
Financiers
Financiers provide loans or debt financing for a project. They include commercial banks, investment institutions, and government-backed lenders. They do not own the project, but they are essential, especially on capital-intensive projects where the owner does not fund the whole cost upfront. They expect repayment, often with interest, once the project is completed or starts generating revenue.
- Because they bear financial risk, financiers keep some control or oversight to protect their investment.
- That oversight may mean requiring progress reports, approving major changes, and enforcing compliance with contracts and regulations.
- They are not involved in day-to-day execution, but their confidence can decide whether a project secures the funding it needs.
Subject matter experts and consultants
Subject matter experts, or SMEs, are hired by owners to give specialized, high-level advice. Their expertise may be technical, contractual, or financial, depending on the project. They may be engaged for specific phases, such as planning or execution, or throughout the project life cycle.
- They support owners in design reviews, risk assessments, cost evaluations, and contract strategies.
- Their input matters most for complex technical issues, regulatory requirements, and critical decision points.
- They do not manage or execute the work. They influence the project’s direction through expert insight, helping owners reduce risk, improve quality, and follow industry best practice.
Suppliers
Suppliers, or vendors, provide the materials and equipment a project needs. They may be contracted directly by the owner or indirectly through a contractor, depending on the procurement strategy and project structure. It is rare for one supplier to provide goods for the whole scope; most supply specific components or systems.
- Like contractors, suppliers are in business to make a profit.
- Strong commercial management and clear agreements are needed to secure their performance and value.
Long-lead items
A long-lead item is a good that takes more than a year to manufacture or deliver. For these, the deck says suppliers should be involved early in the project life cycle, during the design and engineering phases, so that specifications and lead times are aligned.
- Early supplier involvement supports timely procurement.
- It reduces the risk of schedule delays.
- It allows better integration with overall project planning.
Key ideaSupplier timing is a schedule decision. Bring long-lead suppliers in while specifications are still being set, not after the design is finished.
The owner’s representative
Owners may hire a separate entity to act on their behalf during the execution phase, known as the owner’s representative. It acts as a liaison between the owner and other stakeholders, and its main role is to protect the owner’s interests throughout the project. In engineering and construction, the owner’s representative is often called the Consultant or the Engineer.
- It may oversee schedules, budgets, quality, and contract compliance.
- It usually has technical expertise, and reviews designs, approves milestones, and coordinates contractors and suppliers.
- Its objective view helps streamline communication, reduce conflicts, and keep the project aligned with the owner’s vision, standards, and legal requirements.
Key ideaThe owner’s representative supports the owner; it does not replace it. Final decisions and responsibilities stay with the owner.
The six parties at a glance
Each party’s relationship to the owner explains a great deal about how it behaves on the project.
| Party | What it does | Relationship to the owner |
|---|---|---|
| Owner | Takes possession of the result, funds the project, and sets its objectives | The organization the project is delivered for |
| Contractor | Executes all or part of the scope | Paid by the owner; profit-driven |
| Financier | Provides loans or debt financing | Lends to the project; expects repayment and keeps oversight |
| SME or consultant | Gives technical, contractual, or financial advice | Hired by the owner; advises but does not execute |
| Supplier or vendor | Provides materials and equipment | Contracted by the owner or through a contractor; profit-driven |
| Owner’s representative | Oversees schedule, budget, quality, and compliance | Hired by the owner to act on its behalf; does not replace it |
Key takeaways
- The owner takes possession of the result and funds the project, even when the money is borrowed.
- Contractors and suppliers are paid, profit-driven parties, so expectations, performance, and quality must be defined and monitored.
- Financiers do not own the project, but their financial exposure gives them oversight.
- SMEs advise and influence; they do not manage or execute the work.
- Bring long-lead suppliers in early, during design and engineering.
- An owner’s representative acts for the owner, but final decisions remain the owner’s.