Owner

The entity that will ultimately take possession of the asset or product and that funds the project, even with borrowed money.

Review Lesson 1
Contractor

A party paid by the owner to execute all or part of the scope; it does not own the project and aims to make a profit.

Review Lesson 1
Financier

A lender, such as a bank, investment institution, or government-backed lender, that provides debt financing, expects repayment, and keeps oversight.

Review Lesson 1
Subject matter expert (SME)

A consultant hired by the owner for technical, contractual, or financial advice, who influences decisions but does not execute the work.

Review Lesson 1
Supplier

A vendor providing materials or equipment, contracted by the owner or through a contractor, usually for only part of the scope.

Review Lesson 1
Long-lead item

A good that takes more than a year to manufacture or deliver, whose supplier should be involved early, in design and engineering.

Review Lesson 1
Owner’s representative

An entity hired to act for the owner during execution, often called the Consultant or the Engineer. It does not replace the owner.

Review Lesson 1
Contract structure

The dimension of contracting that answers “who will do what?”, including single-entity or multi-prime choices.

Review Lesson 2
Multi-prime model

A structure in which responsibility is shared among several contractors instead of one accountable entity. In the design-bid-build diagram, the owner may hire multiple prime contractors instead of one general contractor.

Review Lesson 2
Prequalification

A step that allows only contractors with the necessary experience, financial capacity, and technical capability to bid.

Review Lesson 2
Sole sourcing

Awarding a contract directly to a specific contractor without competitive bidding, for example on specialized or urgent projects.

Review Lesson 2
Open invitation and limited bidding

Inviting the broader market to bid, or limiting bidding to a shortlist of pre-identified or invited contractors.

Review Lesson 2
Project risk

An uncertain event or condition that, if it materializes, impacts at least one project objective, such as scope, schedule, cost, or quality.

Review Lesson 2
Governing law and jurisdiction

What a dispute resolution clause should name if amicable efforts fail and arbitration or litigation follows.

Review Lesson 2
Statement of work (SOW)

The description of the work a seller must deliver; for fixed price contracts it must be detailed enough to price.

Review Lesson 3
Fixed price contract

A contract for a predetermined total price, in which the seller absorbs cost overruns and the buyer gains cost predictability.

Review Lesson 3
Fixed price incentive fee (FPIF)

A fixed price contract whose incentive adjusts for meeting performance criteria, such as finishing early.

Review Lesson 3
Fixed price plus award fee (FPAF)

A fixed price plus a performance award, decided by a procedure set in advance.

Review Lesson 3
Fixed price with economic price adjustment (FPEPA)

A multiyear fixed price contract that allows adjustment for economic change, such as a consumer price index or material costs.

Review Lesson 3
Graduated fixed price

An agile contract that shares schedule risk and reward through a rate that changes with early, on-time, or late delivery.

Review Lesson 3
Purchase order

The simplest fixed price contract, normally unilateral, signed by one party.

Review Lesson 3
Reimbursable contract

A contract paying actual costs incurred, usually plus a fee, used when scope is unclear; it shifts financial risk to the buyer.

Review Lesson 4
Time and material (T&M)

Payment per hour or per item for work whose level of effort can’t be defined; the rate is fixed but the total is unknown.

Review Lesson 4
Not to exceed (NTE)

A clause limiting the total amount a buyer must pay under a time and material contract.

Review Lesson 4
Allowable costs

The incurred costs a cost-reimbursable contract says the buyer will pay.

Review Lesson 4
Cost plus fixed fee (CPFF)

Actual costs plus a fee fixed before work begins, which does not vary with actual costs.

Review Lesson 4
Cost plus incentive fee (CPIF)

Actual costs plus a fee tied to performance, with a target cost and target fee, and savings or overruns shared.

Review Lesson 4
Cost plus award fee (CPAF)

Costs plus a base fee plus a performance award, with the award procedure set in advance.

Review Lesson 4
Cost plus percentage of cost

All costs plus a percentage of costs as the fee; not allowed for US federal acquisitions and, the deck says, bad for buyers everywhere.

Review Lesson 4
Design-bid-build

The traditional delivery method: the owner contracts an architect/engineer and a general contractor separately.

Review Lesson 5
Architect/engineer (A/E)

The design entity the owner hires, usually referred to as the consultant.

Review Lesson 5
Design-build

A delivery method in which one entity, a firm or joint venture, provides both design and construction.

Review Lesson 5
Trade contractor

A contractor focused on one discipline, such as electrical, mechanical, or civil work.

Review Lesson 5
Agency CM

A construction manager working for a fixed fee as the owner’s agent, extending the owner’s capabilities.

Review Lesson 5
CM at risk

A construction manager that holds the trade contracts, bears cost and schedule risk, and usually guarantees a maximum price.

Review Lesson 5
Guaranteed maximum price (GMP)

The budget within which a CM at risk guarantees to complete the project.

Review Lesson 5
Public-private partnership (PPP)

A long-term contractual collaboration in which a private partner designs, builds, finances, operates, or maintains public infrastructure or services.

Review Lesson 6
Value for money

The core PPP objective: weighing life-cycle cost, innovation, and risk transfer, not just the cheapest bid.

Review Lesson 6
Build-operate-transfer (BOT)

A PPP model in which the private partner designs, finances, builds, and operates an asset for a set period, then transfers it to the public sector.

Review Lesson 6
DBFO, LDO, and concession

PPP models in which the private firm handles nearly everything except ownership (DBFO), leases and upgrades an existing facility (LDO), or operates and maintains infrastructure for a set time (concession).

Review Lesson 6
Mediation

A voluntary, confidential, and flexible process in which a neutral mediator facilitates, but does not impose, a solution.

Review Lesson 7
Arbitration

A formal process in which a private tribunal hears both sides and delivers a binding decision.

Review Lesson 7
Litigation

The formal court route for resolving a dispute, often lengthy, expensive, and public.

Review Lesson 7
Expert determination

A method, increasingly used on software projects, in which a neutral technical expert assesses the issue.

Review Lesson 7
FIDIC

A standard form contract that the deck names as including built-in dispute resolution mechanisms.

Review Lesson 7