Where the boundary runs
The included work runs from confirming the schools and their requirements, through procurement and inspection, to domestic delivery, reconciliation, signed handover, carton recovery, financial reconciliation and sponsor acceptance. Every accepted book must be complete, legible, free from water damage and consistent with the approved educational requirements; unsuitable or damaged items do not count toward the target and must be replaced.
- Excluded: international shipment and customs, library construction or refurbishment, furniture and equipment, digital library development, translation or publishing, continuing teacher training and recurring replenishment.
- Fundraising is excluded because the sponsor provides the funding.
- Long-term library operation, maintenance and formal literacy-impact evaluation sit outside the six-week project.
- The schools own and operate the collections after handover.
Key ideaAn available budget balance does not authorize scope expansion. Additional schools, books or services require a documented change decision.
A usable collection is more than a delivery
The guide's sharpest line about scope is about evidence: a dispatch note proves that books left a supplier, but it does not prove that the right books reached the right schools, or that pupils can reach them. That is why requirements approval, physical delivery, quality verification, school ownership, access and sponsor acceptance are separated rather than bundled into one delivery target.
Six objectives, each with its evidence
All dates run from written authorization, and the six-week period is 42 calendar days. Each objective names what would prove it, which is what makes the closing acceptance decision possible.
| Objective | Due | Evidence it names |
|---|---|---|
| O1 Requirements and participation approved by the four schools and the sponsor | End of Week 1 | Approved requirements and allocation record, with the NGO's consultation notes |
| O2 Delivery and handover of 2,000 conforming books, including replacements | End of Week 5 | Inspection before dispatch, verification on receipt, signed inventories that reconcile |
| O3 All authorized obligations within USD 9,200 | End of Week 6 | Weekly record of spend, commitments and forecast; Finance verifies the closing reconciliation |
| O4 Four signed handovers with custodian, storage and pupil-access schedule | End of Week 5, verified in Week 6 | Signed handover records and the NGO's access verification |
| O5 At least 80% of transport cartons reused or recovered for reuse | End of Week 6 | A carton register with school or NGO confirmation |
| O6 Formal completion and written sponsor acceptance | End of Week 6 | The full evidence pack: inventories, quality and replacement records, handovers, access, cartons, financial statement |
What the objectives refuse to promise
The project can commit to conforming books and usable access. It cannot responsibly promise a percentage improvement in literacy within six weeks, because there is no baseline, no assessment method and no evaluation period. Future educational impact is the reason for the project; it is not claimed as an already demonstrated result.
Key ideaDelivery to a locked or inaccessible store would not meet the access objective. Handover is defined as a custodian, a storage location and an agreed pupil-access schedule.
SMART, and why achievable is conditional
The guide tests the objectives against the five SMART elements and is candid that achievability rests on assumptions still to be validated.
| Element | How the proposal demonstrates it |
|---|---|
| Specific | Identifies books, four schools, educational requirements and handover responsibilities |
| Measurable | Counts accepted books, approvals, inventories, expenditure and recovered cartons |
| Achievable | A bounded district, local sourcing and existing support, with assumptions tested before commitment |
| Relevant | Links the work to access to suitable reading materials rather than shipment volume |
| Time-bound | Week 1 approval, Week 5 delivery and handover, Week 6 verification and acceptance |
Applied choiceThe carton measure is the author's: cartons reused or recovered, divided by total cartons used, times 100. The guide's worked illustration is 40 out of 50 cartons, chosen to show the arithmetic rather than to predict how many cartons the project will use.
Acceptance comes last, and needs evidence
Closure is recommended only when every objective has supporting evidence. The schools accept their allocations, Finance verifies the cost reconciliation, and the sponsor accepts the project as a whole. Outstanding shortages, unsuitable books or missing access arrangements cannot be relabelled as successful completion; an unresolved exception is reported with its impact and a sponsor decision.
Key takeaways
- The exclusions are what keep a donation initiative from growing into an undefined programme.
- Each objective pairs a deadline with the evidence that would prove it.
- Delivery is not the same as access: a locked store fails the access objective.
- The project refuses to claim literacy improvement it cannot measure in six weeks.
- Acceptance is an evidence decision, not a volume count.