Project Management · Module 3 applied case
Applied glossary
What each term means in this proposed charter. These are applied meanings for one case; the Module 3 glossary holds the course definitions.
- Cash ceilingApplied
The maximum cash spend, USD 9,200, with contingency included.
Charter §5
Review Part 4- Base estimateApplied
The sum of the four allowances for books, packaging, transport and coordination: USD 8,000.
Charter §5
Review Part 4- Contingency reserveApplied
15% of the base, held inside the ceiling. It is released only with a recorded justification and the right approval, and unused funds stay with the sponsor.
Charter §5 · Guide §5
Review Part 4- In-kind contributionApplied
Time given without cash payment, recorded separately from the cash budget.
Charter §4 · Guide §5
Review Part 4- AllocationApplied
The agreed split of 2,000 books across the schools, set by validated need rather than equal shares.
Charter §2 · Guide §2
Review Part 1- Acceptance evidenceApplied
The records used to judge an objective: signed receipts, reconciled inventories, named custodians and documented access arrangements.
Charter §3, §9 · Guide §4
Review Part 3- CustodianApplied
The named person responsible for a school's collection after handover.
Charter §3
Review Part 3- Packaging recovery rateApplied
Cartons reused or recovered, divided by all cartons used, multiplied by 100, with each carton counted once.
Charter §3
Review Part 3- Protected deadlineApplied
Week 1 agreement and Week 6 completion, which the Project Manager's resequencing cannot move.
Charter §6
Review Part 5- Cumulative limitApplied
A cap on the total of repeated small approvals, so that they cannot get around oversight.
Charter §6
Review Part 5- Order splittingApplied
Dividing a purchase to stay under an approval limit, which the charter prohibits.
Charter §6
Review Part 5- Charter-level changeApplied
A change to the charter's fundamental commitments. It needs a written impact assessment and sponsor reauthorization.
Charter §6
Review Part 5