Project Management · Module 3 reference

Glossary

Short, source-grounded definitions to use alongside the learning path.

Project charter

The document that formally authorizes a project, developed through high-level planning in the definition phase.

Review Lesson 1
Assumptions and constraints

The key assumptions and limitations, such as time, cost, and resources, that a charter is built on.

Review Lesson 1
Business need

Why the project exists: the issue, pain point, or opportunity it addresses. Also called the problem statement.

Review Lesson 2
Scope overview

A high-level view of what the project includes and excludes.

Review Lesson 2
Approval and sign-off

The charter section where the sponsor or an executive formally authorizes the project.

Review Lesson 2
Project plan

The detailed document, owned by the project manager, that guides execution and defines the detailed WBS.

Review Lesson 2
Compass and guardrail

The deck's image for the charter keeping the team on its goals and within agreed boundaries.

Review Lesson 3
Lean Charter

The lightweight, flexible charter used on agile projects, also called a Project Canvas.

Review Lesson 3
Risk

Uncertainty: an event or condition that, if it materializes, could affect the project's ability to meet its objectives.

Review Lesson 4
Internal risk

A risk that starts within the project team or organization and is generally more controllable.

Review Lesson 4
External risk

A risk from the outside environment that is typically beyond the team's control.

Review Lesson 4
Assumption testing

Checking the project's assumptions, because any assumption that proves false may be a significant risk.

Review Lesson 4
Environmental scan

Reviewing the environment for external risks, such as market or regulatory changes, and internal ones, such as resource constraints.

Review Lesson 4
Delphi technique

Anonymous, moderator-led rounds of electronic idea generation and comment that continue until consensus.

Review Lesson 5
Risk matrix

A likelihood-by-consequence grid used at charter stage to rank risks as high, medium, or low.

Review Lesson 5
Stakeholder

Any group or individual with an interest in the project or affected by it; stakeholders can be internal or external.

Review Lesson 6
Power/interest grid

A grid that classifies stakeholders by power and interest to choose whether to actively consult, regularly engage, keep informed, or maintain interest.

Review Lesson 6
Salience model

A model that classifies stakeholders by legitimacy, power, and urgency.

Review Lesson 6
Definitive stakeholder

In the salience model, a stakeholder with legitimacy, power, and urgency, given the highest priority.

Review Lesson 6
Delegation of authority

The formal assignment of decision-making power from a higher authority to other roles, within defined limits.

Review Lesson 7
Escalation point

The threshold beyond which a decision needs approval from the sponsor or a steering committee.

Review Lesson 7
Responsibility

The obligation to complete a task or deliver an outcome.

Review Lesson 8
Authority

The right to make decisions or allocate resources to fulfil responsibilities.

Review Lesson 8
RACI chart

A chart mapping who is Responsible, Accountable, Consulted, and Informed for each activity.

Review Lesson 8