Original source guide

Week 4: The Project Contract

This map preserves the deck’s teaching sequence while the lessons provide a clearer, learner-facing explanation. Use it to trace every study topic back to the supplied source.

How to use this page

The source is the Week 4 course deck by Dr. Daoud Kiomjian, American University of Beirut. Open a lesson source note for its original teaching focus and slide range. Slide numbers are PDF page numbers, because the deck’s speaker notes run onto extra pages. The deck itself is not republished here, and its diagrams are redrawn rather than copied; distribute the original PDF only when you hold the necessary rights.

Study-guide syntheses

Two elements connect the deck’s ideas rather than quoting it: the requirements-to-dispute chain in Lesson 7 and the Week 4 summary. Both are labelled as syntheses and add no new facts. Open the Week 4 summary

Lesson 01

Different parties to a project

Six kinds of entity usually work on a project: owners, contractors, financiers, consultants, suppliers, and the owner’s representative. Each has a distinct role, relationship to the owner, and interest.

Open learner explanation
Projects have multiple parties

Six entities form an interconnected network: financiers, suppliers, owners, contractors, the owner’s representative, and consultants, each with a distinct role.

Source slides 3-5
Owners

The owner takes possession of the asset, funds the project, and remains the owner when a bank provides financing. Owners lead the front end and should stay involved through closure.

Source slides 6-8
Contractors

Contractors execute all or part of the scope, are paid by the owner, and do not own the project. They are there to make money, so owners must define expectations and monitor performance.

Source slides 9-11
Financiers

Banks, investment institutions, and government-backed lenders provide debt financing, expect repayment, and exercise oversight such as progress reports and approval of major changes.

Source slides 12-14
Subject matter experts

SMEs are hired by owners for technical, contractual, or financial advice. They influence decisions but do not manage or execute work.

Source slides 15-17
Suppliers and long-lead items

Suppliers provide materials and usually only part of the scope. Goods that take more than a year need suppliers involved early, in design and engineering.

Source slides 18-20
Owner’s representative

A separate entity acting for the owner during execution, often called the Consultant or the Engineer. It supports the owner but does not replace it.

Source slides 21-23

Lesson 02

The dimensions of contracting

Every contract answers five connected questions about structure, payment, selection, risk, and dispute resolution, and six further questions help decide what goes into it.

Open learner explanation
Five dimensions

Structure (who will do what), payment or remuneration, selection, risk allocation, and dispute resolution.

Source slide 25
Structure of the contract

Single or multiple accountable parties, how phases are distributed, and how much scope each contractor holds. Single entity or multi-prime affects risk, coordination, and accountability.

Source slides 26-28
Payment structure

Fixed price is a lump sum agreed at the outset with cost certainty for the owner. Reimbursable pays actual costs or quantities, often plus a fee, and needs more oversight.

Source slides 29-30
Selection

Prequalification, whether sole sourcing is allowed, and open invitation or limited bidding, depending on market conditions, complexity, confidentiality, and speed.

Source slides 31-33
Risk transfer

PMI’s definition of project risk, the objectives it affects, causes and conditions, the permit and personnel examples, and the question of which party handles which risk.

Source slides 34-36
Dispute resolution

The contract defines the steps: negotiation or mediation first, then arbitration or litigation with the jurisdiction and governing law.

Source slides 37-39
All of them are connected

The dimensions are distinct and interconnected, and six questions guide what goes into a contract.

Source slides 40-41

Lesson 03

The fixed price contract

A fixed price contract suits well-defined scope, gives the buyer cost predictability, and shifts the risk of cost overruns to the seller. It comes in six forms, from firm fixed price to the purchase order.

Open learner explanation
When fixed price fits

Well-defined specifications, a clear statement of work, and a faster bid. Common in construction and manufacturing, less likely in IT. The seller absorbs cost overruns.

Source slides 43-45
What if the scope is not well defined?

An insufficient statement of work leads to claims and disputes over what is in and out, and a higher risk of overruns or delay. The types of fixed price contract are listed.

Source slides 46-47
Fixed price

A set total price regardless of actual cost; example $1,100,000.

Source slides 48-49
FPIF and FPAF

Incentives for faster, cheaper, or better work ($10,000 a month early), and an award fee ($5,000 a month above plan by more than 15%, up to $50,000) with the procedure set in advance.

Source slides 50-53
FPEPA

A year-two price increase based on the US Consumer Price Index or specific material costs, for multiyear contracts with uncertain economic conditions.

Source slide 54
Graduated fixed price

An agile contract sharing schedule risk and reward: early $110, on time $110, late $90 per hour. The slide title reads Guaranteed Fixed Price.

Source slides 55-56
Purchase order

The simplest fixed price contract, normally unilateral; example 30 linear meters of wood at $9 per meter.

Source slide 57

Lesson 04

Variable price contracts

When scope or effort can’t be defined up front, reimbursable contracts pay for actual time, materials, or costs, through time and material or the cost-reimbursable forms, and shift financial risk to the buyer.

Open learner explanation
Reimbursable contracts

Actual costs plus a fee or profit, used when scope is unclear. Two types, time and material and cost reimbursable, both shift financial risk to the client.

Source slides 59-60
Time and material

Per-hour or per-item payment when the level of effort can’t be defined; examples at $100 per hour; a not-to-exceed clause limits the total.

Source slides 61-64
Cost reimbursable

Allowable incurred costs plus a fee or award; six types listed.

Source slides 65-66
Cost and CPFF

A cost contract pays no fee and suits nonprofits. CPFF adds a fee fixed before work begins, for example $100,000.

Source slides 67-68
CPIF and CPAF

CPIF sets a target cost and target fee and shares savings or overruns. CPAF adds a base fee and an award, with a maximum of $50,000 in the example.

Source slides 69-71
Cost plus percentage of cost

Costs plus a percentage of costs, for example 10%. Not allowed for US federal acquisitions, and bad for buyers everywhere.

Source slide 72

Lesson 05

Contracting for engineers

Engineering and construction projects are delivered through design-bid-build, design-build, or professional construction management, including agency CM and CM at risk with a guaranteed maximum price.

Open learner explanation
Traditional delivery method

The owner contracts an architect/engineer and a general contractor or multiple prime contractors; there is no contract between the builder and the architect/engineer.

Source slide 74
Design-build

One entity provides design and construction, in the interest of schedule; negotiated or competitive selection; a design-build firm or joint venture that hires subcontractors.

Source slides 75-77
Professional CM contract

The owner hires a construction manager to oversee trade contractors, with no contract between the CM and the architect/engineer.

Source slides 78-79
How CM works

Hired on qualifications before construction; develops bid documents, supervises construction, controls information, and mediates conflicts.

Source slides 80-81
Agency CM

Fixed fee, the owner’s agent, service from on-call advice to full project management, sometimes hired before design.

Source slides 82-83
CM at risk

Contracts with the trade contractors, a guaranteed maximum price, two-stage contracting, and popular with private owners.

Source slides 84-85

Lesson 06

Public-private partnerships

In a public-private partnership, a private partner takes long-term responsibility for designing, building, financing, operating, or maintaining public infrastructure or services, with risk shared and payment tied to performance.

Open learner explanation
Understanding PPPs

Long-term collaboration between public and private sectors; the private entity designs, builds, finances, operates, or maintains public infrastructure; the toll road example.

Source slides 87-88
Key features

Risk sharing, long-term contracts of often 15 to 30 years, performance-based payments, and value for money.

Source slides 89-90
Common PPP models

Build-operate-transfer, design-build-finance-operate, lease-develop-operate, and concessions.

Source slides 91-92
Benefits

Faster delivery, private capital, innovation and service quality, and enhanced risk management, when well executed.

Source slides 93-94
Risks and challenges

Complex negotiation, overruns or delays, regulatory and political risk, and public resistance or lack of transparency.

Source slides 95-96
Success factors

A clear legal framework, transparent competitive bidding, effective risk allocation to the party best able to manage it, and strong contract management.

Source slides 97-98
Closing video notes

PPPs are promising but not a universal solution; the key is aligned incentives, transparency, and strong oversight.

Source slides 99-100

Lesson 07

Dispute resolution

Disputes grow out of ambiguity, delay, cost, scope change, and misunderstanding. Negotiation, mediation, arbitration, and litigation resolve them with rising formality, and mediation often protects the relationship.

Open learner explanation
Why disputes arise

Ambiguity, delays, cost overruns, scope changes, miscommunication, unmet expectations, and cultural or legal differences.

Source slides 102-103
Common methods

Negotiation, mediation, arbitration, and litigation, from informal to formal.

Source slides 104-105
Construction disputes

Schedule delays, design variations, and payment disagreements; FIDIC mechanisms escalate from amicable settlement to arbitration or litigation.

Source slides 106-107
Humanitarian disputes

Donors, implementing partners, and local NGOs under time pressure; mediation and negotiation are preferred.

Source slides 108-109
Software disputes

Functionality gaps, delays, intellectual property, agile misalignment, and scope creep; mediation and expert determination are favored.

Source slides 110-111
Mediation and its benefits

Voluntary, confidential, and flexible; the mediator facilitates rather than imposes; relationships, confidentiality, cost, speed, and creative solutions.

Source slides 112-115

Source appendix

Where the deck needs a careful reading

Read with care

Guaranteed or graduated fixed price

Slide 55 is titled “Guaranteed Fixed Price,” while its notes define “Graduated Fixed Price.” The notes say an early finish earns a higher rate, but the example gives $110 per hour for both early and on-time finishes. The lesson uses the notes’ term and shows both.

The incentive fee example

The example on slide 69, cost plus incentive fee, repeats the award fee example on slide 70 word for word. Only the notes describe target cost, target fee, and shared savings or overruns, so the lesson teaches the notes.

The award fee penalty sentence

The notes on slides 70-71 say the incentive is “a potential penalty with no possibility of a penalty,” which contradicts itself. The rest of the slide describes the award as a bonus. The lesson quotes the sentence rather than choosing a reading.

Does every reimbursable contract include a fee?

Slide 59 says reimbursable contracts pay costs plus an additional fee or profit, but the cost contract on slide 67 pays no fee.

Where time and material belongs

Slide 59 places time and material under reimbursable contracts, while slide 61 says it has elements of both fixed price and cost-reimbursable contracts. The lessons show both.

The fixed price list

The list of fixed price types on slide 46 omits graduated fixed price, which slides 55-56 then teach.

Owner-led delivery

The notes on slide 75 say owner-led delivery and design-bid-build have been covered, but no earlier slide covers owner-led delivery. The same notes call design-build a less common method.

How fast is arbitration?

Slide 105 says arbitration is commonly used in construction and software contracts for its confidentiality and speed. Slide 111 says that, on software projects, arbitration and litigation can be expensive and slow.

Humanitarian contracting

Lesson 6 is titled “Public Private Partnerships (Humanitarian Contracting),” but its slides describe government infrastructure and service partnerships. Humanitarian disputes are taught in Lesson 7.

Mediation statistics

Slide 115 says “studies show” a high percentage of commercial mediations end in full or partial resolution, without naming a study or giving a figure. The lesson reports the claim as the deck’s and adds no numbers.

Illustrative numbers and wording

Dollar amounts, rates, and percentages are the deck’s examples, not benchmarks. Typing slips in the deck, such as “renumeration” and “seeler,” are corrected without changing meaning.

Checked against the source slides cited in each note.

What not to take away

The lessons actively work against these misreadings of the material:

  • Whoever lends the money owns the project.
  • The owner’s representative can take the owner’s final decisions.
  • Consultants and SMEs execute the work they advise on.
  • Suppliers can wait until design is finished, whatever the lead time.
  • The five dimensions of contracting can be decided one at a time.
  • A fixed price protects the buyer even when the statement of work is vague.
  • A time and material contract has a known total cost.
  • Cost plus percentage of cost rewards the seller for controlling cost.
  • In design-bid-build, the contractor works under the architect/engineer’s contract.
  • A construction manager holds a contract with the architect/engineer.
  • PPP benefits are guaranteed once a private partner is involved.
  • Value for money means choosing the cheapest bid.
  • Every dispute passes through negotiation, mediation, arbitration, and litigation in turn.
  • A mediator decides who is right.

Study-guide synthesis; each item is addressed in the lessons.