Project Management · Module 7 · Applied case reference

Applied glossary

Terms as this estimate uses them. Where a term is the author's own choice rather than course vocabulary, the source line says so.

Cost sheet

Submission

The completed table the brief asks for: materials, labour, management and overhead, and a total for each activity.

Review Part 1
Bottom-up build

Submission · Deck pp. 33-34

Estimating each activity separately and summing the results, so a change can be traced to one row.

Review Part 1
Stated assumption

Guide · applied choice

A quantity, price, crew size or rate the brief does not supply, declared openly by the author.

Review Part 1
Footprint

Submission · scope · applied choice

The 8 m by 5 m garden, four 2 m by 1 m beds, fencing and two benches that the quantities are based on.

Review Part 2
Exclusion

Submission · resources and exclusions

Work stated as outside the estimate, such as drainage, utilities, hazardous waste and long-term maintenance.

Review Part 2
Material takeoff

Submission · Deck p. 25

The list of items, quantities and rates behind each activity’s materials.

Review Part 3
Double counting

Guide · materials

Paying for the same item in two activities; avoided by placing the soil in B only and saying what each kit excludes.

Review Part 3
Exercise rate

Submission · Guide

An assumed price used for the assignment, to be replaced by a current quotation on a real project.

Review Part 3
Worker-day

Brief · Submission

One worker paid for one day at £100. A measure of effort, not of calendar time.

Review Part 4
Overhead rate

Submission · applied choice

12% of materials plus labour, applied once to each activity, within the brief’s 10% to 15%.

Review Part 4
Row and column check

Guide · how to check

Confirming that the row totals and the column totals reach the same grand total.

Review Part 5
Ripple of a change

Guide · how to check

Each pound of direct cost carries 12 pence of overhead, so £100 more becomes £112.

Review Part 5
Contingency

Submission · applied choice

A separate reserve for uncertainty, here an optional 10% of £431.20, outside the required total.

Review Part 6
Commitment

Submission · control

A purchase agreed but not yet paid, recorded against its activity alongside receipts.

Review Part 6