Project Management · Module 7 · Applied case reference
Applied glossary
Terms as this estimate uses them. Where a term is the author's own choice rather than course vocabulary, the source line says so.
- Cost sheet
Submission
The completed table the brief asks for: materials, labour, management and overhead, and a total for each activity.
Review Part 1- Bottom-up build
Submission · Deck pp. 33-34
Estimating each activity separately and summing the results, so a change can be traced to one row.
Review Part 1- Stated assumption
Guide · applied choice
A quantity, price, crew size or rate the brief does not supply, declared openly by the author.
Review Part 1- Footprint
Submission · scope · applied choice
The 8 m by 5 m garden, four 2 m by 1 m beds, fencing and two benches that the quantities are based on.
Review Part 2- Exclusion
Submission · resources and exclusions
Work stated as outside the estimate, such as drainage, utilities, hazardous waste and long-term maintenance.
Review Part 2- Material takeoff
Submission · Deck p. 25
The list of items, quantities and rates behind each activity’s materials.
Review Part 3- Double counting
Guide · materials
Paying for the same item in two activities; avoided by placing the soil in B only and saying what each kit excludes.
Review Part 3- Exercise rate
Submission · Guide
An assumed price used for the assignment, to be replaced by a current quotation on a real project.
Review Part 3- Worker-day
Brief · Submission
One worker paid for one day at £100. A measure of effort, not of calendar time.
Review Part 4- Overhead rate
Submission · applied choice
12% of materials plus labour, applied once to each activity, within the brief’s 10% to 15%.
Review Part 4- Row and column check
Guide · how to check
Confirming that the row totals and the column totals reach the same grand total.
Review Part 5- Ripple of a change
Guide · how to check
Each pound of direct cost carries 12 pence of overhead, so £100 more becomes £112.
Review Part 5- Contingency
Submission · applied choice
A separate reserve for uncertainty, here an optional 10% of £431.20, outside the required total.
Review Part 6- Commitment
Submission · control
A purchase agreed but not yet paid, recorded against its activity alongside receipts.
Review Part 6