Quantity times price
Week 7 defines a material takeoff as a list of materials, with quantities and types, required to build a structure. The submission uses a small takeoff for each activity, so each allowance can be traced to an item, a quantity and an assumed rate.
| Activity | Items: quantity × assumed rate | Materials |
|---|---|---|
| A · Site preparation | Path membrane 20 m² × £2 = £40 · waste sacks 10 × £3 = £30 · pegs and marking 1 × £30 = £30 | £100 |
| B · Build raised beds | Timber-only bed kits 4 × £120 = £480 · liners 4 × £10 = £40 · fixing packs 4 × £15 = £60 · soil and compost 2.4 m³ × £75 = £180 | £760 |
| C · Install fencing | Mesh 25 m × £8 = £200 · posts 14 × £15 = £210 · 1 m gate and hinges 1 × £160 = £160 · post-mix 10 × £5 = £50 · fixings 1 × £30 = £30 | £650 |
| D · Create seating area | Flat-pack benches 2 × £175 = £350 · paving support pads 10 × £5 = £50 · gravel 0.5 tonnes at £80 a tonne = £40 · anchoring fixings 1 × £10 = £10 | £450 |
| E · Planting | Seed packets 10 × £3 = £30 · seedlings 30 × £2 = £60 · mulch 8 bags × £10 = £80 · labels and ties 1 × £20 = £20 | £190 |
| F · Project supervision | No new materials; existing record forms and equipment are used | £0 |
| Total | £2,150 |
Read with careEvery line was recomputed and matches. The submission writes the gravel line as “0.5 tonnes × £80 = £40”: £80 is the rate per tonne.
One activity, line by line
The guide works through activity B, the raised beds, as its example.
| Item | Calculation | Cost |
|---|---|---|
| Timber-only bed kits | 4 × £120 | £480.00 |
| Bed liners | 4 × £10 | £40.00 |
| Bed fixing packs | 4 × £15 | £60.00 |
| Soil and compost blend | 2.4 m³ × £75 | £180.00 |
| B materials total | £480 + £40 + £60 + £180 | £760.00 |
Paying for each item once
The soil and bed filling sit in B, the raised beds. Planting, E, contains only seeds, seedlings, mulch, labels and ties. The guide gives the reason: this prevents the same soil from being paid for twice.
- The timber-only kits exclude liners and fixings, which are priced separately.
- The gate kit excludes the posts and fixings, which are priced in their own lines.
- Supervision, F, buys no new materials, because existing record forms and equipment are used.
Key ideaSaying what each line excludes is how a takeoff avoids double counting.
Equipment or bulk?
Lesson 2’s material categories fit the garden loosely. Benches and a gate kit are the nearest things to equipment: bought as finished units. Mesh, posts, post-mix, soil and gravel behave like bulk materials, priced by length, volume or weight. This is a study connection drawn by this case; neither document makes it.
Assumed prices, not quotations
Lesson 3’s best practice asks for recent quotes, and firm vendor quotes for significant items. The submission is open that its prices are exercise rates, assumed to include delivery and any applicable taxes. The guide says that on a real project they would be replaced by current quotations and checked specifications.
Applied choiceEvery rate in the takeoff, from £2 a square metre of membrane to £175 a bench, is the author’s assumption.
Read with careThis is the main gap between the exercise and the deck’s best practice. The submission names it, and makes confirming quotations the first step of its control plan in Part 6.
Key takeaways
- Materials total £2,150, built from quantities and assumed rates.
- Activity B is £480 + £40 + £60 + £180 = £760.
- The soil sits in B only, so it is not paid for twice.
- Each line says what it excludes.
- The prices are assumptions; a real estimate would use current quotations.