Six best practices
Engineering documents go through several revisions, so the deck’s first rule is to estimate from the most recent ones. The rest follow from the same idea: estimate from real, current evidence.
- Base estimates on the latest engineering documents.
- Base estimates on material takeoffs from those documents.
- Use recent quotes, and price significant items such as equipment from firm vendor quotes.
- Take labour rates from recent market data, and productivities from historical project data.
- Avoid using factors as much as possible.
- Remember that accurate estimates make the project easier to control later, which saves effort.
What the estimate needs
Several inputs feed the estimation process. The scope and schedule baselines define the deliverables and the timeline. The registers bring lessons and risks from earlier work, and the rest ground the estimate in current prices.
- Plans and registersScope and schedule baseline, lessons learned register, risk register, resource requirements
- History and marketHistorical records and templates, marketplace conditions, commercial cost databases, exchange rate and inflation
- The estimation process
- Cost estimate
Top-down analogous estimation
Top-down estimation starts with an estimate for the whole project and then moves down to the activities. It is usually used early in the project, because it is less accurate. It is easy and cheap to create, but it needs considerable experience and leaves out significant project characteristics.
| Advantages | Disadvantages |
|---|---|
| Quick | Less accurate |
| Activities do not need to be identified | Reflects limited information about the project or its key deliverables |
| Less costly to create | Requires considerable experience to do well |
| Gives early data to evaluate high-level feasibility | There may be infighting for the biggest share of the budget without justifying the need |
| Caps the overall project cost | Difficult with uncertainty, or without similar projects to reference |
| Does not consider differences between projects |
Bottom-up estimation
Bottom-up estimates are developed as the project is refined. They are more accurate because they rely on more detail, but they take considerable time and need a project that is well understood.
Top down, analogous
- Starts from
- The whole project, then moves down
- When
- Early stages
- Accuracy
- Lower
- Effort
- Quick and cheap, but needs experience
Bottom up
- Starts from
- Each activity, then adds up
- When
- As the project is refined
- Accuracy
- Higher
- Effort
- Takes time and money; needs a defined project
| Advantages | Disadvantages |
|---|---|
| More accurate, using analogous, three-point or parametric estimates at the activity level | Takes time and money |
| Gains buy-in, because the team creates estimates it can live with | The team tends to pad estimates unless it understands reserves |
| Based on a detailed analysis of the project and its deliverables | Requires the project to be defined and well understood |
| Provides a basis for control and management | Takes time to break the deliverables into similar pieces |
Exercise: what else do you need?
The deck prices a two-floor house in a quiet Lebanese village. It lists quantities of concrete, stone, tiling, doors, lighting and plumbing fixtures, cables, conduits, piping, glazing and aluminium, an elevator and six air conditioning units, each with a unit price in dollars at 1,500 Lebanese pounds to the dollar. Then it asks what else you would need to know.
- The prevailing wage rate: the exercise gives only material costs, and no labour.
- The exchange rate risk: at 12,000 pounds to the dollar, the notes say, the entire estimate must be revalidated.
Read with careThe deck gives no total, and several quantities are ambiguous, such as whether the stone and tiling areas are per floor and how the cable and conduit lengths split. The point is what is missing, not the sum.
Key takeaways
- Estimate from the latest documents, takeoffs, recent and firm quotes, market labour rates and historical productivity.
- Avoid factors where real quantities and prices are available.
- Inputs include the scope and schedule baselines, the registers, resource needs, history, market conditions, cost databases, exchange rates and inflation.
- Top down is quick and early but less accurate; bottom up is accurate and controllable but slow.
- An estimate without labour rates, or with an exchange rate that moves, is not finished.