Project Management · Module 7Lesson 5

Study explanation · Lesson 05 · 22 min

Project controls fundamentals

Control tracks time, money, resources, materials and tasks, not cost alone. This lesson covers when to monitor, and the earned value method: planned value, earned value and actual cost, the variances and indices built from them, and the forecasts of the final cost.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

What project control tracks

Project control does not focus only on cost; it also covers schedule, quality and resources. It shows the project’s progress, whether changes are needed, and whether any variation orders are required.

Project controls and monitoring · Source slide 52

Inputs

  • Time
  • Money
  • Resources
  • Material usage
  • Tasks

Outputs

  • Progress and costs
  • Job starts and job completion
  • Engineering and design changes
  • Quality and technical performance
  • Variation orders

Read with careThe notes say control “does only focus on cost but” also covers the rest. The sense is “does not only focus on cost”.

When to monitor

Monitoring can run at different frequencies and levels of detail, depending on the project’s needs and where it is in its life cycle. The deck lists eight moments.

  • At the end of the project, to assess overall performance.
  • Continuously and regularly, for ongoing oversight.
  • Logically, in line with the project’s structure and workflow.
  • While there is still time to react, and as soon as possible when issues arise.
  • At task completion, and at pre-planned decision points, the milestones.

Key ideaMonitoring is only useful while there is still time to act on what it shows.

The earned value method

The earned value method, EVM, is the most common way to measure project progress. The Project Management Institute (2008) defines it as a method for integrating scope, schedule and resources and measuring project performance. It compares the work planned with the work actually earned and the money actually spent, to see whether cost and schedule performance are as planned. Moreira and Figueiredo (2012) call it the most adequate method for tracking project status and forecasting final duration and cost.

Key ideaFor tasks in progress, earned value is the estimated percentage of physical completion multiplied by the planned cost of the task. The result is what should have been spent on the work so far, which can be compared with what was actually spent.

Three values

Every earned value calculation starts from three elements of data, each with an older name in brackets.

The three elements of earned value · Source slides 57 and 62

Planned value · PV

Older name
BCWS, budgeted cost of work scheduled
Asks
What should be done by now?
Is
The budget for the work scheduled to date

Earned value · EV

Older name
BCWP, budgeted cost of work performed
Asks
What has actually been done?
Is
The budget for the work completed: percent complete × the work’s budget

Actual cost · AC

Older name
ACWP, actual cost of work performed
Asks
What has it cost?
Is
The money actually spent on that work

Read with careSlide 57 writes EV as planned value times percent complete; slide 62 uses percent complete times the budget at completion. They agree when the planned value is the work’s full budget, as in Lesson 6’s first example, where the work was due to finish today. These lessons use the budget of the work.

Variances and indices

Four metrics compare the three values. Variances show the gap in money; indices show efficiency as a ratio.

Earned value metrics · Source slides 58-60 and 62
MetricFormulaReading
Cost variance (CV)EV − ACNegative: over budget. Positive: under budget
Schedule variance (SV)EV − PVNegative: behind schedule. Positive: ahead of schedule
Cost performance index (CPI)EV ÷ ACAbove 1: cost efficient
Schedule performance index (SPI)EV ÷ PVAbove 1: ahead of schedule

Forecasting the final cost

Three more terms look forward to the end of the project.

  • Budget at completion (BAC) How much was budgeted for the total job.
  • Estimate at completion (EAC) What the total project is currently expected to cost. EAC = BAC ÷ CPI.
  • Estimate to complete (ETC) How much more is expected to be spent. ETC = EAC − AC.

Key ideaThe deck gives one formula for EAC. Dividing the budget by the CPI projects today’s cost efficiency onto the rest of the work.

All the terms together

Slide 62 gathers the terms in one table and stresses that three elements of data are needed to analyse performance: the budgeted cost of work scheduled, the budgeted cost of work performed, and the actual cost of work performed.

Earned value terms · Source slide 62
TermFormulaInterpretation
BCWS (PV)Work load × BACThe share of the budget planned to be spent at a point in time; the performance measurement baseline
BCWP (EV)% completed work × BACA measure of the project’s physical progress
ACWP (AC)RecordedThe money spent on completed work at some stage
CV and SVBCWP − ACWP; BCWP − BCWSCV below 0 is over budget; SV below 0 is behind schedule
CPI and SPIBCWP ÷ ACWP; BCWP ÷ BCWSEarned value against actual cost; against planned value
EACBAC ÷ CPIA prediction of total cost, which may differ from BAC
ETCEAC − ACWPThe expected extra cost to finish
ETC (t)Planned duration ÷ SPIA prediction of the final duration, which may differ from the planned duration

Read with careThe deck labels ETC (t) “estimated time to completion”, but its own interpretation describes the predicted final duration.

Key takeaways

  • Control covers schedule, quality and resources as well as cost.
  • Monitor regularly, at milestones, and while there is still time to react.
  • PV is the work planned, EV the work done valued at its budget, AC the money spent.
  • CV = EV − AC and SV = EV − PV; negative means over budget or behind.
  • CPI = EV ÷ AC and SPI = EV ÷ PV; above 1 is good.
  • EAC = BAC ÷ CPI forecasts the total; ETC = EAC − AC is what is left to spend.

Study explanation based on the supplied Week 7: Costing and Control source deck. Open the source notes above for slide-level traceability.