What project control tracks
Project control does not focus only on cost; it also covers schedule, quality and resources. It shows the project’s progress, whether changes are needed, and whether any variation orders are required.
Inputs
- Time
- Money
- Resources
- Material usage
- Tasks
Outputs
- Progress and costs
- Job starts and job completion
- Engineering and design changes
- Quality and technical performance
- Variation orders
Read with careThe notes say control “does only focus on cost but” also covers the rest. The sense is “does not only focus on cost”.
When to monitor
Monitoring can run at different frequencies and levels of detail, depending on the project’s needs and where it is in its life cycle. The deck lists eight moments.
- At the end of the project, to assess overall performance.
- Continuously and regularly, for ongoing oversight.
- Logically, in line with the project’s structure and workflow.
- While there is still time to react, and as soon as possible when issues arise.
- At task completion, and at pre-planned decision points, the milestones.
Key ideaMonitoring is only useful while there is still time to act on what it shows.
The earned value method
The earned value method, EVM, is the most common way to measure project progress. The Project Management Institute (2008) defines it as a method for integrating scope, schedule and resources and measuring project performance. It compares the work planned with the work actually earned and the money actually spent, to see whether cost and schedule performance are as planned. Moreira and Figueiredo (2012) call it the most adequate method for tracking project status and forecasting final duration and cost.
Key ideaFor tasks in progress, earned value is the estimated percentage of physical completion multiplied by the planned cost of the task. The result is what should have been spent on the work so far, which can be compared with what was actually spent.
Three values
Every earned value calculation starts from three elements of data, each with an older name in brackets.
Planned value · PV
- Older name
- BCWS, budgeted cost of work scheduled
- Asks
- What should be done by now?
- Is
- The budget for the work scheduled to date
Earned value · EV
- Older name
- BCWP, budgeted cost of work performed
- Asks
- What has actually been done?
- Is
- The budget for the work completed: percent complete × the work’s budget
Actual cost · AC
- Older name
- ACWP, actual cost of work performed
- Asks
- What has it cost?
- Is
- The money actually spent on that work
Read with careSlide 57 writes EV as planned value times percent complete; slide 62 uses percent complete times the budget at completion. They agree when the planned value is the work’s full budget, as in Lesson 6’s first example, where the work was due to finish today. These lessons use the budget of the work.
Variances and indices
Four metrics compare the three values. Variances show the gap in money; indices show efficiency as a ratio.
| Metric | Formula | Reading |
|---|---|---|
| Cost variance (CV) | EV − AC | Negative: over budget. Positive: under budget |
| Schedule variance (SV) | EV − PV | Negative: behind schedule. Positive: ahead of schedule |
| Cost performance index (CPI) | EV ÷ AC | Above 1: cost efficient |
| Schedule performance index (SPI) | EV ÷ PV | Above 1: ahead of schedule |
Forecasting the final cost
Three more terms look forward to the end of the project.
- Budget at completion (BAC) How much was budgeted for the total job.
- Estimate at completion (EAC) What the total project is currently expected to cost. EAC = BAC ÷ CPI.
- Estimate to complete (ETC) How much more is expected to be spent. ETC = EAC − AC.
Key ideaThe deck gives one formula for EAC. Dividing the budget by the CPI projects today’s cost efficiency onto the rest of the work.
All the terms together
Slide 62 gathers the terms in one table and stresses that three elements of data are needed to analyse performance: the budgeted cost of work scheduled, the budgeted cost of work performed, and the actual cost of work performed.
| Term | Formula | Interpretation |
|---|---|---|
| BCWS (PV) | Work load × BAC | The share of the budget planned to be spent at a point in time; the performance measurement baseline |
| BCWP (EV) | % completed work × BAC | A measure of the project’s physical progress |
| ACWP (AC) | Recorded | The money spent on completed work at some stage |
| CV and SV | BCWP − ACWP; BCWP − BCWS | CV below 0 is over budget; SV below 0 is behind schedule |
| CPI and SPI | BCWP ÷ ACWP; BCWP ÷ BCWS | Earned value against actual cost; against planned value |
| EAC | BAC ÷ CPI | A prediction of total cost, which may differ from BAC |
| ETC | EAC − ACWP | The expected extra cost to finish |
| ETC (t) | Planned duration ÷ SPI | A prediction of the final duration, which may differ from the planned duration |
Read with careThe deck labels ETC (t) “estimated time to completion”, but its own interpretation describes the predicted final duration.
Key takeaways
- Control covers schedule, quality and resources as well as cost.
- Monitor regularly, at milestones, and while there is still time to react.
- PV is the work planned, EV the work done valued at its budget, AC the money spent.
- CV = EV − AC and SV = EV − PV; negative means over budget or behind.
- CPI = EV ÷ AC and SPI = EV ÷ PV; above 1 is good.
- EAC = BAC ÷ CPI forecasts the total; ETC = EAC − AC is what is left to spend.