Project Management · Module 7Lesson 4

Study explanation · Lesson 04 · 18 min

Estimate accuracy

Estimates are graded by how much of the project is defined when they are made. The AACE classes run from class 5, a concept screening estimate made in under an hour, to class 1, a detailed check estimate for parts of the project. The right class depends on the decision the estimate supports.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Grading the quality of an estimate

Like technical standards, the industry has categories for the quality of cost estimates. Among the most popular are the classes of the Association for the Advancement of Cost Engineering, AACE. It defines five classes, depending on the basis used to prepare an estimate and its accuracy. AACE also offers certificates in cost estimation.

The five AACE classes

As the project is defined, there is more information about it, so more detailed estimates become possible. Class 1 is the most accurate and class 5 the most high level.

From screening to checking · Study-guide arrangement of source slide 39

Little defined, wide range

  1. Class 5Concept screening
  2. Class 4Study or feasibility
  3. Class 3Budget authorization
  4. Class 2Control or bid
  5. Class 1Check estimate or bid

Fully defined, narrow range

AACE estimate classes · Source slide 39
ClassProject definitionEnd usageMethodologyExpected accuracy
Class 50% to 2%Concept screeningCapacity factored, parametric models, judgment, or analogyLow −20% to −50%; high +30% to +100%
Class 41% to 15%Study or feasibilityEquipment factored or parametric modelsLow −15% to −30%; high +20% to +50%
Class 310% to 40%Budget, authorization, or controlSemi-detailed unit costs with assembly-level line itemsLow −10% to −20%; high +10% to +30%
Class 230% to 70%Control or bid and tenderDetailed unit costs with forced detailed takeoffLow −5% to −15%; high +5% to +20%
Class 150% to 100%Check estimate or bid and tenderDetailed unit costs with detailed takeoffLow −3% to −10%; high +3% to +15%

Read with careProject definition is expressed as a percentage of complete definition. The ranges overlap as the table prints them.

Class 5 and class 4: screening and feasibility

The two least defined classes support early decisions about whether a project is worth pursuing.

  • Class 5 Prepared from very limited information, so the accuracy range is wide. Some organizations decline to classify such estimates at all. It may take less than an hour, when little more than the proposed plant type, location and capacity is known.
  • Class 4 Prepared from limited information, with fairly wide ranges. Used for screening, feasibility, concept evaluation and preliminary budget approval. Engineering is typically 1% to 15% complete: capacity, block schematics, an indicated layout, process flow diagrams for the main systems, and preliminary equipment lists.

Class 3 and class 2: budget and control

The middle classes are the ones a project is funded and controlled against.

  • Class 3 The basis for budget authorization, appropriation or funding, and typically the initial control estimate against which all actual costs and resources are monitored. Engineering is 10% to 40% complete.
  • Class 2 A detailed control baseline for monitoring all project work in cost and progress. For contractors it is often the bid estimate that sets the contract value. Engineering is 30% to 70% complete, including vendor quotations, detailed execution plans and workforce plans.

Class 1: checking the parts

Class 1 estimates are usually prepared for discrete parts of a project rather than the whole. Subcontractors use them for bids, and owners use them as check estimates. Engineering is 50% to 100% complete.

  • The updated estimate is often called the current control estimate, and becomes the new baseline for cost and schedule control.
  • It can serve as a fair price or bid check estimate against a contractor’s bid, or to evaluate or dispute claims.

Class 1 is not always the answer

A more accurate estimate costs more time and information to prepare. If the team is only assessing a project’s viability or feasibility, a class 5 or class 4 estimate is sufficient.

Key ideaMatch the class to the decision: screening needs speed, funding needs a control estimate, and a bid needs detail.

Key takeaways

  • AACE grades estimates into five classes by how much of the project is defined.
  • Class 5 screens concepts in hours; class 4 supports feasibility; class 3 authorizes budgets; class 2 sets the control baseline or bid; class 1 checks parts.
  • Accuracy narrows from as wide as −50% to +100% at class 5 to −3% to +15% at its best at class 1.
  • The right class depends on the decision; class 1 is not always needed.

Study explanation based on the supplied Week 7: Costing and Control source deck. Open the source notes above for slide-level traceability.

Your study checkpoint

Ready to continue?

Mark the lesson complete after you have read, reflected, and tested the main idea.

Next · Lesson 5