Control starts with the estimate
Read as a whole, the Week 7 deck treats cost control as the second half of a job whose first half is estimating well. This page is a study-guide synthesis of the six lessons and adds no new facts. In those terms, managing cost means answering six questions.
- What must we know first Lesson 1 asks about financing, equipment funding, economic calculations and local content, and sets the cost management plan.
- What kind of cost is it Lesson 2 sorts costs by source and variability, and materials into equipment and bulk.
- How do we estimate it Lesson 3 sets best practice and chooses between top down and bottom up.
- How good is the estimate Lesson 4 grades it with the AACE classes, matched to the decision.
- How do we measure progress Lesson 5 defines PV, EV and AC, the variances, the indices and the forecasts.
- What is the status today Lesson 6 builds the S-curve baseline and reads the project against it.
From questions to control
One way to hold the whole week in mind is as a chain, each step feeding the next. The chain loops: a forecast that runs over the budget sends the team back to the estimate, the plan and its change control.
- Settle the money and the rulesFinancing, equipment, economics, local content · Lesson 1
- Cost management planCurrency, accuracy, baseline, thresholds, roles · Lesson 1
- Categorize the costsDirect or indirect, fixed or variable, equipment or bulk · Lesson 2
- EstimateBest practice, top down or bottom up · Lesson 3
- Grade the estimateThe AACE class that fits the decision · Lesson 4
- MeasurePV, EV, AC; variances, indices, forecasts · Lesson 5
- Read and actThe S-curve baseline and the status today · Lesson 6
Quick reference
Use these four groups for revision. Each line links to the lesson section that teaches it.
Before and around the estimate
- Three questions
- Financing mix, equipment funding, economic calculations.
- Local content
- Local sourcing and hiring rules change labour and material costs.
- Cost management plan
- Currency, accuracy, techniques, baseline, thresholds, change control, roles.
- Do not forget
- Quality, risk, management, space, overhead, contingency, escalation.
Categories and methods
- Direct or indirect
- Attributable to the work, or shared overhead; the PM’s salary is direct.
- Fixed or variable
- Unchanged by production, or changing with it.
- Takeoff and quotation
- Quantities to build; a priced offer with a validity.
- Top down or bottom up
- Quick and early, or detailed and controllable.
Accuracy
- Class 5
- 0% to 2% defined; concept screening; −50% to +100% at worst.
- Class 3
- 10% to 40% defined; budget authorization; initial control estimate.
- Class 1
- 50% to 100% defined; check estimates for parts of the project.
- Fit for purpose
- Feasibility needs class 5 or 4, not class 1.
Earned value
- PV, EV, AC
- Work planned, work done at budget, money spent.
- CV and SV
- EV − AC and EV − PV; negative is bad.
- EAC and ETC
- BAC ÷ CPI, and EAC − AC.
- Slip and overspend
- EV below PV, and AC above EV.