Project Management · Module 7Lesson 1

Study explanation · Lesson 01 · 20 min

Costing basics

Cost has to be estimated before it can be controlled, and an unrealistic estimate can never be controlled. This lesson covers what to settle before estimating, local content rules, the cost management plan, and what a project estimate must include.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Why cost matters

Cost is one of the three pillars of success for any project, a node on the iron triangle. The notes add that many managers treat it as the most critical dimension, often viewing it as king. Yet cost is not one simple thing: it covers several processes and needs careful management throughout the project’s life cycle.

Cost on a project: settle, plan, estimate, control · Study-guide arrangement of source slides 3-13
  1. Settle the moneyFinancing, equipment funding, economic calculations, local content
  2. PlanThe cost management plan
  3. EstimateRealistic and well supported
  4. ControlMonitor, report, correct

Estimate first, then control

The first step is a realistic, well-supported estimate, which predicts future expenses from the scope, the resources and the known risks. It is the foundation for every later cost decision. Once it is set, the focus shifts to controlling costs through monitoring, reporting and timely corrective action.

Key ideaAn unrealistic estimate is always impossible to control against. In the notes’ words, no amount of control can salvage it, so accuracy from the start is crucial.

Before estimating: three questions

Before getting their hands dirty with estimates, the deck says, the team needs to understand three things about the money behind the project.

  • How the project is financed The debt and equity mix. External funding brings interest, which affects the project’s costs, and some lenders require a specific estimating methodology.
  • How major equipment is funded Some funders give tax breaks, and others require equipment to be sourced from certain countries.
  • Which economic calculations apply Net present value, return on investment, payback period or discounted cash flow. They decide the project’s feasibility as budgets are developed.

Local content requirements

It is very important to know local laws and regulations before estimating. Some laws require materials to be sourced locally and a certain number of local people to be hired; others prevent sourcing equipment and materials from some countries. Either way, they limit the options for sourcing materials and labour.

Deck exampleSuppose the prevailing wage in a country is 30 dollars an hour and half the workforce must be local. An estimate that assumed migrant labour at an average of 10 dollars an hour would be far too low.

The cost management plan

Cost management planning is part of the overall project management plan. The cost management plan sets the framework for how costs will be estimated, monitored and controlled across the project life cycle. The deck lists fourteen things it covers, grouped here in four sets.

  • How estimates are stated The currency; the levels of accuracy and precision needed; the approved estimating techniques; whether indirect costs are included.
  • How performance is measured Reporting formats; rules for measuring cost performance; guidelines for the cost baseline to measure against; control accounts or other ways to monitor spending.
  • How change is controlled Control thresholds that trigger corrective action, and the cost change control procedures.
  • Money and people Funding decisions; methods for documenting costs; how to deal with fluctuations in resource costs and exchange rates; roles and responsibilities for each cost activity.

What a project estimate includes

Project estimation means generating cost estimates for all the project’s activities and resources, assuming a bottom-up approach, and then combining them into one time-phased spending plan spread over the project’s life.

  • The main costs to estimate are labour, equipment, materials and training.
  • Do not forget quality efforts, risk efforts, project management activities, and physical spaces used directly for the project, such as rent.
  • Include overhead costs as applicable, such as management salaries and general office expenses.
  • Always include contingency and escalation.

Read with careThe notes promise more on contingency and escalation “later”, but the deck never returns to them. Lesson 2 also explains why the project manager’s own salary is a direct cost, even though “management salaries” appear here under overhead.

Key takeaways

  • Cost is estimated first and controlled second; no control can rescue an unrealistic estimate.
  • Before estimating, know the financing mix, how equipment is funded, and which economic calculations apply.
  • Local content laws can change labour and material costs sharply.
  • The cost management plan sets currency, accuracy, techniques, baseline, thresholds, change control and roles.
  • An estimate covers labour, equipment, materials and training, plus quality, risk, management, space, overhead, contingency and escalation.

Study explanation based on the supplied Week 7: Costing and Control source deck. Open the source notes above for slide-level traceability.