Two ways to categorize costs
There are several ways to categorize costs: by their source or by their variability. The two are not mutually exclusive. A cost can be direct and fixed, or direct and variable.
By source
- Direct
- Attributable to the project’s work
- Indirect
- Overhead, or shared by several projects
By variability
- Variable
- Changes with the amount of work
- Fixed
- Does not change with production
The two are not mutually exclusive: a cost can be direct and fixed, or direct and variable.
Direct and indirect costs
Direct costs can be linked directly to the work on the project. Examples include team wages, team travel, recognition expenses and the materials used. If the team pours a concrete slab, the workers’ wages and the concrete itself are direct costs.
- Indirect costs are overhead items, or costs incurred for the benefit of more than one project, such as taxes, fringe benefits and janitorial services.
- Head office costs and executive management costs are indirect.
- Indirect costs are generally harder to estimate than direct costs.
Try it: direct or indirect?
The deck asks how to classify three salaries. Decide each one, then compare with its answer.
| Cost | Category | Why |
|---|---|---|
| The project manager’s salary | Direct | The role works on this project |
| The CEO’s time spent reviewing the project | Indirect | Executive management serves more than one project |
| The design engineer’s salary | Direct | Design work is attributable to the project’s work |
Read with careLesson 1’s list of overheads includes “management salaries”. Read with slide 17, that means head office and executive management. The project manager’s own salary is a direct cost.
Fixed and variable costs
Variable costs change with the amount of production work: materials, supplies and wages. Fixed costs do not change as production changes: setup, rent and utilities.
| Cost | Category | Why |
|---|---|---|
| Workers’ salaries | Variable | They vary with the amount of work |
| Site office rent | Fixed | Constant regardless of how much is built |
| Concrete on a building project | Variable | It varies with the quantity |
| Tax on land rent | Fixed | Constant |
Read with careTax is indirect by source (slide 17) and fixed by variability: the two classifications describe the same cost in different ways.
Equipment and bulk materials
Material costs divide into two categories, which behave differently in an estimate.
Equipment
- Size
- Volume intensive, large
- Cost
- Typically expensive
- Installation labour
- Minimal compared with its cost
- Examples
- Compressors, transformers, elevators, heat exchangers
Bulk materials
- Size
- Small; a small truck can carry them
- Cost
- Less expensive than equipment
- Installation labour
- Nearly equal to the material cost
- Examples
- Piping, cables, trays, concrete
Key ideaThe difference shows in the labour: installing equipment takes little labour relative to its cost, while bulk materials need roughly as much labour as they cost.
Material takeoffs and quotations
Two definitions close the lesson, and Lesson 3 builds on both.
- Material takeoff A list of materials, with their quantities and types, required to build a structure.
- Quotation A document from a seller to a buyer offering goods or services at a stated price and with a specified validity.
Key takeaways
- By source, costs are direct or indirect; by variability, fixed or variable; one cost has both labels.
- The project manager’s salary is direct; the CEO’s review time is indirect.
- Indirect costs are harder to estimate than direct costs.
- Equipment is large, expensive and quick to install; bulk materials cost about as much to install as to buy.
- A takeoff lists quantities; a quotation prices them for a stated period.