Project Management · Module 7Lesson 2

Study explanation · Lesson 02 · 18 min

Cost categories

Costs can be sorted by their source, direct or indirect, and by their variability, fixed or variable, and a single cost belongs to both. Materials divide into equipment and bulk materials. The lesson ends with two terms every estimate needs: the material takeoff and the quotation.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Two ways to categorize costs

There are several ways to categorize costs: by their source or by their variability. The two are not mutually exclusive. A cost can be direct and fixed, or direct and variable.

Basic cost categories · Source slides 15-16

By source

Direct
Attributable to the project’s work
Indirect
Overhead, or shared by several projects

By variability

Variable
Changes with the amount of work
Fixed
Does not change with production

The two are not mutually exclusive: a cost can be direct and fixed, or direct and variable.

Direct and indirect costs

Direct costs can be linked directly to the work on the project. Examples include team wages, team travel, recognition expenses and the materials used. If the team pours a concrete slab, the workers’ wages and the concrete itself are direct costs.

  • Indirect costs are overhead items, or costs incurred for the benefit of more than one project, such as taxes, fringe benefits and janitorial services.
  • Head office costs and executive management costs are indirect.
  • Indirect costs are generally harder to estimate than direct costs.

Try it: direct or indirect?

The deck asks how to classify three salaries. Decide each one, then compare with its answer.

Direct or indirect · Source slide 19
CostCategoryWhy
The project manager’s salaryDirectThe role works on this project
The CEO’s time spent reviewing the projectIndirectExecutive management serves more than one project
The design engineer’s salaryDirectDesign work is attributable to the project’s work

Read with careLesson 1’s list of overheads includes “management salaries”. Read with slide 17, that means head office and executive management. The project manager’s own salary is a direct cost.

Fixed and variable costs

Variable costs change with the amount of production work: materials, supplies and wages. Fixed costs do not change as production changes: setup, rent and utilities.

Fixed or variable · Source slides 21-22
CostCategoryWhy
Workers’ salariesVariableThey vary with the amount of work
Site office rentFixedConstant regardless of how much is built
Concrete on a building projectVariableIt varies with the quantity
Tax on land rentFixedConstant

Read with careTax is indirect by source (slide 17) and fixed by variability: the two classifications describe the same cost in different ways.

Equipment and bulk materials

Material costs divide into two categories, which behave differently in an estimate.

Material cost categories · Source slides 23-24

Equipment

Size
Volume intensive, large
Cost
Typically expensive
Installation labour
Minimal compared with its cost
Examples
Compressors, transformers, elevators, heat exchangers

Bulk materials

Size
Small; a small truck can carry them
Cost
Less expensive than equipment
Installation labour
Nearly equal to the material cost
Examples
Piping, cables, trays, concrete

Key ideaThe difference shows in the labour: installing equipment takes little labour relative to its cost, while bulk materials need roughly as much labour as they cost.

Material takeoffs and quotations

Two definitions close the lesson, and Lesson 3 builds on both.

  • Material takeoff A list of materials, with their quantities and types, required to build a structure.
  • Quotation A document from a seller to a buyer offering goods or services at a stated price and with a specified validity.

Key takeaways

  • By source, costs are direct or indirect; by variability, fixed or variable; one cost has both labels.
  • The project manager’s salary is direct; the CEO’s review time is indirect.
  • Indirect costs are harder to estimate than direct costs.
  • Equipment is large, expensive and quick to install; bulk materials cost about as much to install as to buy.
  • A takeoff lists quantities; a quotation prices them for a stated period.

Study explanation based on the supplied Week 7: Costing and Control source deck. Open the source notes above for slide-level traceability.