Project Management · Module 7 reference
Glossary
Short, source-grounded definitions to use alongside the learning path.
- Iron triangle
The three pillars of project success, of which cost is one node.
Review Lesson 1- Cost estimation
Predicting future expenses from the scope, resources and known risks; the foundation for every later cost decision.
Review Lesson 1- Cost control
Monitoring, reporting and timely corrective action against the estimate.
Review Lesson 1- Local content requirements
Laws requiring local sourcing or local hires, or preventing sourcing from some countries.
Review Lesson 1- Cost management plan
Part of the project management plan that sets how costs are estimated, monitored and controlled.
Review Lesson 1- Contingency and escalation
Allowances the deck says every estimate must include; it does not define them further.
Review Lesson 1- Direct cost
A cost directly attributable to the project’s work, such as team wages, travel and materials.
Review Lesson 2- Indirect cost
Overhead, or a cost incurred for more than one project, such as taxes, fringe benefits, head office and executive management.
Review Lesson 2- Fixed cost
A cost that does not change as production changes, such as setup, rent and utilities.
Review Lesson 2- Variable cost
A cost that changes with the amount of production work, such as materials, supplies and wages.
Review Lesson 2- Equipment
Large, typically expensive material items needing little installation labour relative to their cost.
Review Lesson 2- Bulk materials
Small, cheaper materials whose labour costs are nearly equal to their material costs.
Review Lesson 2- Material takeoff
A list of materials, with quantities and types, required to build a structure.
Review Lesson 2- Quotation
A seller’s offer of goods or services at a stated price with a specified validity.
Review Lesson 2- Top-down analogous estimation
Estimating the whole project first, from similar projects, then moving down to activities; quick but less accurate.
Review Lesson 3- Bottom-up estimation
Estimating each activity in detail and adding them up; accurate but slow.
Review Lesson 3- AACE
The Association for the Advancement of Cost Engineering, whose five estimate classes grade estimate quality.
Review Lesson 4- Class 5 estimate
Concept screening with 0% to 2% definition; the widest accuracy range.
Review Lesson 4- Class 3 estimate
Budget authorization with 10% to 40% definition; typically the initial control estimate.
Review Lesson 4- Class 1 estimate
A check or bid estimate for parts of the project, with 50% to 100% definition.
Review Lesson 4- Current control estimate
An updated class 1 estimate that becomes the new baseline for cost and schedule control.
Review Lesson 4- Variation order
One of the outputs project control may show is needed.
Review Lesson 5- Earned value method (EVM)
A method that integrates scope, schedule and resources, comparing planned work, earned work and actual spending.
Review Lesson 5- Planned value (PV, BCWS)
The budgeted cost of the work scheduled to be completed up to a point in time.
Review Lesson 5- Earned value (EV, BCWP)
The budgeted amount for the work actually completed.
Review Lesson 5- Actual cost (AC, ACWP)
The total cost incurred for the work done in a period.
Review Lesson 5- Cost variance (CV)
EV − AC; negative means over budget.
Review Lesson 5- Schedule variance (SV)
EV − PV; negative means behind schedule.
Review Lesson 5- CPI and SPI
EV ÷ AC and EV ÷ PV; above 1 means cost efficient or ahead of schedule.
Review Lesson 5- BAC, EAC and ETC
Budget at completion; estimate at completion, BAC ÷ CPI; estimate to complete, EAC − AC.
Review Lesson 5- S-curve
Cumulative baseline cost plotted against time.
Review Lesson 6- Slip and overspend
EV reaching a budget level later than PV, and AC sitting above EV.
Review Lesson 6