Project Management · Module 7 reference

Glossary

Short, source-grounded definitions to use alongside the learning path.

Iron triangle

The three pillars of project success, of which cost is one node.

Review Lesson 1
Cost estimation

Predicting future expenses from the scope, resources and known risks; the foundation for every later cost decision.

Review Lesson 1
Cost control

Monitoring, reporting and timely corrective action against the estimate.

Review Lesson 1
Local content requirements

Laws requiring local sourcing or local hires, or preventing sourcing from some countries.

Review Lesson 1
Cost management plan

Part of the project management plan that sets how costs are estimated, monitored and controlled.

Review Lesson 1
Contingency and escalation

Allowances the deck says every estimate must include; it does not define them further.

Review Lesson 1
Direct cost

A cost directly attributable to the project’s work, such as team wages, travel and materials.

Review Lesson 2
Indirect cost

Overhead, or a cost incurred for more than one project, such as taxes, fringe benefits, head office and executive management.

Review Lesson 2
Fixed cost

A cost that does not change as production changes, such as setup, rent and utilities.

Review Lesson 2
Variable cost

A cost that changes with the amount of production work, such as materials, supplies and wages.

Review Lesson 2
Equipment

Large, typically expensive material items needing little installation labour relative to their cost.

Review Lesson 2
Bulk materials

Small, cheaper materials whose labour costs are nearly equal to their material costs.

Review Lesson 2
Material takeoff

A list of materials, with quantities and types, required to build a structure.

Review Lesson 2
Quotation

A seller’s offer of goods or services at a stated price with a specified validity.

Review Lesson 2
Top-down analogous estimation

Estimating the whole project first, from similar projects, then moving down to activities; quick but less accurate.

Review Lesson 3
Bottom-up estimation

Estimating each activity in detail and adding them up; accurate but slow.

Review Lesson 3
AACE

The Association for the Advancement of Cost Engineering, whose five estimate classes grade estimate quality.

Review Lesson 4
Class 5 estimate

Concept screening with 0% to 2% definition; the widest accuracy range.

Review Lesson 4
Class 3 estimate

Budget authorization with 10% to 40% definition; typically the initial control estimate.

Review Lesson 4
Class 1 estimate

A check or bid estimate for parts of the project, with 50% to 100% definition.

Review Lesson 4
Current control estimate

An updated class 1 estimate that becomes the new baseline for cost and schedule control.

Review Lesson 4
Variation order

One of the outputs project control may show is needed.

Review Lesson 5
Earned value method (EVM)

A method that integrates scope, schedule and resources, comparing planned work, earned work and actual spending.

Review Lesson 5
Planned value (PV, BCWS)

The budgeted cost of the work scheduled to be completed up to a point in time.

Review Lesson 5
Earned value (EV, BCWP)

The budgeted amount for the work actually completed.

Review Lesson 5
Actual cost (AC, ACWP)

The total cost incurred for the work done in a period.

Review Lesson 5
Cost variance (CV)

EV − AC; negative means over budget.

Review Lesson 5
Schedule variance (SV)

EV − PV; negative means behind schedule.

Review Lesson 5
CPI and SPI

EV ÷ AC and EV ÷ PV; above 1 means cost efficient or ahead of schedule.

Review Lesson 5
BAC, EAC and ETC

Budget at completion; estimate at completion, BAC ÷ CPI; estimate to complete, EAC − AC.

Review Lesson 5
S-curve

Cumulative baseline cost plotted against time.

Review Lesson 6
Slip and overspend

EV reaching a budget level later than PV, and AC sitting above EV.

Review Lesson 6