Six steps
The deck sets out earned value management as a sequence. Each step needs the one before it.
- Clearly define each activity, including its resource needs and budget.
- Create usage schedules for the activities and resources.
- Develop a time-phased budget: the planned value.
- Total the actual costs of doing each task: the actual cost.
- Calculate the cost variance and the schedule variance.
- Calculate the estimate at completion and the estimate to complete.
Constructing the baseline
Each activity’s cost is assumed to be spread evenly across its duration, so its daily cost is its cost divided by its duration. On each day, the total daily cost is the sum of the daily costs of the activities scheduled that day. The cumulative cost on a day is the sum of all costs from the first day to that day.
Each activity’s cost is spread evenly over its bar. Adding the daily costs and accumulating them from day one gives the S-curve. The bar positions and the curve are illustrative.
Key ideaPlotted against time, cumulative cost forms an S-curve: slow at the start, steep while many activities overlap, flat at the end. It can also be shown as a percentage of the total project cost.
Slip and overspend
Another way to read the values is on two axes, cost and schedule. Earned value reaches a budget level later than planned value did: that horizontal gap is the slip. Actual cost sits above earned value for the same work: that vertical gap is the overspend.
The same budgeted value is earned later than it was planned: that is the slip. The work performed cost more than its budget: that is the overspend.
Read with careThe notes on slide 68 say that if earned value is above planned value, the project is slipping. That reverses the deck’s own formulas: SPI above 1, or SV above 0, means ahead of schedule. The project slips when earned value is below planned value.
Reading the status on a given day
On the review day, compare where the three curves stand. The deck gives two cases. In the first, the work completed is worth more than planned, so the project is ahead of schedule, and the actual cost is below both, so the work is cheaper than planned. In the second, both conclusions are reversed.
EV above PV: more work done than planned. AC below EV: the work cost less than its budget.
The opposite case
Here the value of the work done is less than planned, so the project is behind schedule. The actual cost is greater than the planned value and greater than the earned value, so the work has been more costly than planned.
EV below PV: less work done than planned. AC above EV: the work cost more than its budget.
Six possible outcomes
Slide 71 draws six combinations of the baseline, the earned value and the actual cost. The signs of the two variances describe each one.
| Case | Schedule variance | Cost variance | Meaning |
|---|---|---|---|
| (a) and (b) | Positive | Positive | Ahead of schedule and under budget |
| (c) and (d) | Negative | Negative | Behind schedule and over budget |
| (e) | Negative | Positive | Behind schedule but under budget |
| (f) | Positive | Negative | Ahead of schedule but over budget |
Read with careThe deck’s pairs differ in where the curves sit relative to one another, not in the signs.
Worked example: one work package
A work package was budgeted at 1,500 dollars and scheduled to finish today. So far 1,350 dollars has been spent, and two thirds of the work is complete. Earned value is 1,500 × 2/3 = 1,000 dollars.
| Metric | Calculation | Result |
|---|---|---|
| Cost variance | 1,000 − 1,350 | −350 dollars |
| Schedule variance | 1,000 − 1,500 | −500 dollars |
| CPI | 1,000 ÷ 1,350 | 0.74 |
| SPI | 1,000 ÷ 1,500 | 0.67 |
Key ideaThe package is spending more than budgeted, and for what it has spent it is not as far along as it should be.
Extending the example: the forecast
The deck stops at the indices. Applying its own formulas from Lesson 5 gives the forecast. With a budget at completion of 1,500 dollars and a CPI of about 0.74, the estimate at completion is 1,500 ÷ 0.7407 = 2,025 dollars, and the estimate to complete is 2,025 − 1,350 = 675 dollars.
Study-guide calculationIf the package keeps spending at today’s efficiency, it will finish at 2,025 dollars, 525 dollars over its budget.
Worked example: the country park
A project to develop a country park reaches month 17 with an actual cost of 350,000 dollars, a planned value of 475,000 dollars and an earned value of 300,000 dollars.
| Metric | Calculation | Result |
|---|---|---|
| Cost variance | 300,000 − 350,000 | −50,000 dollars: cost overrun |
| Schedule variance | 300,000 − 475,000 | −175,000 dollars: behind schedule |
| CPI | 300,000 ÷ 350,000 | 0.86 |
| SPI | 300,000 ÷ 475,000 | 0.63 |
Read with careThe deck gives no budget at completion for this project, so no estimate at completion can be calculated.
Key ideaThe project is late and costing more than it should.
Key takeaways
- Define activities and budgets, schedule them, phase the budget, record actuals, then calculate variances and forecasts.
- The baseline spreads each activity’s cost over its duration; cumulative cost forms an S-curve.
- EV below PV means slip; AC above EV means overspend.
- The signs of SV and CV give four kinds of outcome.
- In the work package example, CV is −350 dollars, SV −500 dollars, CPI 0.74 and SPI 0.67.