Project Management · Module 7Applied casePart 6

Applied case · Part 06 · 13 min

Contingency and cost control

The required total stays at £4,312.00. Beside it, the author proposes a separate 10% contingency of £431.20, and a plan to confirm prices before committing funds and to record spending against completed work. The case connects that plan to Week 7’s monitoring and earned value.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Overhead is not contingency

Week 7 reminds estimators to consider contingency and escalation. The submission does so without changing the required table: it proposes a separate reserve. The guide draws the line between the two allowances.

  • Overhead Pays for expected shared support, such as administration and purchasing.
  • Contingency Allows for uncertainty, such as extra timber or additional paid effort.
The required total and the optional reserve · Submission · Guide
AmountCalculationValue
Required cost-sheet totalMaterials + labour + overhead£4,312.00
Optional contingency10% × £4,312£431.20
Indicative funding with the reserve£4,312 + £431.20£4,743.20

Applied choiceThe 10% contingency is the author’s supplementary assumption. The assignment does not prescribe a rate, and the reserve is not an approved one; it sits outside both the overhead and the table total.

When a cost changes

The guide works one change through. Suppose the timber costs £60 more. Overhead rises by 12% of £60, which is £7.20, so the estimate rises by £67.20 to £4,379.20. If an approved contingency covered it, £364.00 would remain of the £431.20 reserve.

Key ideaRecord the reason and the approval, and do not count the same increase twice.

Before committing funds

The submission’s control plan starts before any money is spent. It would confirm the site measurements, the material specifications, the crew allowances and the supplier quotations, and only then seek approval for the estimate and any reserve.

Key ideaThis is where the exercise’s assumed prices become the firm quotes that Lesson 3’s best practice asks for.

After approval: record against the work

Once approved, the plan records receipts, purchase commitments and paid days against activities A to F, compares costs with completed work, and gets approval for scope changes or use of the reserve. It follows Week 7’s advice to monitor while there is still time to react.

Less spending is not a saving

The guide adds one sentence that is the heart of earned value: less spending alone does not prove a saving if the work is unfinished. Comparing cost with completed work, not with the calendar, is what Lessons 5 and 6 formalize.

Study connectionSuppose fencing, C, is half built and £500 has been spent. Its earned value is 50% × £1,176 = £588, so the cost variance is £588 − £500 = £88 under budget for the work done. If the same £500 had bought only a quarter of the fence, EV would be £294 and CV −£206. This illustration is this case’s own; neither document computes earned value.

Key takeaways

  • The required total stays £4,312.00; a 10% contingency of £431.20 sits beside it.
  • Overhead covers expected shared support; contingency covers uncertainty.
  • Timber at £60 more adds £67.20, leaving £364.00 of the reserve.
  • Confirm prices and quantities before committing funds; then record spending against A to F.
  • Compare cost with completed work: less spending is not a saving if the work is unfinished.

Study explanation of an academic cost sheet submission and its explanation guide, read against the supplied Week 7: Costing and Control course deck. Open the source notes above to see which document each claim comes from.