The completed sheet
This is the table the brief asks for. Each activity has its materials, its labour, its share of management and overhead, and a total. The grand total is £4,312.00.
| Activity | Materials | Labour | Management / overhead | Total |
|---|---|---|---|---|
| A · Site preparation | £100.00 | £200.00 | £36.00 | £336.00 |
| B · Build raised beds | £760.00 | £400.00 | £139.20 | £1,299.20 |
| C · Install fencing | £650.00 | £400.00 | £126.00 | £1,176.00 |
| D · Create seating area | £450.00 | £200.00 | £78.00 | £728.00 |
| E · Planting | £190.00 | £200.00 | £46.80 | £436.80 |
| F · Project supervision | £0.00 | £300.00 | £36.00 | £336.00 |
| Grand total | £2,150.00 | £1,700.00 | £462.00 | £4,312.00 |
Read with careLabour = workers × paid days × £100. Overhead = 12% × (materials + labour). Every row and column was recomputed for this case, and all agree.
Three ways to check it
The guide sets out a quick audit that catches most errors in a cost sheet.
- Check the rows: each activity total equals its three cost categories added together.
- Check the columns: materials £2,150 + labour £1,700 = £3,850 of direct cost, and £3,850 × 12% = £462 of overhead.
- Check both directions: £3,850 + £462 = £4,312, which also equals the sum of the six activity totals.
Key ideaWhen the row sums and the column sums give the same grand total, the arithmetic holds.
How a change ripples through
Because overhead is a percentage of direct cost, every pound of direct cost carries 12 pence of overhead with it. A £100 increase in direct costs adds £12 of overhead, so the activity total rises by £112.
- Change the quantity or rate in one line, and only that activity moves.
- Recalculate its overhead from the new direct cost.
- Never apply 12% again to a total that already includes overhead.
Pence are not precision
Totals such as £1,299.20 carry pence only because 12% of £1,160 is £139.20. The guide warns that this does not mean the estimate is accurate to the nearest penny: the prices behind it are assumptions.
Key ideaWeek 7’s AACE classes grade an estimate by how much is defined, not by its decimal places. With assumed prices and an outline scope, this estimate would sit at the less defined end of that scale. That placing is this case’s study connection; neither document assigns a class.
Key takeaways
- Grand total: £2,150 materials + £1,700 labour + £462 overhead = £4,312.
- Check rows, columns and both directions.
- £100 more direct cost means £112 more in total.
- Never apply the overhead rate twice.
- Pence come from arithmetic, not from precision.