The exercise in one line
Estimate the cost of six activities, A to F, for a school community garden: site preparation, raised beds, fencing, a seating area, planting and project supervision. Labour is charged at £100 per worker-day, and management and overhead at 10% to 15% of materials plus labour. The result is a completed cost sheet, submitted as a three-page document.
Key ideaThe guide names the real test: give a reasonable scope, show the assumptions behind the amounts, apply the required labour and overhead rules, and check that every total agrees.
The answer first
The submission opens with its result before any working: an estimated cost of £4,312.00, including materials, paid labour and 12% management and overhead. It says how the number was built in the same sentence: each activity was estimated separately and the results were added, a bottom-up approach.
- £2,150MaterialsTakeoff: quantity × assumed rate
- £1,700Labour17 worker-days × £100
- £462Overhead12% × £3,850 direct cost
- £4,312Cost sheet totalSummed by activity and by column
A separate 10% contingency of £431.20 is proposed alongside, not inside, the total: £4,743.20 if accepted.
Specified, and chosen
The brief fixes the activities and two rates, and nothing else. Everything in the right-hand column below is the author’s choice, and both documents say so.
| Specified by the assignment | Chosen for this estimate |
|---|---|
| The six activities, A to F, and the school garden scenario | An 8 m × 5 m garden with four beds, fencing with a gate, and two benches |
| Labour at £100 per worker-day | The crew size and paid effort for each activity; the same rate for the supervisor |
| Overhead between 10% and 15% of materials plus labour | 12%, applied the same way to every activity |
| A completed cost sheet in a three-page document | Quantity-based supporting calculations, and a separate optional contingency note |
Applied choiceThe garden’s size, the quantities, the material prices, the crew sizes and the 12% rate are the author’s assumptions, stated so a reader can see exactly what was priced. The submission calls the prices “assumptions for this exercise, not supplier quotations”.
Why bottom up
The guide explains the choice of method. Starting from the work and building up to the total makes every change traceable: one extra bench changes activity D, rather than an unexplained project-wide lump sum.
- Identify the materials for each activity.
- Estimate the paid effort.
- Add overhead.
- Sum activities A to F.
Key takeaways
- The brief fixes six activities, a £100 worker-day and a 10% to 15% overhead range; everything else is assumed.
- The answer, £4,312.00, comes first, with how it was built.
- A bottom-up build makes each change traceable to one activity.
- Assumptions are labelled as assumptions, not facts or quotations.