Paid effort times the daily rate
Labour cost = workers × paid days per worker × £100. Two workers for two days contribute four worker-days, so B costs 2 × 2 × £100 = £400 in labour.
| Activity | Workers | Paid days per person | Worker-days | Labour cost |
|---|---|---|---|---|
| A · Site preparation | 2 | 1 | 2 | £200 |
| B · Build raised beds | 2 | 2 | 4 | £400 |
| C · Install fencing | 2 | 2 | 4 | £400 |
| D · Create seating area | 2 | 1 | 2 | £200 |
| E · Planting | 2 | 1 | 2 | £200 |
| F · Project supervision | 1 | 3 | 3 | £300 |
| Total paid effort | 17 | £1,700 |
Read with care14 days of site labour and 3 supervisor-days. Worker-days measure paid effort, not the calendar duration of the project.
Applied choiceThe crew sizes and paid days are the author’s planning assumptions, and the work is assumed to be done in suitable conditions.
Worker-days are not calendar days
The 17 worker-days mean £1,700 of paid effort. They do not mean the project lasts 17 days. A schedule would decide which activities overlap and when people are available, and the three supervisor-days can be spread across planning, site visits, quality checks and handover.
Key ideaEffort prices the work; the schedule times it. Week 6 built the schedule; this sheet prices the effort.
Direct or indirect?
Week 7 defines a direct cost as one attributable to the project’s work, and an indirect cost as overhead, or a cost shared by more than one project. The guide applies that split to the garden.
- Direct Materials, construction workers, and the project supervisor’s time: all belong specifically to this garden.
- Indirect Shared office administration, communications and purchasing support: allocated through the overhead rate.
Why supervision is not overhead
The brief’s column is headed “Management / Overhead”, yet F, project supervision, puts £300 in labour. The guide explains: Week 7 classifies the project manager’s pay as a direct cost, so the supervisor’s three days are charged to F. The overhead column then carries only shared support, and excludes that supervisor time.
Read with careThe deck itself lists “management salaries” among overheads on slide 12 but the project manager’s salary as direct on slide 19. Read with slide 17, management overhead means head office and executive management, which is the reading the submission follows. In the guide’s words, calling a column Management / Overhead does not require all managerial work to sit in it.
12% of direct cost, applied once
Overhead = (materials + labour) × 0.12, so each activity’s total = (materials + labour) × 1.12. For B, direct cost is £760 + £400 = £1,160, overhead is £139.20, and the total is £1,299.20. For F, overhead is 12% of £300, which is £36, for a total of £336.
- The rate sits inside the 10% to 15% the brief permits.
- Applying one rate to every row makes the rows comparable.
- The percentage is applied once, to materials plus labour, never to a total that already includes overhead.
Applied choice12% is the author’s choice within the brief’s range. The guide says it is not a quoted school policy or a market rate.
Key takeaways
- Labour = workers × paid days × £100: 17 worker-days, £1,700.
- Worker-days measure effort, not how long the project takes.
- Materials, workers and the supervisor are direct; shared administration is indirect.
- Supervision is charged in labour, so overhead excludes it.
- Overhead is 12% of materials plus labour, applied once.