Project Management · Module 7Applied casePart 4

Applied case · Part 04 · 14 min

Labour, overhead and direct costs

Labour is paid effort times the £100 daily rate: 17 worker-days, £1,700. Overhead is 12% of materials plus labour, applied once. The case explains why the supervisor sits in labour rather than overhead, using Week 7’s split between direct and indirect costs.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Worker-days are not calendar days

The 17 worker-days mean £1,700 of paid effort. They do not mean the project lasts 17 days. A schedule would decide which activities overlap and when people are available, and the three supervisor-days can be spread across planning, site visits, quality checks and handover.

Key ideaEffort prices the work; the schedule times it. Week 6 built the schedule; this sheet prices the effort.

Direct or indirect?

Week 7 defines a direct cost as one attributable to the project’s work, and an indirect cost as overhead, or a cost shared by more than one project. The guide applies that split to the garden.

  • Direct Materials, construction workers, and the project supervisor’s time: all belong specifically to this garden.
  • Indirect Shared office administration, communications and purchasing support: allocated through the overhead rate.

Why supervision is not overhead

The brief’s column is headed “Management / Overhead”, yet F, project supervision, puts £300 in labour. The guide explains: Week 7 classifies the project manager’s pay as a direct cost, so the supervisor’s three days are charged to F. The overhead column then carries only shared support, and excludes that supervisor time.

Read with careThe deck itself lists “management salaries” among overheads on slide 12 but the project manager’s salary as direct on slide 19. Read with slide 17, management overhead means head office and executive management, which is the reading the submission follows. In the guide’s words, calling a column Management / Overhead does not require all managerial work to sit in it.

12% of direct cost, applied once

Overhead = (materials + labour) × 0.12, so each activity’s total = (materials + labour) × 1.12. For B, direct cost is £760 + £400 = £1,160, overhead is £139.20, and the total is £1,299.20. For F, overhead is 12% of £300, which is £36, for a total of £336.

  • The rate sits inside the 10% to 15% the brief permits.
  • Applying one rate to every row makes the rows comparable.
  • The percentage is applied once, to materials plus labour, never to a total that already includes overhead.

Applied choice12% is the author’s choice within the brief’s range. The guide says it is not a quoted school policy or a market rate.

Key takeaways

  • Labour = workers × paid days × £100: 17 worker-days, £1,700.
  • Worker-days measure effort, not how long the project takes.
  • Materials, workers and the supervisor are direct; shared administration is indirect.
  • Supervision is charged in labour, so overhead excludes it.
  • Overhead is 12% of materials plus labour, applied once.

Study explanation of an academic cost sheet submission and its explanation guide, read against the supplied Week 7: Costing and Control course deck. Open the source notes above to see which document each claim comes from.

Your study checkpoint

Ready to continue?

Mark the part complete once you have read it, checked its sources, and tested the idea against a project of your own.

Next · Part 5