Project Management · Module 07 · Applied case

A garden, costed bottom up

Six activities, one takeoff, 17 worker-days and 12% overhead: how a £4,312 estimate is built, checked and controlled.

A three-page cost sheet for a school community garden and its explanation guide, read part by part: what the brief really tests, why the scope comes before the price, the material takeoff, labour and overhead as direct and indirect costs, the completed sheet and its checks, and the contingency and control that sit beside it. Every quantity, price and rate the author chose is marked as an applied choice.

The estimate, part by part

Watch six activities become one costed answer.

Open case sources
01The briefThe exercise asks for the resources and cost of six activities to build a school community garden, with labour at £100 per worker-day and overhead of 10% to 15%. It supplies no prices or dimensions, so it tests whether an estimate can be built, explained and checked from stated assumptions.11 min02Scope before priceFour small beds cost differently from ten large ones, so the estimate fixes a footprint first: an 8 m by 5 m garden, four beds, 25 m of fencing and a gate, two benches. It also says what the school provides and what is left out, so the price has a boundary.12 min03The material takeoffEvery material allowance is a quantity multiplied by a rate, listed item by item for each activity, so £2,150 can be traced back line by line. The case also shows how one item is kept from being paid for twice, and where the assumed prices fall short of the deck’s best practice.13 min04Labour and overheadLabour is paid effort times the £100 daily rate: 17 worker-days, £1,700. Overhead is 12% of materials plus labour, applied once. The case explains why the supervisor sits in labour rather than overhead, using Week 7’s split between direct and indirect costs.14 min05The cost sheetThe sheet adds materials, labour and overhead for each of the six activities to reach £4,312.00. The guide checks it three ways: across each row, down each column, and both directions together. It also shows how a change ripples through the 12% rate.12 min06Contingency and controlThe required total stays at £4,312.00. Beside it, the author proposes a separate 10% contingency of £431.20, and a plan to confirm prices before committing funds and to record spending against completed work. The case connects that plan to Week 7’s monitoring and earned value.13 min