Where each part of this case comes from, and how its Week 7 page references stand against the course deck.
The three sources
The case reads a three-page cost sheet submission and the author's explanation guide, which explains it and is not part of the assessed work. The brief was not supplied as a file; its requirements come from what both documents state. References name the section of each document. Neither document is republished here.
Why there is a deck check
The explanation guide and the draft of the submission cite the Week 7 deck by PDF page; the final submitted PDF drops those page numbers and refers to Week 7 by name. The deck is in this library, so every cited page was checked against it and the result is published below. The check is this case's own work. Open the full case reference →
Case map · Submission, Guide and Deck
Case part
Submission
Guide
Course lessons applied
1 · The brief
Opening answer; calculation method
What the exercise asks; specified and chosen; why bottom up
Week 7: cost estimation, costing basics
2 · Scope before price
Scope; resources and exclusions
Why the scope comes before the price
Week 7: cost estimation, costing basics
3 · The material takeoff
Material quantities and price assumptions
Materials are quantity multiplied by price
Week 7: cost categories, cost estimation
4 · Labour and overhead
Labour allowances; overhead and supervision
Labour; why overhead and supervision are separate
Week 7: cost categories, costing basics
5 · The cost sheet
Completed cost sheet; calculation method
How to check the completed table
Week 7: cost estimation, estimate accuracy
6 · Contingency and control
Contingency; how I would control the costs
How to interpret and use the estimate
Week 7: project controls, applying earned value
Read with careNeither document numbers its sections, so references use their headings.
Week 7 references checked against the deck
Claim in the submission draft or guide
Deck
Result
Cost planning and what an estimate covers
pp. 9-13
Matches
Contingency and escalation should be considered
pp. 12-13
Matches; the deck gives no rate, so 10% is the author’s
Direct and indirect costs
pp. 17-18
Matches
Project manager pay is a direct cost
p. 19
Matches
A material takeoff lists quantities
p. 25
Matches
Estimate from quantities, current quotations and checked specifications
pp. 27-28
Matches; both documents say the exercise prices are assumptions, not the firm quotes the deck asks for
Bottom-up estimation
pp. 33-34
Matches
Monitor spending while there is still time to react
pp. 52-54
Matches
Read with careNo contradiction with the deck was found. The final submitted PDF keeps the same claims without page numbers. Every number in the case was also recomputed, and all match both documents.
Part 01
The brief, and what it really tests
The exercise asks for the resources and cost of six activities to build a school community garden, with labour at £100 per worker-day and overhead of 10% to 15%. It supplies no prices or dimensions, so it tests whether an estimate can be built, explained and checked from stated assumptions.
Six activities, a daily labour rate and an overhead range.
Brief, as stated in both documents
What it asks you to demonstrate
Scope, assumptions, the required rules, and totals that agree.
Guide · what the exercise is asking
The answer
£4,312.00, built bottom up.
Submission · opening · Deck pp. 33-34
Specified and chosen
The two-column table of requirements and choices.
Guide · specified and chosen
Part 02
Scope before price
Four small beds cost differently from ten large ones, so the estimate fixes a footprint first: an 8 m by 5 m garden, four beds, 25 m of fencing and a gate, two benches. It also says what the school provides and what is left out, so the price has a boundary.
The 8 m by 5 m garden, beds, fencing, benches, planting and supervision.
Submission · scope
Why the scope comes first
Different beds need different timber and soil; the dimensions are not a design.
Guide · why the scope comes before the price
Resources and exclusions
What the school provides; what is excluded; no escalation or volunteer discount.
Submission · resources and exclusions
Course connection
The scope baseline as an input; contingency and escalation.
Deck pp. 12-13, 29
Part 03
The material takeoff
Every material allowance is a quantity multiplied by a rate, listed item by item for each activity, so £2,150 can be traced back line by line. The case also shows how one item is kept from being paid for twice, and where the assumed prices fall short of the deck’s best practice.
Assumed prices include delivery and applicable taxes.
Submission · resources and exclusions
Equipment and bulk
A study connection, not in either document.
Deck pp. 23-24
Part 04
Labour, overhead and direct costs
Labour is paid effort times the £100 daily rate: 17 worker-days, £1,700. Overhead is 12% of materials plus labour, applied once. The case explains why the supervisor sits in labour rather than overhead, using Week 7’s split between direct and indirect costs.
Submission · overhead · Guide · overhead and supervision · Deck pp. 17-19
The deck’s management salaries
Overhead on slide 12; the PM direct on slide 19.
Deck pp. 12, 17, 19
Part 05
The completed cost sheet, and how to check it
The sheet adds materials, labour and overhead for each of the six activities to reach £4,312.00. The guide checks it three ways: across each row, down each column, and both directions together. It also shows how a change ripples through the 12% rate.
Labour, overhead and total formulas; the column check.
Submission · calculation method
How to check the table
Rows, columns, both directions; £100 becomes £112.
Guide · how to check the completed table
Accuracy classes
A study connection, not in either document.
Deck p. 39
Part 06
Contingency and cost control
The required total stays at £4,312.00. Beside it, the author proposes a separate 10% contingency of £431.20, and a plan to confirm prices before committing funds and to record spending against completed work. The case connects that plan to Week 7’s monitoring and earned value.
The garden’s size, every quantity and price, the crew sizes, the 12% rate and the 10% contingency are the author’s assumptions. The brief supplies only the activities, the £100 worker-day and the 10% to 15% overhead range.
Short of the deck’s best practice
Week 7 asks for recent quotes, and firm vendor quotes for significant items. The exercise uses assumed rates; the submission says so, and makes confirming quotations the first step of its control plan.
A management column without the manager
The brief’s column is headed “Management / Overhead”, but the supervisor is charged in labour. This follows the deck’s slide 19, where project manager pay is direct, rather than slide 12, which lists management salaries under overhead.
Effort, not duration
17 worker-days is paid effort. The cost sheet sets no calendar, and the case does not invent one.
The gravel line
The submission writes “0.5 tonnes × £80 = £40”; £80 is the rate per tonne. The arithmetic is right; the wording can mislead.
Pence are not precision
Totals carry pence because of the 12% rate, not because the estimate is accurate to the penny. The guide says so.
Study connections are this case’s own
The equipment and bulk reading in Part 3, the AACE placing in Part 5 and the earned value illustrations in Part 6 and the practice apply Week 7 to the garden. Neither document makes them.
Two versions of the submission
The case was first built from the submission’s working draft, which cites deck pages and ends with a reference list. The final three-page PDF has the same cost sheet, numbers, scope, takeoff, labour, contingency and control plan, but drops the page citations and the reference list. One sentence lost its page cite and now reads “the quantity-based estimating approach in Week .”, with the number missing. Nothing in the case changes; deck pages cited here are the case’s own checks.
The brief is described, not reproduced
No brief file was supplied. Its requirements are taken from what both documents state. The due date and upload steps are left out.
Checked against the submission, the explanation guide and the Week 7 deck.
What not to take away
The case parts actively work against these misreadings:
A cost sheet can be priced before the scope is stated.
Assumed exercise prices are the same as supplier quotations.
The same item can safely appear in two activities.
17 worker-days means a 17-day project.
The supervisor belongs in the overhead column because of its heading.
Overhead can be applied to a total that already includes it.
Pence in a total mean the estimate is precise.
Contingency and overhead are the same allowance.
The contingency is part of the required total.
A reserve can be spent without approval.
Spending less than the budget proves a saving.
Prompt purchasing removes the need to think about escalation, whatever the delay.
Study-guide synthesis; each item is addressed in the parts.