Case context reference

The garden cost sheet: the full reference

Everything this case is built from, in one place: the completed sheet, the takeoff, the labour allowances, every check recomputed, the reserve and what-if, the deck check and the points that need a careful reading.

The sources

Two documents, kept apart throughout. A three-page submission answers the exercise with a completed cost sheet. The author’s explanation guide explains it and is not part of the assessed work. The brief was not supplied as a file; its requirements are taken from what both documents state. Both are compared against the Week 7 deck, cited by PDF page. The author’s name, the due date and the upload steps are left out, and neither document is republished.

How to use this reference

The brief fixes six activities, labour at £100 per worker-day and overhead of 10% to 15%. The garden’s size, every quantity and price, the crew sizes, the 12% rate and the 10% contingency are the author’s stated assumptions. Every number below was recomputed, and all of them match both documents. Open the case source guide

The completed cost sheet, in pounds sterling · Submission
ActivityMaterialsLabourManagement / overheadTotal
A · Site preparation£100.00£200.00£36.00£336.00
B · Build raised beds£760.00£400.00£139.20£1,299.20
C · Install fencing£650.00£400.00£126.00£1,176.00
D · Create seating area£450.00£200.00£78.00£728.00
E · Planting£190.00£200.00£46.80£436.80
F · Project supervision£0.00£300.00£36.00£336.00
Grand total£2,150.00£1,700.00£462.00£4,312.00

Read with careLabour = workers × paid days × £100. Overhead = 12% × (materials + labour). Every row and column was recomputed for this case, and all agree.

Every total, recomputed · Submission · Guide
CheckCalculationResult
Direct cost£2,150 materials + £1,700 labour£3,850
Overhead£3,850 × 12%£462
Grand total by columns£3,850 + £462£4,312
Grand total by rows£336 + £1,299.20 + £1,176 + £728 + £436.80 + £336£4,312
Worker-days2 + 4 + 4 + 2 + 2 + 317, of which 14 on site and 3 supervising
Perimeter2 × (8 + 5)26 m = 25 m mesh + 1 m gate
Soil4 × 2 m × 1 m × 0.3 m2.4 m³ × £75 = £180
The material takeoff · Submission
ActivityItems: quantity × assumed rateMaterials
A · Site preparationPath membrane 20 m² × £2 = £40 · waste sacks 10 × £3 = £30 · pegs and marking 1 × £30 = £30£100
B · Build raised bedsTimber-only bed kits 4 × £120 = £480 · liners 4 × £10 = £40 · fixing packs 4 × £15 = £60 · soil and compost 2.4 m³ × £75 = £180£760
C · Install fencingMesh 25 m × £8 = £200 · posts 14 × £15 = £210 · 1 m gate and hinges 1 × £160 = £160 · post-mix 10 × £5 = £50 · fixings 1 × £30 = £30£650
D · Create seating areaFlat-pack benches 2 × £175 = £350 · paving support pads 10 × £5 = £50 · gravel 0.5 tonnes at £80 a tonne = £40 · anchoring fixings 1 × £10 = £10£450
E · PlantingSeed packets 10 × £3 = £30 · seedlings 30 × £2 = £60 · mulch 8 bags × £10 = £80 · labels and ties 1 × £20 = £20£190
F · Project supervisionNo new materials; existing record forms and equipment are used£0
Total£2,150

Read with careEvery line was recomputed and matches. The submission writes the gravel line as “0.5 tonnes × £80 = £40”: £80 is the rate per tonne.

Labour allowances · Submission
ActivityWorkersPaid days per personWorker-daysLabour cost
A · Site preparation212£200
B · Build raised beds224£400
C · Install fencing224£400
D · Create seating area212£200
E · Planting212£200
F · Project supervision133£300
Total paid effort17£1,700

Read with care14 days of site labour and 3 supervisor-days. Worker-days measure paid effort, not the calendar duration of the project.

Contingency and what-if · Submission · Guide, each row recomputed
CaseCalculationResult
Optional contingency10% × £4,312£431.20, for £4,743.20 in all
£100 more direct cost£100 × 1.12£112 more in total
Timber £60 more£60 × 1.12 = £67.20Estimate £4,379.20; £364.00 of the reserve left

Read with careThe contingency is the author’s supplementary assumption, outside the required total.

Part map · where each source is used
Case partMain sources
1 · The briefGuide · what the exercise asks, specified and chosen · Submission · opening · Deck pp. 33-34
2 · Scope before priceSubmission · scope, resources and exclusions · Guide · scope · Deck pp. 12-13, 29
3 · The material takeoffSubmission · takeoff · Guide · materials · Deck pp. 23-25, 27-28
4 · Labour and overheadSubmission · labour, overhead · Guide · labour, overhead · Deck pp. 12, 17-19
5 · The cost sheetSubmission · cost sheet, method · Guide · checking · Deck p. 39
6 · Contingency and controlSubmission · contingency, control · Guide · interpreting · Deck pp. 12-13, 52-58
Week 7 references checked against the deck
Claim in the submission draft or guideDeckResult
Cost planning and what an estimate coverspp. 9-13Matches
Contingency and escalation should be consideredpp. 12-13Matches; the deck gives no rate, so 10% is the author’s
Direct and indirect costspp. 17-18Matches
Project manager pay is a direct costp. 19Matches
A material takeoff lists quantitiesp. 25Matches
Estimate from quantities, current quotations and checked specificationspp. 27-28Matches; both documents say the exercise prices are assumptions, not the firm quotes the deck asks for
Bottom-up estimationpp. 33-34Matches
Monitor spending while there is still time to reactpp. 52-54Matches

Read with careNo contradiction with the deck was found. The final submitted PDF keeps the same claims without page numbers. Every number in the case was also recomputed, and all match both documents.

Reference appendix

What the guide adds, and what to read with care

Read with care

Assumptions, not quotations

The garden’s size, every quantity and price, the crew sizes, the 12% rate and the 10% contingency are the author’s assumptions. The brief supplies only the activities, the £100 worker-day and the 10% to 15% overhead range.

Short of the deck’s best practice

Week 7 asks for recent quotes, and firm vendor quotes for significant items. The exercise uses assumed rates; the submission says so, and makes confirming quotations the first step of its control plan.

A management column without the manager

The brief’s column is headed “Management / Overhead”, but the supervisor is charged in labour. This follows the deck’s slide 19, where project manager pay is direct, rather than slide 12, which lists management salaries under overhead.

Effort, not duration

17 worker-days is paid effort. The cost sheet sets no calendar, and the case does not invent one.

The gravel line

The submission writes “0.5 tonnes × £80 = £40”; £80 is the rate per tonne. The arithmetic is right; the wording can mislead.

Pence are not precision

Totals carry pence because of the 12% rate, not because the estimate is accurate to the penny. The guide says so.

Study connections are this case’s own

The equipment and bulk reading in Part 3, the AACE placing in Part 5 and the earned value illustrations in Part 6 and the practice apply Week 7 to the garden. Neither document makes them.

Two versions of the submission

The case was first built from the submission’s working draft, which cites deck pages and ends with a reference list. The final three-page PDF has the same cost sheet, numbers, scope, takeoff, labour, contingency and control plan, but drops the page citations and the reference list. One sentence lost its page cite and now reads “the quantity-based estimating approach in Week .”, with the number missing. Nothing in the case changes; deck pages cited here are the case’s own checks.

The brief is described, not reproduced

No brief file was supplied. Its requirements are taken from what both documents state. The due date and upload steps are left out.

Checked against the submission, the explanation guide and the Week 7 deck.

Key points from the explanation guide

  • The exercise tests a reasonable scope, visible assumptions, the required rules, and totals that agree (Guide · what the exercise is asking).
  • Bottom up makes a change traceable: one extra bench changes D, not an unexplained lump sum (Guide · why bottom up).
  • Four small beds need different timber and soil from ten large ones, so the scope comes before the price (Guide · scope).
  • Soil sits in B only, so it is not paid for twice (Guide · materials).
  • 17 worker-days are £1,700 of paid effort, not 17 calendar days (Guide · labour).
  • A column called Management / Overhead does not require all managerial work to sit in it (Guide · overhead).
  • Never apply 12% again to a total that already includes overhead; £100 of direct cost becomes £112 (Guide · checking).
  • Overhead pays for expected shared support; contingency allows for uncertainty (Guide · interpreting).
  • Less spending alone does not prove a saving if the work is unfinished (Guide · real project).