Planning & Controls · probabilistic schedule analysis reference
Glossary
Short definitions as the module uses them, each linked to the lesson it comes from.
- Probabilistic schedule analysis
An examination of possible duration outcomes and completion-date probabilities under stated modeling assumptions.
Review Lesson 1- Mean
The total of the observations divided by their number.
Review Lesson 1- Median
The middle of the ordered observations.
Review Lesson 1- Mode
The value that occurs most often, corresponding to the most likely input in the three-point estimate.
Review Lesson 3- Standard deviation
A measure of spread around the mean, in the duration's original units.
Review Lesson 1- Variance
The square of standard deviation, expressed here in days squared.
Review Lesson 3- Positive skew
An asymmetric distribution with a longer right tail, allowing unusually long durations.
Review Lesson 1- Kurtosis
A description of tail weight and extreme observations.
Review Lesson 1- Anchoring
An estimation bias in which the first estimate influences later estimates.
Review Lesson 1- Rolling wave planning
Adding detail to near-term work while keeping later work at a higher level until information improves.
Review Lesson 2- PERT
The course's three-point estimating approach using (a + 4m + b) ÷ 6 for expected duration and (b − a) ÷ 6 for approximate standard deviation.
Review Lesson 3- Path dependence
Connection between path-duration outcomes, as when both routes contain the same activity or respond to a common risk.
Review Lesson 4- Monte Carlo simulation
Repeated sampling of uncertain inputs and recalculation of the network to collect a distribution of finishes and criticality outcomes.
Review Lesson 5- Beta-PERT
A smooth bounded duration model using three-point estimates, listed separately from triangular in the deck.
Review Lesson 5- P80
The completion date by which eighty percent of modeled outcomes have finished, leaving twenty percent later.
Review Lesson 6- Schedule contingency
A time allowance informed by the analysis of schedule uncertainty and the agreed completion confidence.
Review Lesson 6