Planning & Controls · probabilistic schedule analysisLesson 1

Study explanation · Lesson 01 · 9 min

Duration data, variability and estimation bias

An average describes only part of a duration estimate. Examine the center, spread and shape of the evidence, then check how bias can affect the estimate.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Uncertainty remains behind a planned date

An activity's actual duration can be shorter or longer than its estimate. Weather, productivity and deliveries can affect the outcome. A single-estimate schedule assigns one duration to each activity and calculates one finish date. A probabilistic model considers possible durations and the probability of finishing by a specified date. Read probability with its assumptions. Twenty percent means about twenty occurrences in a hundred comparable cases over repeated experience. It does not require exactly twenty occurrences in the next hundred, or describe how much of the work is complete.

Key ideaA planned date becomes more useful when the team can explain the uncertainty around it.

The center depends on the question

The deck's five durations are 3, 4, 4, 5 and 14 days. Their total is thirty, giving a mean of six days. Four is both the middle value and the most frequent value, so the median and mode are four. The long observation pulls the mean upward. Before using these records for another activity, ask what the long duration represents. A relevant delay belongs in the risk discussion. Removing it simply to make the average smaller would hide that evidence.

The five-duration example · slide 3
MeasureCalculation or meaningResult
Mean(3 + 4 + 4 + 5 + 14) ÷ 56 days
MedianMiddle value in the ordered list4 days
ModeMost frequent value4 days

Spread and shape describe additional risk

The native chart on slide 4 contains seven observations for each named series. Dana's mean is four days and sample standard deviation about 0.82 days. Rami's mean is about 6.29 days and sample standard deviation about 3.04 days. These describe different centers and variability in the records. The deck does not establish that their work and conditions are comparable, so the figures alone cannot rank individual performance. A symmetric distribution balances around its center. Positive skew has a longer right tail, making unusually long durations important. Kurtosis concerns tail weight and extreme observations. The slide warns that a small sample cannot establish the full distribution shape.

Observations preserved in slide 4's native chart
SeriesABCDEFGMeanSample SD
Dana34534454 days0.82 days
Rami287593106.29 days3.04 days

Read with careLetters label the chart's seven observations. These records support the displayed statistics, not a performance comparison or a proven distribution.

Bias can change the estimate before any calculation

Optimism makes the team expect fewer delays than the evidence supports. Anchoring lets the first estimate influence later estimates. Availability gives a memorable or recent event excessive weight. Make the evidence and conditions explicit when reviewing a number, including why the next activity resembles the historical work.

Estimation biases · slide 6
BiasEstimate-review question
OptimismWhich plausible delays have we left out?
AnchoringWould our evidence support this number if we had not heard the first estimate?
AvailabilityAre we giving one memorable event more weight than the wider record supports?

Read with careThe questions are study-guide applications of the deck's definitions.

Key takeaways

  • Mean, median and mode describe different features of the same data.
  • Standard deviation measures spread in the duration's original units.
  • Small samples and incomparable work limit the conclusions available.
  • Review estimation bias alongside the evidence.

Based on Week 3_ Probabilistic Schedule Analysis.pptx by Farah Demachkieh, Ph.D. Source notes identify slide coverage; practice and reflections are study-guide additions.

Your study checkpoint

Ready to continue?

Mark the lesson complete once you have read it and tried its idea on something real.

Next · Lesson 2