Project Planning, Scheduling and Controls - FA26-27 · Assignment project
Project Scheduling and Network Analysis
Work through five completed networks, explain the controlling dates and understand the flexibility between activities.
A guided study of Fadi Zahhar's completed scheduling assignment: five networks, complete activity tables, delay effects, mixed precedence and float, followed by the learning guide's separate PERT and expected-value example.
- CPM
- AON and AOA
- Early and late dates
- Critical paths
- FS, SS, FF and SF
- Total and free float
- Delay effects
- PERT and EMV extension
Project introduction
Make each date explain the work
The completed assignment gives the results; the companion guide explains how to discuss them confidently. Begin with the model and time conventions, then work through the five exercises. Keep every relationship visible and ask which start or finish restriction controls the next decision. The final lesson extends the learning through a separate hypothetical example of uncertainty and financial value. Use the summary and practice to explain the reasoning in your own words.
- Set the methodModel, time and endpoint restrictions
- Work the networksFive complete examples and date tables
- Explain flexibilityDelay effects and shared float
- Extend carefullySeparate PERT, probability and value example