Project Scheduling and Network Analysis

Work through five completed networks, explain the controlling dates and understand the flexibility between activities.

A guided study of Fadi Zahhar's completed scheduling assignment: five networks, complete activity tables, delay effects, mixed precedence and float, followed by the learning guide's separate PERT and expected-value example.

  • CPM
  • AON and AOA
  • Early and late dates
  • Critical paths
  • FS, SS, FF and SF
  • Total and free float
  • Delay effects
  • PERT and EMV extension

Project introduction

Make each date explain the work

The completed assignment gives the results; the companion guide explains how to discuss them confidently. Begin with the model and time conventions, then work through the five exercises. Keep every relationship visible and ask which start or finish restriction controls the next decision. The final lesson extends the learning through a separate hypothetical example of uncertainty and financial value. Use the summary and practice to explain the reasoning in your own words.

Your path through the scheduling assignment
  1. Set the methodModel, time and endpoint restrictions
  2. Work the networksFive complete examples and date tables
  3. Explain flexibilityDelay effects and shared float
  4. Extend carefullySeparate PERT, probability and value example

Your learning path

Your path through the assignment

Open source guide
01Model and methodA useful scheduling calculation begins with the right model. Identify the activities, preserve every relationship, state the time convention, then calculate early dates, late dates and float. The five completed exercises use fixed durations; the companion guide explains what those assumptions leave open.9 min02Exercise 1 · Paths and delaysKen's network takes twenty weeks and has two critical paths. Work through the five complete routes, the activity dates and the separate delay tests. The useful management question is which restriction changes when an activity takes longer.8 min03Exercise 2 · Events and floatThe activity-on-arrow network finishes at the end of day fifteen. Use event times to calculate the schedule, convert the activity labels consistently, then compare total, free, interfering and independent float through H and G.9 min04Exercise 3 · Mixed relationshipsThis six-activity network combines all four relationship types. Preserve the two A-to-B conditions and both diagonal arrows, then explain why the project finishes at twenty-seven time units with two controlling sequences.8 min05Exercise 4 · RestrictionsThe engineering network finishes after thirty-four working days. Compare the two D-to-J conditions, explain how K can start before H, and trace the controlling endpoint sequence through A, C, F, I and L.9 min06Exercise 5 · Shared floatBuild the forty-five-day schedule one restriction at a time, then reverse the conditions to find the latest dates. F and G both have five days of total float, but their different free floats explain how that allowance is shared.11 min07Extension · PERT and valueThe guide uses a separate invented X–Y–Z sequence to explain uncertainty and financial decisions. Follow its three-point estimates, approximate deadline probability and expected monetary value while keeping those assumed inputs separate from the five completed networks.9 minExplain the schedule, then check its limitsThe five completed networks show how dependencies control dates, how float differs across activities and why overlap changes the calculation. A separate guide example introduces PERT, probability and monetary value using explicit invented inputs.Summary