Assignment · Project Scheduling and Network Analysis
Where each part comes from, what was not supplied, and the places where the material needs a careful reading.
The sources
This study path uses two supplied files dated 11 November 2026: FadiZahhar_Assignment_ProjectScheduling.docx, the student's completed analysis, and FadiZahhar_LearningGuide_ProjectScheduling.pdf, its 15-page companion explanation. The DOCX contains five reproduced networks, complete result tables, embedded equations, assumptions and references. The guide explains the calculations and adds an explicitly separate invented X–Y–Z example for PERT, probability and expected monetary value. Both documents cite an original assignment as [A], but that original brief was not supplied here. This path explains the supplied work; it does not claim to reproduce official instructions, grading criteria or an independently verified answer key. Practice questions, scenarios and the lesson organization are study-guide additions.
Listening
Use Listen on lesson and summary pages for the same Marin AI narration as the other narrated courses, with sentence and word highlighting. Back to the project →
Where the assignment lessons come from
Lesson
Completed assignment coverage
Learning guide pages
1 · Model and method
Calculation conventions; Notation; Calculation method and references
2–4, 6, 11 and 14
2 · Exercise 1
Network, five paths, activity times and delay effects
5; check on 14
3 · Exercise 2
AOA network, event times, dates and requested floats
3 and 6
4 · Exercise 3
Mixed relationships, all dates, forward/backward pass and free float
7
5 · Exercise 4
Engineering network, simultaneous constraints and all activity times
8
6 · Exercise 5
Precedence network, early/late dates and requested floats
9–11
7 · Separate extension
Not an additional solved assignment exercise
12–13; boundary on 14
Recap and practice
Five-exercise results and stated calculation assumptions
1 and 14; references on 15
Part 01
Build the network and keep time consistent
A useful scheduling calculation begins with the right model. Identify the activities, preserve every relationship, state the time convention, then calculate early dates, late dates and float. The five completed exercises use fixed durations; the companion guide explains what those assumptions leave open.
Fixed durations, elapsed time, inclusive day labels, zero-lag interpretations and the relationship conversion table.
Completed assignment · Calculation conventions; Notation; Calculation method and references
Model, time and float
AON and AOA, resource assumptions, time conversion, endpoint restrictions and verification.
Learning guide · pp. 2–4, 6, 11 and 14
Part 02
Exercise 1 Two critical paths and three delay tests
Ken's network takes twenty weeks and has two critical paths. Work through the five complete routes, the activity dates and the separate delay tests. The useful management question is which restriction changes when an activity takes longer.
The complete network, five paths, fourteen-activity table and separate delay scenarios.
Completed assignment · Exercise 1 Network and paths; Activity times and delay effects
Meaning of the result
M's merge, I's latest start, the deadline and near-critical monitoring.
Learning guide · p. 5; understanding check on p. 14
Part 03
Exercise 2 Events, inclusive dates and four kinds of float
The activity-on-arrow network finishes at the end of day fifteen. Use event times to calculate the schedule, convert the activity labels consistently, then compare total, free, interfering and independent float through H and G.
Event times, four complete paths, activity dates, floats and the requested H and G calculations.
Completed assignment · Exercise 2 Activity on arrow network; Activity dates and floats
Day conversion and float meaning
How elapsed event times produce inclusive dates, and why the float measures differ.
Learning guide · pp. 3 and 6
Part 04
Exercise 3 Overlap and two controlling sequences
This six-activity network combines all four relationship types. Preserve the two A-to-B conditions and both diagonal arrows, then explain why the project finishes at twenty-seven time units with two controlling sequences.
Simultaneous relationships, diagonal-arrow assumptions, complete activity table and forward/backward calculations.
Completed assignment · Exercise 3 Activity on node network; Activity times and working
Overlap and controlling sequences
Step-by-step explanation of B, E and F, and why duration sums are inappropriate.
Learning guide · p. 7
Part 05
Exercise 4 Simultaneous restrictions and start-to-finish logic
The engineering network finishes after thirty-four working days. Compare the two D-to-J conditions, explain how K can start before H, and trace the controlling endpoint sequence through A, C, F, I and L.
The explicit D-to-J pair, SF interpretation, I-to-L assumption and all ten activity rows.
Completed assignment · Exercise 4 Engineering project network; Activity times and critical activities
Endpoint explanation
The C/F overlap, J's stronger restriction, H/K timing and L's three conditions.
Learning guide · p. 8
Part 06
Exercise 5 Lags, late dates and shared flexibility
Build the forty-five-day schedule one restriction at a time, then reverse the conditions to find the latest dates. F and G both have five days of total float, but their different free floats explain how that allowance is shared.
The full precedence diagram, early/late activity table and requested float calculations.
Completed assignment · Exercise 5 Precedence diagram and forward pass; Activity times and requested floats
Reasoning through the schedule
The early schedule, reversed conditions, shared allowance and duration-change distinction.
Learning guide · pp. 9–11
Part 07
Learning extension PERT, deadline probability and expected value
The guide uses a separate invented X–Y–Z sequence to explain uncertainty and financial decisions. Follow its three-point estimates, approximate deadline probability and expected monetary value while keeping those assumed inputs separate from the five completed networks.
Invented estimates, classical formulas, independence assumption and path variance.
Learning guide · p. 12
Probability and financial extension
Normal approximation, merge and correlation caveats, invented outcomes and EMV.
Learning guide · p. 13; boundary reiterated on p. 14
Source appendix
Where the material needs a careful reading
Read with care
Completed work is the source
The DOCX is the student's completed analysis, not the original assignment instructions. The original brief cited as [A] was not supplied, so these pages do not establish official requirements, marking criteria or independent answer verification.
Keep the units and time labels
Exercises 1, 3, 4 and 5 use elapsed time from zero. Exercise 2 uses inclusive activity-day labels while its event calculations remain elapsed. Exercise 3 has no specified unit; Exercise 4 uses working days.
Preserve the stated interpretations
Unlabeled and unqualified relationships are interpreted as FS 0. This includes the Exercise 3 diagonals and Exercise 4 I-to-L link. Both A-to-B conditions in Exercise 3 and D-to-J conditions in Exercise 4 apply simultaneously. Crossing lines in Exercise 3 are not a junction.
Fixed durations and sufficient resources
The calculations keep the given durations fixed, permit the stated overlaps, impose no extra crew or equipment restrictions and add no calendar exceptions. All activities must finish by project completion. These assumptions need confirmation for a real delivery plan.
Float and duration changes differ
Total float measures movement of a fixed-duration activity. Mixed SS, FF and SF relationships may respond differently to an isolated duration change. Recalculate the affected endpoints rather than assuming every zero-float duration increase has the same effect.
Delay tests are separate
Exercise 1's two-week increases to I, H and J each begin at the original schedule. They are not cumulative changes.
The uncertainty example is separate
The five networks supply no optimistic, most likely or pessimistic estimates and no bidding amounts. The PERT, 84.13% probability and $4,730.76 EMV belong only to the guide's invented X–Y–Z example and its explicit assumptions.
References are carried from the supplied files
The resource links are the method references recorded in the source documents. They are not additional course material independently reviewed for this addition. The guide distinguishes practitioner conference papers from the formal PMI standard.
Checked against the supplied documents cited in each note.
What not to take away
The lessons actively work against these misreadings:
Activity letters require alphabetical execution or missing letters must be added.
AOA events have activity durations of their own.
Starting the day labels at one adds an extra day to completion.
The forward pass chooses the smallest incoming requirement.
Every arrow means finish-to-start.
A positive lag requires an exact gap rather than a minimum interval.
An SF successor cannot start before its predecessor.
All connected activity durations can be added despite overlap.
A noncritical activity cannot become controlling after a delay.
Each activity owns its total float independently of its neighbors.
Free float and independent float always have the same value.
The Exercise 1 delay tests should be combined.
A deterministic finish supplies a deadline probability.
The invented X–Y–Z probability applies to Ken's network.
Expected monetary value is a guaranteed profit or an actual bid.
Study-guide synthesis; each item is addressed in the parts.