Planning & Controls · Scheduling assignmentPart 7

Study explanation · Part 07 · 9 min

Learning extension PERT, deadline probability and expected value

The guide uses a separate invented X–Y–Z sequence to explain uncertainty and financial decisions. Follow its three-point estimates, approximate deadline probability and expected monetary value while keeping those assumed inputs separate from the five completed networks.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The five exercises do not supply uncertainty inputs

The companion guide says the course purpose mentions PERT, probabilities and bidding, while the supplied exercise data contain fixed durations. They provide no optimistic, most likely or pessimistic estimates and no financial inputs for a bid. You therefore cannot calculate a defensible deadline probability or actual bidding recommendation for those networks from these sources. The guide introduces an entirely separate project with three activities, X followed by Y followed by Z. Its durations, outcomes and probability assumptions are invented teaching values. Keep that boundary visible: the probability and money results in this lesson apply only to this example, not to Ken or the other completed exercises.

Read with careThe following X–Y–Z example is additional learning from the guide, not another answer to the assignment.

Use the three estimates to calculate mean and variance

Let a be the optimistic estimate, m the most likely estimate and b the pessimistic estimate. The classical PERT expected duration is a plus four times m plus b, divided by six. The approximate standard deviation is b minus a, divided by six. Variance is that standard deviation squared. For X, the estimates are two, five and eight days. Its mean is two plus four times five plus eight, divided by six, giving five days. Its standard deviation is eight minus two, divided by six, giving one day, and its variance is one day squared. Y's estimates are one, seven and thirteen, giving a seven-day mean and variance four. Z's estimates are two, eight and fourteen, giving an eight-day mean and variance four. The expected sequence duration is five plus seven plus eight, or twenty days. Assuming independent activity durations, add the variances: one plus four plus four gives nine days squared. The sequence standard deviation is the square root of nine, or three days. Add variances before taking the square root; adding individual standard deviations would give a different and incorrect result for this assumption.

Invented PERT teaching values for the separate X–Y–Z sequence
ActivityOptimistic aMost likely mPessimistic bMean in daysVariance in days²
X25851
Y171374
Z281484

Read with careExpected duration = (a + 4m + b) ÷ 6. Standard deviation ≈ (b − a) ÷ 6. Variance is standard deviation squared.

A probability needs an explicit distribution assumption

Now assume the total duration of this teaching sequence can be approximated by a normal distribution with mean twenty days and standard deviation three. A twenty-three-day deadline is one standard deviation above the mean. The standardized value z is twenty-three minus twenty, divided by three, which equals one. The standard normal cumulative probability at one gives approximately 84.13 percent for finishing by day twenty-three. This is a conditional classroom calculation. With only three activities, the normal approximation has not been established as a validated forecast. In a larger network, another route may become longest, and shared risks can make durations move together. A single-path calculation may understate risk where routes merge. The 84.13 percent result cannot be transferred to Ken's twenty-week schedule.

Key ideaA deterministic finish date alone supplies no numerical probability of meeting it.

Weight each financial outcome by its probability

Continue with the same invented sequence. Assume an on-time outcome produces a net profit of six thousand dollars and a late outcome a net loss of two thousand dollars. Those amounts already include the relevant costs, and the two outcomes are mutually exclusive and cover all cases. Expected monetary value, or EMV, weights each outcome by its probability. Using the unrounded probability, the calculation is 0.8413447 times six thousand dollars plus 0.1586553 times negative two thousand dollars. The result is four thousand seven hundred thirty dollars and seventy-six cents. It is an average for comparing alternatives under the assumptions, not the amount this one project will earn. The modeled outcome is either the six-thousand-dollar profit or the two-thousand-dollar loss. An actual bid also needs price, costs, contractual consequences and acceptable loss exposure. If a penalty depends on the number of days late, a single probability of being late is insufficient; probabilities for the different delay lengths are needed. The example explains the method without inventing those missing commercial facts.

Invented financial outcomes and expected value
OutcomeProbability usedNet outcome
On time0.8413447$6,000 profit
Late0.1586553$2,000 loss
Expected monetary valueProbability-weighted sum$4,730.76

Key takeaways

  • The PERT and financial inputs belong only to the guide's invented X–Y–Z example.
  • Its expected duration is twenty days, variance nine and standard deviation three days.
  • A normal approximation gives about 84.13 percent by day twenty-three under the stated assumptions.
  • Its EMV is $4,730.76; a realized outcome remains a profit or a loss.
  • A real probability forecast or bid needs evidence beyond the five fixed-duration networks.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.