Planning & Controls · Scheduling assignmentSummary

Project summary · 7 min

Explain the schedule, then check its limits

The five completed networks show how dependencies control dates, how float differs across activities and why overlap changes the calculation. A separate guide example introduces PERT, probability and monetary value using explicit invented inputs.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Keep the five results and their units together

Exercise 1 finishes in twenty weeks, controlled by B–E–J–M and C–G–L–N. Its separate two-week increases to I, H and J give finishes of twenty, twenty-one and twenty-two weeks. Exercise 2 finishes in fifteen days through B–E–I, displayed as completion at the end of day 15. H has one day of interfering float, and G has zero independent float. Exercise 3 finishes in twenty-seven time units through A–B–D–E and A–B–D–F; C alone has two units of total and free float. Exercise 4 finishes in thirty-four working days through A–C–F–I–L. Exercise 5 finishes in forty-five days through A–C–D–E–H; F and G share five days of flexibility, with free floats of zero and five respectively.

The five completed results at a glance
ExerciseDurationCritical path or controlling sequence
120 weeksB–E–J–M and C–G–L–N
215 daysB–E–I
327 time unitsA–B–D–E and A–B–D–F
434 working daysA–C–F–I–L
545 daysA–C–D–E–H

Read with careMixed-precedence sequences are traced through their actual endpoints and lags. Their activity durations cannot simply be added.

Explain what makes a restriction controlling

Forward calculations take the largest required start because every incoming condition must hold. Backward calculations reverse the conditions and take the smallest permissible latest-start limit. Ordinary FS zero permits duration sums along serial paths. Mixed links require attention to starts and finishes, so connected boxes alone do not establish a serial path. In Exercise 4, J starts at thirteen because FF plus two is stricter than SS plus three. K begins before H because their link restricts K's finish from H's start. In Exercise 5, H overlaps E because their FF zero link restricts finishes. These results follow different endpoint restrictions, not exceptions to the stated rules.

  • Total float Shift while preserving project completion.
  • Free float Shift while preserving immediate successors' early timing.
  • Interfering float Total float minus free float.
  • Independent float What remains with late predecessors and early successors.

Keep uncertainty and money tied to their inputs

The five networks use fixed durations and supply no three-point uncertainty estimates or bidding amounts. The guide's separate X–Y–Z example has an expected duration of twenty days, variance nine days squared and standard deviation three days. A normal approximation gives about 84.13 percent by day twenty-three. Invented net outcomes of a six-thousand-dollar profit or two-thousand-dollar loss give an expected monetary value of $4,730.76. Those figures remain conditional teaching results. They are not probabilities or financial recommendations for the five networks. A real forecast must examine the estimates, dependence between activities, alternative paths and practical resources. A commercial decision also needs costs, price, contract effects and acceptable exposure.

Use a checked schedule to guide action

The guide connects calculation to management: record scope, owners, dependencies, calendars, duration assumptions and resource availability. Check that every required activity is connected and each timing relationship has a practical explanation. Keep lags visible; where a waiting interval contains real work, consider modeling that work explicitly in a real project. Monitor the controlling activities and relationships alongside near-critical branches. Recalculate when actual progress changes, compare the forecast with the approved baseline, record approved changes and communicate the consequences. Available float alone does not replace schedule risk analysis or establish how much contingency the project needs.

  • Preserve the complete network and state the time convention.
  • Check every interval, relationship and terminal finish.
  • Explain float as a connected timing allowance.
  • Distinguish a whole-activity shift from a duration change under mixed links.
  • State the extra assumptions before quoting a probability or expected value.
  • Revisit the forecast as actual progress and approved decisions change.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.