Exercise 1 Two critical paths and three delay tests

Ken's network takes twenty weeks and has two critical paths. Work through the five complete routes, the activity dates and the separate delay tests. The useful management question is which restriction changes when an activity takes longer.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Both terminal branches must finish

All relationships in Exercise 1 are finish-to-start with zero lag. The completed network has five routes. A–D–H–M totals nineteen weeks. A–I–M totals seventeen. B–E–J–M totals twenty. C–F–K–N totals sixteen. C–G–L–N totals twenty. Both M and N must finish, so the project duration is twenty weeks and the critical paths are B–E–J–M and C–G–L–N. Ken's twenty-week deadline is met exactly under the stated fixed durations. There is no project time reserve. This result describes the deterministic schedule; it does not give a probability of on-time completion or guarantee that the estimates will occur.

Exercise 1 activity-on-node network: Start branches to A, B and C; H, I and J merge into M, K and L merge into N, and both terminal activities lead to Finish. The five complete routes are listed below.
Network reproduced from the supplied completed assignment. Node values are weeks; blue marks the critical activities and routes. All links are FS 0 and Start/Finish have zero duration.
All five complete start-to-finish routes
RouteDuration calculationWeeks
A–D–H–M6 + 4 + 3 + 619
A–I–M6 + 5 + 617
B–E–J–M3 + 7 + 4 + 620
C–F–K–N4 + 4 + 3 + 516
C–G–L–N4 + 6 + 5 + 520

Calculate the dates at a merge

M waits for H, I and J. Their earliest finishes are thirteen, eleven and fourteen, so M starts at the maximum, fourteen, and finishes at twenty. N waits for K at eleven and L at fifteen, so it starts at fifteen and finishes at twenty. Selecting the earliest incoming finish would let work begin before all its predecessors were complete. Working backward from twenty, M must start by fourteen. I must therefore finish by fourteen. Its duration is five, so its latest start is nine. I's early start is six, giving three weeks of total float. The table records the same forward and backward process for every activity. B, E, J, M, C, G, L and N have zero total float.

Exercise 1 complete activity dates in elapsed weeks
ActivityDurationESEFLSLFTF
A606171
B303030
C404040
D46107111
E73103100
F4488124
G64104100
H3101311141
I56119143
J4101410140
K381112154
L5101510150
M6142014200
N5152015200

Read with careTF is total float, also called slack. Each row uses elapsed weeks from zero.

Recalculate each requested delay separately

Each delay test starts from the original schedule. If I takes two extra weeks, it finishes at thirteen. J still controls M's start at fourteen, so the project stays at twenty weeks. If H takes two extra weeks, it finishes at fifteen. M then finishes at twenty-one, one week after the deadline. If J takes two extra weeks, it finishes at sixteen and M finishes at twenty-two, two weeks late. Monitor both critical paths, and keep attention on A–D–H–M. That route is only one week shorter than the project duration. A, D and H share the same one-week flexibility; each does not own an independent week. The H scenario shows how a previously noncritical branch can become controlling.

Separate two-week duration increases
Change from baselineAffected routeProject finishDeadline effect
I adds 2 weeksA–I–M becomes 19 weeks20 weeksStill met
H adds 2 weeksA–D–H–M becomes 21 weeks21 weeks1 week late
J adds 2 weeksB–E–J–M becomes 22 weeks22 weeks2 weeks late

Key ideaAn activity's effect depends on the remaining restrictions at its merge, not only on whether it was critical initially.

Key takeaways

  • Completion requires twenty weeks, with two critical paths.
  • M starts at fourteen because J is its latest-finishing predecessor.
  • The independent I, H and J delay tests give twenty, twenty-one and twenty-two weeks.
  • Near-critical branches and shared float matter when monitoring progress.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.