Copy the work and the relationships first
The completed assignment analyses five project networks. Begin by recording each activity, its duration and every incoming relationship. Activity letters identify the work; they do not tell you to work alphabetically. Exercise 4 contains A, C, D, E, F, H, I, J, K and L, with no B or G. Adding the missing letters would change the model. In an activity-on-node network, usually abbreviated AON, a node contains an activity and arrows describe its timing relationships. In an activity-on-arrow network, or AOA, an arrow is the activity and its numbered endpoints are events. An event marks an instant and has no activity duration of its own. Exercise 2 uses AOA; the other four use AON. The analysis keeps durations fixed, assumes sufficient resources for the stated overlaps and adds no calendar exceptions. Unlabeled relationships are interpreted as finish-to-start with zero lag. Every activity must be complete at the project finish. In a real project, confirm owners, calendars and resource availability before treating the model as a practical delivery commitment.
- ModelActivities, durations and every relationship
- Calculate forwardEarliest permitted dates
- Calculate backwardLatest dates preserving completion
- CheckFloat and every original restriction
Read with careThese sources are the student's completed analysis and its companion explanation. The original assignment instructions cited inside them were not supplied for this course addition.
Choose the labels before counting
Exercises 1, 3, 4 and 5 use elapsed time starting at zero. Earliest finish equals earliest start plus duration. An activity running from zero to five occupies five time units; an ordinary finish-to-start successor can start at five without adding an extra day. Latest start equals latest finish minus duration. Exercise 2 presents starts at the beginning of a numbered day and finishes at its end. Its formula is earliest finish equals earliest start plus duration minus one. A two-day activity runs from the morning of day 1 through the end of day 2, and its ordinary successor starts on day 3. Latest start equals latest finish minus duration plus one. The underlying timeline has not changed. For Exercise 2, B occupies elapsed time zero to two and days 1 to 2. E occupies elapsed time two to ten and days 3 to 10. I occupies elapsed time ten to fifteen and days 11 to 15. The sequence takes fifteen elapsed days and finishes at the end of day 15. Convert elapsed starts by adding one; finishes already identify the last working day. Consistent relabeling leaves float unchanged.
| Exercise | Unit | Date convention |
|---|---|---|
| 1 | Weeks | Elapsed time from zero |
| 2 | Days | Inclusive day labels; events remain elapsed times |
| 3 | Time units | Elapsed time from zero; the diagram supplies no unit |
| 4 | Working days | Elapsed time from zero |
| 5 | Days | Elapsed time from zero |
Key ideaWrite the convention once, then keep every row on that convention.
A relationship restricts particular endpoints
Finish-to-start, or FS, restricts the successor start using the predecessor finish. Start-to-start, or SS, uses the two starts. Finish-to-finish, or FF, uses the two finishes. Start-to-finish, or SF, restricts the successor finish using the predecessor start. A positive lag adds a required interval. These are minimum restrictions: another relationship may make the actual gap larger. Translate each condition into a lower bound on the successor start. For FS, use predecessor finish plus lag. For SS, use predecessor start plus lag. For FF, use predecessor finish plus lag minus successor duration. For SF, use predecessor start plus lag minus successor duration. If several conditions apply, all must hold, so the forward pass takes the largest required start. The backward pass preserves the calculated finish, reverses each restriction and takes the smallest permissible latest-start limit. For ordinary FS with zero lag, these rules reduce to maximum predecessor earliest finish moving forward and minimum successor latest start moving backward. SS can permit overlap, and SF can permit a successor to start before its predecessor. Check the specified endpoints before deciding that a date is wrong.
| Relationship | Required lower bound on successor start |
|---|---|
| FS + lag | Predecessor finish + lag |
| SS + lag | Predecessor start + lag |
| FF + lag | Predecessor finish + lag − successor duration |
| SF + lag | Predecessor start + lag − successor duration |
Read with careFF also abbreviates free float in the results. Read the context: an FF relationship is a finish-to-finish condition; an FF value is an amount of free float.
Ask which kind of flexibility you mean
ES and EF are earliest start and finish. LS and LF are latest start and finish without extending the calculated project finish. Total float, or TF, is LS minus ES, which also equals LF minus EF for a fixed duration. It asks how far an activity can move while preserving project completion. Free float asks how far it can move without moving an immediate successor's early timing. Interfering float is total float minus free float. Independent float asks what remains when predecessors use late timing while successors keep early timing. For an AOA arrow from event i to event j with duration d, let E be an earliest event time and L a latest event time. Total float is L(j) minus E(i) minus d. Free float is E(j) minus E(i) minus d. Independent float is the greater of zero and E(j) minus L(i) minus d. Mixed-precedence networks require the actual linked endpoints and lags when calculating flexibility. Positive float is a timing window within a connected network. Several activities can share it, so their individual total floats cannot simply be added. Zero total float means a fixed-duration activity cannot shift later without affecting completion. Under mixed relationships, an isolated duration increase can behave differently from shifting the whole activity; recalculate the restrictions.
- Every interval matches its duration on the stated time convention.
- Every original relationship and lag is satisfied.
- ES does not exceed LS, and total float agrees from starts and finishes.
- All terminal activities fit the same project finish.
- The controlling start or finish endpoint is identified for mixed links.
Key takeaways
- A correct model preserves all activities, arrows and simultaneous conditions.
- Elapsed time and inclusive day labels describe the same timeline when converted consistently.
- Take the strongest lower bound forward and the tightest permissible limit backward.
- Float measures different kinds of flexibility and may be shared along a chain.