Planning & Controls · Scheduling assignmentPart 5

Study explanation · Part 05 · 9 min

Exercise 4 Simultaneous restrictions and start-to-finish logic

The engineering network finishes after thirty-four working days. Compare the two D-to-J conditions, explain how K can start before H, and trace the controlling endpoint sequence through A, C, F, I and L.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The critical sequence contains overlapping activities

A runs from zero to five working days. The SS plus eight link to C places C at eight to eleven. C-to-F is FF plus five. F must finish at least five days after C, at sixteen; its eight-day duration places its start at eight. C and F therefore start together while finishing five days apart. F-to-I is FS plus three, so I runs from nineteen to twenty-four. I-to-L is unlabeled in the source network and is interpreted as FS zero, placing L at twenty-four to thirty-four. The controlling sequence is A–C–F–I–L through SS plus eight, FF plus five, FS plus three and FS zero. Adding those activity durations would ignore the actual endpoint relationships.

Exercise 4 engineering network: A branches through C–F–I, D–J and E–H–K; all three branches constrain L. The blue controlling sequence is A–C–F–I–L. Each endpoint type and lag is listed below.
Network reproduced from the supplied completed assignment. Node values are working days and blue marks the controlling sequence. Both D-to-J conditions apply; I-to-L is interpreted as FS 0.
The complete relationship model used by the completed analysis
FromToRelationship
ACSS +8
ADFS +2
AESS +5
CFFF +5
DJSS +3 and FF +2, both applying
EHFS 0
FIFS +3
HKSF +3
ILFS 0, interpreted unlabeled arrow
JLFF +5
KLFS +4

J must satisfy two conditions from D

D begins two days after A finishes and runs from seven to seventeen. D-to-J has SS plus three and FF plus two. The SS condition permits J to start at ten. The FF condition requires J to finish at least at nineteen; J's six-day duration therefore requires a start of thirteen. Select thirteen because both conditions must hold. J runs from thirteen to nineteen. The calculation is the maximum of seven plus three and seventeen plus two minus six. FF plus two is controlling here. Selecting ten would respect the start condition while breaking the finish condition. A relationship with a positive lag means at least that interval; it does not require an exact gap if another condition is stronger.

L takes the strongest of three incoming conditions

I's finish requires L to start at twenty-four. J-to-L is FF plus five: J finishes at nineteen, so L must finish at least at twenty-four. Since L lasts ten days, this permits a start at fourteen. K-to-L is FS plus four, requiring a start at twelve plus four, or sixteen. The maximum of twenty-four, fourteen and sixteen is twenty-four, giving a project finish of thirty-four working days. Working backward, J's latest start is thirty-four minus five minus six, or twenty-three. Reversing both D-to-J conditions gives D a latest start of seventeen. K must finish by L's latest start of twenty-four minus four, so its latest finish is twenty and its latest start thirteen. Reversing H-to-K then gives H a latest start of twenty minus three, or seventeen. The complete table gives A, C, F, I and L zero total float. D and J have ten days, while E, H and K have eight. These are fixed-duration shift allowances. An isolated duration change still needs recalculation through the relevant start and finish restrictions.

Exercise 4 complete dates and total float in elapsed working days
ActivityDurationESEFLSLFTF
A505050
C38118110
D10717172710
E45913178
F88168160
H1392217308
I5192419240
J61319232910
K751213208
L10243424340

Key takeaways

  • The engineering network takes thirty-four working days.
  • J starts at thirteen because its FF condition is stricter than its SS condition.
  • K's interval of five to twelve satisfies the SF +3 condition from H's start at nine.
  • I controls L's start at twenty-four; the other two incoming conditions also hold.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.