Planning & Controls · Scheduling assignment reference

Glossary

Short definitions as the project uses them, each linked to the part it comes from.

Critical Path Method (CPM)

The scheduling method used in the completed analysis to calculate early and late dates, float and the relationships controlling project completion.

Review Part 1
Activity-on-node (AON)

A network with activities in nodes and timing relationships on arrows.

Review Part 1
Activity-on-arrow (AOA)

A network with activities on arrows and numbered events at their endpoints.

Review Part 3
Event

A point in time in an AOA network; it occurs after every incoming activity is complete and has no activity duration of its own.

Review Part 3
Predecessor

An activity whose timing restricts another activity.

Review Part 1
Successor

An activity whose timing is restricted by another activity.

Review Part 1
Lag

A stated interval in a relationship; a positive lag adds a minimum interval between the specified endpoints.

Review Part 1
Earliest start and finish (ES and EF)

The earliest permitted start and finish under the modeled durations and relationships.

Review Part 1
Latest start and finish (LS and LF)

The latest dates that preserve the calculated project finish with the modeled durations and relationships.

Review Part 1
Elapsed time

A time scale beginning at zero, with finish equal to start plus duration.

Review Part 1
Inclusive day labels

Beginning-of-day start labels and end-of-day finish labels; finish equals start plus duration minus one.

Review Part 3
Finish-to-start (FS)

A relationship requiring successor start to be at least predecessor finish plus lag.

Review Part 1
Start-to-start (SS)

A relationship requiring successor start to be at least predecessor start plus lag.

Review Part 4
Finish-to-finish (FF relationship)

A relationship requiring successor finish to be at least predecessor finish plus lag.

Review Part 5
Start-to-finish (SF)

A relationship requiring successor finish to be at least predecessor start plus lag; it can permit the successor to begin before the predecessor.

Review Part 5
Forward pass

Calculation of earliest dates by satisfying every incoming restriction and selecting the strongest lower bound.

Review Part 1
Backward pass

Calculation of latest dates by preserving the project finish, reversing restrictions and choosing the tightest limit.

Review Part 6
Critical path or controlling sequence

A route of binding relationships that controls completion; mixed-precedence timing follows linked endpoints rather than a simple duration sum.

Review Part 4
Total float (TF)

The amount a fixed-duration activity can shift without moving project completion; LS − ES equals LF − EF.

Review Part 1
Free float

The amount an activity can shift without moving its immediate successors' early timing, respecting the linked endpoints and lags.

Review Part 3
Interfering float

Total float minus free float; the part of the allowance that affects following early timing.

Review Part 3
Independent float

Remaining flexibility when predecessors use late timing while successors keep early timing, with a minimum of zero.

Review Part 6
Near-critical route

A route close to the controlling duration, such as Exercise 1's nineteen-week branch within a twenty-week project.

Review Part 2
Program Evaluation and Review Technique (PERT)

The guide's learning extension using optimistic, most likely and pessimistic estimates to calculate expected durations and approximate uncertainty.

Review Part 7
Variance

The square of standard deviation; independent activity variances are added for the guide's simple sequence.

Review Part 7
Expected monetary value (EMV)

The sum of each modeled financial outcome multiplied by its probability; an average, not a guaranteed realized result.

Review Part 7