Planning & Controls · Scheduling assignment reference
Glossary
Short definitions as the project uses them, each linked to the part it comes from.
- Critical Path Method (CPM)
The scheduling method used in the completed analysis to calculate early and late dates, float and the relationships controlling project completion.
Review Part 1- Activity-on-node (AON)
A network with activities in nodes and timing relationships on arrows.
Review Part 1- Activity-on-arrow (AOA)
A network with activities on arrows and numbered events at their endpoints.
Review Part 3- Event
A point in time in an AOA network; it occurs after every incoming activity is complete and has no activity duration of its own.
Review Part 3- Predecessor
An activity whose timing restricts another activity.
Review Part 1- Successor
An activity whose timing is restricted by another activity.
Review Part 1- Lag
A stated interval in a relationship; a positive lag adds a minimum interval between the specified endpoints.
Review Part 1- Earliest start and finish (ES and EF)
The earliest permitted start and finish under the modeled durations and relationships.
Review Part 1- Latest start and finish (LS and LF)
The latest dates that preserve the calculated project finish with the modeled durations and relationships.
Review Part 1- Elapsed time
A time scale beginning at zero, with finish equal to start plus duration.
Review Part 1- Inclusive day labels
Beginning-of-day start labels and end-of-day finish labels; finish equals start plus duration minus one.
Review Part 3- Finish-to-start (FS)
A relationship requiring successor start to be at least predecessor finish plus lag.
Review Part 1- Start-to-start (SS)
A relationship requiring successor start to be at least predecessor start plus lag.
Review Part 4- Finish-to-finish (FF relationship)
A relationship requiring successor finish to be at least predecessor finish plus lag.
Review Part 5- Start-to-finish (SF)
A relationship requiring successor finish to be at least predecessor start plus lag; it can permit the successor to begin before the predecessor.
Review Part 5- Forward pass
Calculation of earliest dates by satisfying every incoming restriction and selecting the strongest lower bound.
Review Part 1- Backward pass
Calculation of latest dates by preserving the project finish, reversing restrictions and choosing the tightest limit.
Review Part 6- Critical path or controlling sequence
A route of binding relationships that controls completion; mixed-precedence timing follows linked endpoints rather than a simple duration sum.
Review Part 4- Total float (TF)
The amount a fixed-duration activity can shift without moving project completion; LS − ES equals LF − EF.
Review Part 1- Free float
The amount an activity can shift without moving its immediate successors' early timing, respecting the linked endpoints and lags.
Review Part 3- Interfering float
Total float minus free float; the part of the allowance that affects following early timing.
Review Part 3- Independent float
Remaining flexibility when predecessors use late timing while successors keep early timing, with a minimum of zero.
Review Part 6- Near-critical route
A route close to the controlling duration, such as Exercise 1's nineteen-week branch within a twenty-week project.
Review Part 2- Program Evaluation and Review Technique (PERT)
The guide's learning extension using optimistic, most likely and pessimistic estimates to calculate expected durations and approximate uncertainty.
Review Part 7- Variance
The square of standard deviation; independent activity variances are added for the guide's simple sequence.
Review Part 7- Expected monetary value (EMV)
The sum of each modeled financial outcome multiplied by its probability; an average, not a guaranteed realized result.
Review Part 7