Exercise 5 Lags, late dates and shared flexibility

Build the forty-five-day schedule one restriction at a time, then reverse the conditions to find the latest dates. F and G both have five days of total float, but their different free floats explain how that allowance is shared.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Build the early schedule through D, F and G

A runs from zero to five days. B has FS plus five after A, so it runs from ten to fifteen. C has ordinary FS after A and runs from five to twenty. D waits for both B and C; C controls its start at twenty, so D finishes at twenty-five. E starts five days after D starts because their relationship is SS plus five. E runs from twenty-five to forty-five. D also finishes at twenty-five because its duration happens to be five, but that coincidence does not change the SS relationship. C-to-F is FF plus five. C finishes at twenty, so F must finish no earlier than twenty-five. F lasts five days and runs from twenty to twenty-five. C-to-G also has FF plus five. G's ten-day duration would permit fifteen to twenty-five under that condition alone. G must also wait for F to finish, so its actual early interval is twenty-five to thirty-five.

Exercise 5 precedence network: A branches to B and C; B and C constrain D then E, while C also constrains F and G; E, F and G all constrain H. Blue marks A–C–D–E–H. Full relationship types and lags are listed below.
Network reproduced from the supplied completed assignment. Node values are days and blue marks the controlling sequence. Unqualified predecessors are interpreted as FS 0; the E-to-H FF 0 link permits overlap.
Exercise 5 complete precedence model
FromToRelationship
ABFS +5
ACFS 0
BDFS 0
CDFS 0
CFFF +5
CGFF +5
DESS +5
EHFF 0
FGFS 0
FHFS +10
GHFS 0

Read with careThe completed analysis interprets unqualified predecessors as FS with zero lag.

H waits for the strongest endpoint restriction

H has three incoming conditions. FF zero after E requires H to finish at least at forty-five. H lasts five days, so this requires a start at forty. FS plus ten after F requires a start at twenty-five plus ten, or thirty-five. Ordinary FS after G also requires thirty-five. Select forty, making H run from forty to forty-five. The project takes forty-five days. A, C, D, E and H have zero total float, and their controlling sequence uses FS zero, FS zero, SS plus five and FF zero. H overlaps the final five days of E. Adding all five activity durations would incorrectly give fifty because it would treat the overlap as serial work.

Key ideaFF zero means the successor finish cannot precede the predecessor finish. It does not require identical starts.

Work backward from the forty-five-day finish

H's latest start is forty. G must finish by forty, giving its latest start of thirty. E-to-H is FF zero, so E can finish by H's latest finish of forty-five; E's twenty-day duration gives its latest start of twenty-five. F must finish by G's latest start of thirty. The FS plus ten link to H also requires F to finish by forty minus ten, or thirty. Both limits agree, giving F a latest start of twenty-five. D-to-E is SS plus five, so D must start by twenty-five minus five, or twenty. B must finish by D's start at twenty, giving B a latest start of fifteen. C has three successors. D limits C's latest start to twenty minus fifteen, or five. F's FF plus five condition limits it to thirty minus five minus fifteen, or ten. G's FF plus five condition limits it to forty minus five minus fifteen, or twenty. Choose the smallest, five, to preserve all three. A's two successor conditions then give a latest start of zero. B, F and G each have five days of total float; the others have zero.

Exercise 5 complete activity dates and total float in elapsed days
ActivityDurationESEFLSLFTF
A505050
B5101515205
C155205200
D5202520250
E20254525450
F5202525305
G10253530405
H5404540450

F and G share their five-day allowance

F has five days of total float but no free float. G is scheduled to start at F's early finish of twenty-five, so any later F finish moves G. The other outgoing condition, FS plus ten to H, would allow five days, but free float takes the tighter limit. F's free float is the minimum of twenty-five minus twenty-five and forty minus twenty-five minus ten, giving zero. G has five days of free float: H starts at forty and G finishes at thirty-five. If F moves to its latest interval of twenty-five to thirty, G moves to thirty to forty and consumes that same five-day allowance. Their two five-day total floats cannot be added into ten days of reserve. F's interfering float is five minus zero, or five days. For F's independent float, allow C its late finish of twenty. C-to-F FF plus five requires F to finish no earlier than twenty-five, so F must start no earlier than twenty. Keep G's early start at twenty-five: F must start no later than twenty. H's early start would permit F to start as late as twenty-five, but G is tighter. The available independent interval is therefore zero days.

Requested float distinctions in Exercise 5
MeasureResultReason
F total float5 daysLS 25 − ES 20
F free float0 daysG starts as soon as F finishes
G free float5 daysH ES 40 − G EF 35
F interfering float5 daysTF 5 − free float 0
F independent float0 daysLate C and early G both require F start 20

Read with careThe float values concern shifting fixed-duration activities. Under SS and FF links, lengthening an activity can change different endpoints; recalculate before claiming a duration effect.

Key takeaways

  • H's FF condition from E controls a forty-five-day finish.
  • Backward calculations reverse the actual relationship endpoints and choose the tighter limit.
  • B, F and G each have five days of total float.
  • F has zero free and independent float, five interfering; G has five free.
  • F and G share flexibility rather than owning two independent reserves.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.