Exercise 3 Overlap and two controlling sequences

This six-activity network combines all four relationship types. Preserve the two A-to-B conditions and both diagonal arrows, then explain why the project finishes at twenty-seven time units with two controlling sequences.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Keep every original arrow

A lasts eight time units and begins at zero. B lasts twelve and has two incoming restrictions from A: SS plus three and FF plus four. The SS condition requires B to start at least at three. The FF condition requires B to finish at least at twelve, allowing a start at zero for a twelve-unit activity. The stronger restriction is three, so B runs from three to fifteen. B-to-D is FS zero, and B-to-C is SS plus six. C-to-E is labeled FS zero. The completed analysis interprets the unlabeled diagonal D-to-E and C-to-F arrows as FS zero. D-to-F is SF plus twelve. The crossing diagonal lines are not a junction, and the final milestone requires both E and F. The diagram supplies no time unit, so these results stay in time units.

Exercise 3 activity-on-node network: A has SS +3 and FF +4 into B; B links to D and C; both C and D constrain E and F, which lead to Finish. The full endpoint relationships are listed below.
Network reproduced from the supplied completed assignment. Blue marks controlling activities and relationships. The crossing diagonals are not a junction; the completed analysis interprets the unlabeled diagonal arrows as FS 0.
Relationships preserved in Exercise 3
FromToRelationship
ABSS +3 and FF +4, both applying
BCSS +6
BDFS 0
CEFS 0
CFFS 0, interpreted unlabeled arrow
DEFS 0, interpreted unlabeled arrow
DFSF +12

Calculate the strongest restriction forward

C begins six units after B starts, so C runs from nine to thirteen. D waits for B's finish and runs from fifteen to twenty-one. E waits for both C and D; twenty-one is the later finish, so E runs from twenty-one to twenty-seven. F waits for C to finish, requiring a start of at least thirteen. The SF plus twelve relationship from D requires F's finish to be at least D's start of fifteen plus twelve, or twenty-seven. F lasts twelve, so this second condition requires a start of at least fifteen. F therefore runs from fifteen to twenty-seven. D and F start together in this result, although their relationship is SF rather than SS. Both terminal activities finish at twenty-seven. The controlling sequences are A–B–D–E and A–B–D–F. Follow their endpoint timing: three plus twelve plus six plus six gives twenty-seven for the first; three plus twelve plus twelve gives twenty-seven for the second. Adding all activity durations on either connected route would count overlapping time incorrectly.

Key ideaSF +12 constrains F's finish using D's start. It does not make F wait for D's finish.

Use the backward pass to find C's window

Preserve completion at twenty-seven. E's latest start is twenty-one and F's is fifteen. D's latest start is the minimum of twenty-one minus six and fifteen, which is fifteen. C must finish by E's start at twenty-one and F's start at fifteen; with a four-unit duration, its latest start is eleven. B's latest start is the minimum of fifteen minus twelve and eleven minus six, giving three. Reversing both A-to-B conditions then keeps A's latest start at zero. C is the only activity with positive total float: eleven minus nine gives two units. Its free float is the minimum of twenty-one minus thirteen and fifteen minus thirteen, also two. A, B, D, E and F have zero total and free float.

Exercise 3 complete dates and floats in elapsed time units
ActivityDurationESEFLSLFTFFree float
A8080800
B1231531500
C4913111522
D61521152100
E62127212700
F121527152700

Key takeaways

  • Both A-to-B conditions hold, with SS +3 controlling B's start.
  • F finishes at twenty-seven because of the SF +12 condition from D's start.
  • The project has two controlling sequences and finishes at twenty-seven time units.
  • C alone has positive float: two units total and free.

Based on the supplied completed assignment and companion learning guide. The original assignment brief was not supplied; practice is study-guide material.