Each input describes a different part of the estimate
Optimistic a describes a short duration under favorable conditions. Most likely m is the duration expected to occur most often. Pessimistic b describes a long duration under unfavorable conditions. Use comparable scope and conditions for the three values. The most likely value is a mode. PERT's expected duration is a weighted average, which can differ from that most likely value when the range is asymmetric.
| Input | Meaning | Source example |
|---|---|---|
| a · optimistic | Short under favorable conditions | 8 days |
| m · most likely | Expected to occur most often | 10 days |
| b · pessimistic | Long under unfavorable conditions | 16 days |
Calculate duration and variability separately
The course uses expected duration = (a + 4m + b) ÷ 6, estimated standard deviation = (b − a) ÷ 6 and estimated variance = [(b − a) ÷ 6]². For 8, 10 and 16 days, the weighted total is sixty-four. Dividing by six gives about 10.67 days. The standard deviation is about 1.33 days. Squaring the unrounded value gives a variance of about 1.78 days squared. Keep full precision until the final rounding. Variance and expected duration cannot be substituted for one another.
| Quantity | Calculation | Rounded result |
|---|---|---|
| Expected duration | (8 + 4 × 10 + 16) ÷ 6 | 10.67 days |
| Standard deviation | (16 − 8) ÷ 6 | 1.33 days |
| Variance | [(16 − 8) ÷ 6]² | 1.78 days² |
Key ideaThe expected duration supports a model. It does not guarantee the activity's actual finish.
Key takeaways
- Most likely and expected duration can differ.
- Standard deviation uses days; variance uses days squared.
- Round after calculating, rather than before squaring or summing.
- A PERT expected duration is a model estimate.