Planning & Controls · probabilistic schedule analysisLesson 3

Study explanation · Lesson 03 · 7 min

Three-point estimates and PERT arithmetic

Keep optimistic, most likely and pessimistic estimates distinct, then calculate expected duration, standard deviation and variance with the right units.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Each input describes a different part of the estimate

Optimistic a describes a short duration under favorable conditions. Most likely m is the duration expected to occur most often. Pessimistic b describes a long duration under unfavorable conditions. Use comparable scope and conditions for the three values. The most likely value is a mode. PERT's expected duration is a weighted average, which can differ from that most likely value when the range is asymmetric.

The PERT inputs · slide 9
InputMeaningSource example
a · optimisticShort under favorable conditions8 days
m · most likelyExpected to occur most often10 days
b · pessimisticLong under unfavorable conditions16 days

Calculate duration and variability separately

The course uses expected duration = (a + 4m + b) ÷ 6, estimated standard deviation = (b − a) ÷ 6 and estimated variance = [(b − a) ÷ 6]². For 8, 10 and 16 days, the weighted total is sixty-four. Dividing by six gives about 10.67 days. The standard deviation is about 1.33 days. Squaring the unrounded value gives a variance of about 1.78 days squared. Keep full precision until the final rounding. Variance and expected duration cannot be substituted for one another.

The worked activity · slide 10
QuantityCalculationRounded result
Expected duration(8 + 4 × 10 + 16) ÷ 610.67 days
Standard deviation(16 − 8) ÷ 61.33 days
Variance[(16 − 8) ÷ 6]²1.78 days²

Key ideaThe expected duration supports a model. It does not guarantee the activity's actual finish.

Key takeaways

  • Most likely and expected duration can differ.
  • Standard deviation uses days; variance uses days squared.
  • Round after calculating, rather than before squaring or summing.
  • A PERT expected duration is a model estimate.

Based on Week 3_ Probabilistic Schedule Analysis.pptx by Farah Demachkieh, Ph.D. Source notes identify slide coverage; practice and reflections are study-guide additions.

Your study checkpoint

Ready to continue?

Mark the lesson complete once you have read it and tried its idea on something real.

Next · Lesson 4