Network paths and deadline confidence

Follow the deck's four-activity network, calculate the two path distributions, and explain why a fixed-path probability cannot establish whole-project confidence.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The project waits for both parallel branches

A starts the project. B and C both follow A. D waits for B and C. The two paths are A–B–D and A–C–D, and all durations are in days. Calculate every activity's expected duration using the same PERT formula before comparing the routes. Using expected durations, A–B–D takes 4 + 9 + 3.5 = 16.5 days. A–C–D takes 4 + 8.5 + 3.5 = 16 days. A–B–D is therefore critical in this expected-duration schedule. Actual sampled durations can produce a different controlling branch.

The complete network inputs · slide 11
ActivityPredecessorambExpected days
ANone23104
BA89109
CA28178.5
DB and C1383.5

Add variances before taking the square root

The source's path calculation assumes independent activity durations. Under that assumption, add activity variances along a fixed path, then take the square root to obtain its standard deviation. The activity variances derived from slide 11 are about 1.7778 for A, 0.1111 for B, 6.25 for C and 1.3611 for D, in days squared. A–B–D has variance 3.25 days squared and standard deviation about 1.80 days. A–C–D has variance about 9.39 days squared and standard deviation about 3.06 days. The second path has a slightly shorter expected duration and much greater variability.

Path results · slide 12
PathExpected durationVarianceStandard deviation
A–B–D16.5 days3.25 days²1.80 days
A–C–D16.0 days9.39 days²3.06 days

Read with careActivity variances shown in the paragraph are arithmetic derived from slide 11. Path values match slide 12. Independent activity durations are an explicit assumption.

A deadline probability belongs to the path being modeled

For A–B–D alone, the deck applies a normal approximation. With a twenty-day deadline, Z = (deadline − mean) ÷ standard deviation = (20 − 16.5) ÷ √3.25 ≈ 1.94. The cumulative normal probability is about 97.4 percent. The same path's P95 estimate is 16.5 + 1.645 × √3.25, about 19.47 days. These results describe the fixed A–B–D path under the stated approximation. They do not establish a 97.4-percent chance that the whole project finishes by day twenty, because D also waits for C.

Source calculation · slide 13A–B–D: mean 16.5 days; SD √3.25 ≈ 1.80 days. Z by day 20 ≈ 1.94. Cumulative normal probability ≈ 97.4%. Fixed-path P95 ≈ 19.47 days.

The two paths share risk as well as work

Slide 14 gives about 90.4 percent by day twenty for A–C–D, using its mean of sixteen and standard deviation of about 3.06 days. The project needs both routes to finish. The native density chart illustrates the second path's broader spread and longer right tail. Do not multiply the two path probabilities. They share A and D, so even an independent-activity assumption leaves their path durations dependent. A long A or D affects both. A model of the whole project must preserve those shared activities and evaluate the network consistently.

Read with careCritical in the expected-duration schedule does not mean critical in every possible outcome. The deck supplies path approximations, not a numerical whole-project completion probability.

Key takeaways

  • D starts after both B and C finish.
  • A–B–D is critical using expected durations, while A–C–D has greater variability.
  • Independent activity variances add along a fixed path.
  • Shared activities make the path durations dependent.
  • A fixed-path deadline probability is insufficient for the complete project.

Based on Week 3_ Probabilistic Schedule Analysis.pptx by Farah Demachkieh, Ph.D. Source notes identify slide coverage; practice and reflections are study-guide additions.