The project waits for both parallel branches
A starts the project. B and C both follow A. D waits for B and C. The two paths are A–B–D and A–C–D, and all durations are in days. Calculate every activity's expected duration using the same PERT formula before comparing the routes. Using expected durations, A–B–D takes 4 + 9 + 3.5 = 16.5 days. A–C–D takes 4 + 8.5 + 3.5 = 16 days. A–B–D is therefore critical in this expected-duration schedule. Actual sampled durations can produce a different controlling branch.
| Activity | Predecessor | a | m | b | Expected days |
|---|---|---|---|---|---|
| A | None | 2 | 3 | 10 | 4 |
| B | A | 8 | 9 | 10 | 9 |
| C | A | 2 | 8 | 17 | 8.5 |
| D | B and C | 1 | 3 | 8 | 3.5 |
Add variances before taking the square root
The source's path calculation assumes independent activity durations. Under that assumption, add activity variances along a fixed path, then take the square root to obtain its standard deviation. The activity variances derived from slide 11 are about 1.7778 for A, 0.1111 for B, 6.25 for C and 1.3611 for D, in days squared. A–B–D has variance 3.25 days squared and standard deviation about 1.80 days. A–C–D has variance about 9.39 days squared and standard deviation about 3.06 days. The second path has a slightly shorter expected duration and much greater variability.
| Path | Expected duration | Variance | Standard deviation |
|---|---|---|---|
| A–B–D | 16.5 days | 3.25 days² | 1.80 days |
| A–C–D | 16.0 days | 9.39 days² | 3.06 days |
Read with careActivity variances shown in the paragraph are arithmetic derived from slide 11. Path values match slide 12. Independent activity durations are an explicit assumption.
A deadline probability belongs to the path being modeled
For A–B–D alone, the deck applies a normal approximation. With a twenty-day deadline, Z = (deadline − mean) ÷ standard deviation = (20 − 16.5) ÷ √3.25 ≈ 1.94. The cumulative normal probability is about 97.4 percent. The same path's P95 estimate is 16.5 + 1.645 × √3.25, about 19.47 days. These results describe the fixed A–B–D path under the stated approximation. They do not establish a 97.4-percent chance that the whole project finishes by day twenty, because D also waits for C.
Source calculation · slide 13A–B–D: mean 16.5 days; SD √3.25 ≈ 1.80 days. Z by day 20 ≈ 1.94. Cumulative normal probability ≈ 97.4%. Fixed-path P95 ≈ 19.47 days.
Key takeaways
- D starts after both B and C finish.
- A–B–D is critical using expected durations, while A–C–D has greater variability.
- Independent activity variances add along a fixed path.
- Shared activities make the path durations dependent.
- A fixed-path deadline probability is insufficient for the complete project.