Planning & Controls · probabilistic schedule analysisSummary

Module summary · 5 min

A completion forecast with its assumptions visible

Review the source's calculations and distinguish the uncertainty in an activity, a fixed path and the complete project. Use completion confidence to support an explained schedule decision.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Read the evidence before choosing the model

For 3, 4, 4, 5 and 14 days, the mean is six while the median and mode are four. Dana's seven charted observations have a mean of four and sample SD about 0.82 days. Rami's have a mean about 6.29 and sample SD about 3.04 days. These statistics describe the records; comparable work and conditions are still needed before judging performance. Review spread, shape and optimism, anchoring or availability. Under the illustrated normal model with mean ten and SD two days, the central 68%, 95% and 99.7% bands are 8–12, 6–14 and 4–16 days. The source warns that not every project finish is normal. Rolling wave planning improves detail as information arrives, while agile approaches use short delivery and feedback cycles.

Keep the PERT quantities and network consistent

The 8–10–16 activity has expected duration about 10.67 days, SD about 1.33 days and variance about 1.78 days squared. In the complete four-activity example, A starts the work, B and C follow A, and D waits for both. A–B–D has mean 16.5 and variance 3.25, while A–C–D has mean sixteen and variance about 9.39. The A–B–D normal approximation gives about 97.4% by day twenty and a fixed-path P95 about 19.47 days. A–C–D gives about 90.4% by day twenty. The project needs both routes, which share A and D. The probabilities cannot be multiplied, and neither alone establishes whole-project completion confidence.

Use the modeled outcomes to support a decision

Monte Carlo assigns distributions, samples coherent activity durations, recalculates the complete network and repeats. Model shared weather or supplier effects, preserve each activity's value within a trial, and avoid counting a risk twice. Choose triangular, beta-PERT, uniform or normal inputs from their suitability and evidence. The separate illustrative curve gives P50 at thirty days, P80 at 32.5 and P95 at 34.9. It is not an actual simulation of the four-activity example. State the confidence behind a proposed date, agree its use in the commitment and time allowance, address important risks and update the model as evidence changes.

Based on Week 3_ Probabilistic Schedule Analysis.pptx by Farah Demachkieh, Ph.D. Source notes identify slide coverage; practice and reflections are study-guide additions.