One trial represents one possible execution
Assign distributions to uncertain activity durations, sample durations, recalculate the network and repeat thousands of times. Record the finish date and which activities become critical in each trial. The resulting finish-date distribution captures alternative controlling paths within the modeled schedule. For the four-activity example, a consistent trial uses one sampled duration for A and one for D wherever those activities appear. The trial's project duration is A + the greater of B and C + D. This expression is a study-guide explanation of the supplied predecessor logic. Sampling separate versions of A for each path would describe contradictory executions of the same work.
- AssignChoose activity duration distributions
- SampleGenerate one coherent set of durations
- RecalculateResolve the network and controlling path
- RepeatCollect many finishes and criticality outcomes
Choose a distribution that fits the evidence
A triangular model uses minimum, most likely and maximum estimates. Beta-PERT provides a smooth bounded model using three-point estimates. Uniform assigns equal likelihood to equal-sized intervals within its range. A normal model needs evidence supporting a symmetric shape. Using three estimates does not make triangular and beta-PERT identical. Nor does it make all values inside the range equally likely. Document why the chosen model represents the work and how its parameters were estimated.
| Distribution | When the deck says it may be useful |
|---|---|
| Triangular | Minimum, most likely and maximum estimates |
| Beta-PERT | A smooth bounded model using three-point estimates |
| Uniform | All values within the range are equally likely |
| Normal | A symmetric model supported by evidence |
Key takeaways
- Recalculate the whole network in each trial.
- Use one sampled duration consistently for each shared activity.
- Choose distributions from evidence and stated assumptions.
- Preserve material common causes and avoid double counting risks.