Planning & Controls · probabilistic schedule analysisLesson 5

Study explanation · Lesson 05 · 8 min

Monte Carlo simulation and model inputs

Sample plausible activity durations, recalculate the complete network, and preserve shared risks across many trials. Input choices determine what the results can mean.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

One trial represents one possible execution

Assign distributions to uncertain activity durations, sample durations, recalculate the network and repeat thousands of times. Record the finish date and which activities become critical in each trial. The resulting finish-date distribution captures alternative controlling paths within the modeled schedule. For the four-activity example, a consistent trial uses one sampled duration for A and one for D wherever those activities appear. The trial's project duration is A + the greater of B and C + D. This expression is a study-guide explanation of the supplied predecessor logic. Sampling separate versions of A for each path would describe contradictory executions of the same work.

Monte Carlo workflow · slide 15
  1. AssignChoose activity duration distributions
  2. SampleGenerate one coherent set of durations
  3. RecalculateResolve the network and controlling path
  4. RepeatCollect many finishes and criticality outcomes

Choose a distribution that fits the evidence

A triangular model uses minimum, most likely and maximum estimates. Beta-PERT provides a smooth bounded model using three-point estimates. Uniform assigns equal likelihood to equal-sized intervals within its range. A normal model needs evidence supporting a symmetric shape. Using three estimates does not make triangular and beta-PERT identical. Nor does it make all values inside the range equally likely. Document why the chosen model represents the work and how its parameters were estimated.

Input distribution choices · slide 16
DistributionWhen the deck says it may be useful
TriangularMinimum, most likely and maximum estimates
Beta-PERTA smooth bounded model using three-point estimates
UniformAll values within the range are equally likely
NormalA symmetric model supported by evidence

Shared conditions connect different activities

Weather or a supplier can affect several activities together. The deck asks the team to model common causes and avoid counting the same risk twice. Independent sampling may miss that connection when a shared event delays many tasks. Adding a separate allowance for a risk already represented in the duration inputs can also overstate it. Record where each important risk enters the model, which activities it affects, and whether the resulting sampled durations need to move together. The credibility of the output depends on those assumptions as well as on the number of trials.

Key ideaRepeated calculation explores the model supplied. Review the network and its inputs before relying on the output.

Key takeaways

  • Recalculate the whole network in each trial.
  • Use one sampled duration consistently for each shared activity.
  • Choose distributions from evidence and stated assumptions.
  • Preserve material common causes and avoid double counting risks.

Based on Week 3_ Probabilistic Schedule Analysis.pptx by Farah Demachkieh, Ph.D. Source notes identify slide coverage; practice and reflections are study-guide additions.