Where each lesson comes from, what was not supplied, and the places where the material needs a careful reading.
The sources
This path follows the supplied Week 3_ Probabilistic Schedule Analysis.pptx, an eighteen-slide deck by Farah Demachkieh, Ph.D. Slide numbering includes the title. The complete slide text, tables, equations and six native chart data sets were inspected. There are no embedded source images or speaker-note explanations. The guide preserves the source's numerical examples; intermediate calculations, interpretations, questions and scenarios are labeled teaching additions. The separate 12 November recording has its own study path and learner Q&A.
Listening
Use Listen on lesson and summary pages for the same Marin AI narration as the other narrated courses, with sentence and word highlighting. Back to the lessons →
The complete Week 3 deck mapped to the lessons
Lesson
Coverage
Slides
1 · Data and estimation bias
Uncertainty, center, seven-observation chart, variability, shape, probability and bias
2–6
2 · Normal models and planning
Normal density and central bands, CLT limit, rolling wave and agile
7–8
3 · PERT for one activity
Three-point inputs, equations and the 8–10–16 calculation
9–10
4 · Paths and deadlines
Four-activity network, path statistics, Z, P95, shared paths and density comparison
11–14
5 · Simulation and inputs
Monte Carlo workflow, four input distributions and common risks
15–16
6 · Confidence and decisions
Illustrative cumulative curve, percentile labels, commitments and updates
17–18
Read with careSlide 1 identifies the course, author and Week 3 title. Native charts on slides 4, 5, 7, 14 and 17 were read alongside their text.
Lesson 01
Duration data, variability and estimation bias
An average describes only part of a duration estimate. Examine the center, spread and shape of the evidence, then check how bias can affect the estimate.
Keep optimistic, most likely and pessimistic estimates distinct, then calculate expected duration, standard deviation and variance with the right units.
Follow the deck's four-activity network, calculate the two path distributions, and explain why a fixed-path probability cannot establish whole-project confidence.
Four activity inputs, predecessor conditions, two path means, variances and standard deviations. Intermediate activity variances are derived calculations.
Sample plausible activity durations, recalculate the complete network, and preserve shared risks across many trials. Input choices determine what the results can mean.
Assign distributions, sample and recalculate, repeat thousands of times, and record finishes and critical activities. The A + max(B,C) + D expression is a teaching explanation of slide 11's network.
Week 3_ Probabilistic Schedule Analysis.pptx · slides 11 and 15
Inputs and common risks
The four distributions, shared weather or supplier effects, common-cause modeling and the double-counting warning.
Read the illustrative completion curve, explain the risk remaining after a percentile date, and use the analysis to support a realistic commitment and future updates.
Slide 4's chart supplies Dana's and Rami's seven observations, and its stated sample statistics reproduce correctly. These describe the records. The deck does not establish comparable tasks or conditions, so the lesson avoids ranking individual performance.
Distribution shapes are illustrative
Slides 5 and 7 contain native illustrative density charts. A small sample does not establish a full shape, and the normal-model bands do not prove that every project finish is normal.
PERT values are rounded estimates
The 8–10–16 results and the four-activity path values agree with the deck's formulas. Intermediate arithmetic retains precision before final rounding. Variance uses days squared.
Activity independence and path dependence differ
Slide 12 adds activity variances under independence. Slides 13–14 concern fixed-path normal approximations. The two path durations still depend on one another through shared A and D, so their deadline probabilities cannot be multiplied.
The complete project probability is not supplied
A–B–D is initially critical using expected durations, but C has greater uncertainty. The source gives approximately 97.4% and 90.4% for individual paths by day twenty, rather than a numerical whole-project probability.
The completion curve is a separate illustration
Slide 17 explicitly labels P50 thirty, P80 32.5 and P95 34.9 days as an interpretation example, not actual simulation results. These dates are separate from the four-activity network. The native curve's rounded percentile labels are preserved.
The guide explains the supplied model
No simulation output or software model accompanies the deck. The A + max(B,C) + D trial expression and the review checklists explain the source logic. Practice scenarios are study additions, rather than official assessment questions.
Checked against the supplied documents cited in each note.
What not to take away
The lessons actively work against these misreadings:
An average describes all duration risk.
A larger standard deviation alone proves worse performance.
A small sample establishes a normal distribution.
A central 95-percent interval ends at the 95th percentile.
Most likely and expected duration are always equal.
Activity standard deviations should be added instead of variances.
The original critical path controls every sampled outcome.
Independent activity durations make shared path durations independent.
The 97.4-percent path result is the whole-project probability.
P80 means the work is eighty percent complete.
The illustrative completion curve is an actual simulation of the four-activity network.
Thousands of trials repair unsupported inputs or double-counted risks.
Study-guide synthesis; each item is addressed in the lessons.