The bands depend on the normal model
The illustrated normal distribution has a mean of ten days and standard deviation of two days. About 68 percent of its outcomes fall within one standard deviation of the mean, about 95 percent within two and about 99.7 percent within three. The symmetric native density chart illustrates that assumed shape. These are central intervals in the model. The upper end of the central 95-percent interval is not the 95th percentile: the remaining probability is split across both tails. A deadline probability requires the cumulative probability up to the chosen date.
| Band | Interval | Approximate share |
|---|---|---|
| Mean ± 1 SD | 8 to 12 days | 68% |
| Mean ± 2 SD | 6 to 14 days | 95% |
| Mean ± 3 SD | 4 to 16 days | 99.7% |
Read with careThe interval-versus-percentile distinction is a study-guide clarification of the illustrated central bands.
A theorem does not choose every project distribution
The deck states that the central limit theorem supports some sums and averages, and explicitly warns that it does not make every project finish normally distributed. Treat normality as an assumption to justify. A whole project involves network relationships, merges and potentially shared risks as well as uncertain durations. The normal illustration explains a useful reference model. Later lessons show why the path with the greatest expected duration can change as activity durations vary, and why the whole network needs attention.
Read with careThe slide's bell curve does not establish that a particular activity or complete project follows that distribution.
Progressive detail and short delivery cycles
Rolling wave planning gives near-term work more detail and keeps later work at a higher level until more information is available. Agile approaches deliver usable results in short cycles, review feedback and adapt upcoming work. Both help teams plan amid uncertainty, but they describe different planning and delivery practices. The deck says CPM is not required within every sprint. This does not mean dependencies disappear. Use the appropriate planning detail and scheduling method for the actual work, and revise assumptions as information improves.
Rolling wave planning
- Detail the work that is near
- Keep later work at a higher level
- Add detail as information improves
Agile approaches
- Deliver usable results in short cycles
- Review feedback
- Adapt upcoming work
Key takeaways
- The normal-model bands depend on a suitable distribution assumption.
- A central interval and a completion percentile answer different questions.
- The central limit theorem does not make every project finish normal.
- Rolling wave planning concerns progressive detail; agile approaches use short delivery and feedback cycles.