Planning & Controls · Resource allocation reference

Glossary

Short definitions as the module uses them, each linked to the lesson it comes from.

Over-allocation

Assigning more work to a resource than it can realistically accomplish in the relevant period.

Review Lesson 1
Renewable resource

A resource whose availability renews each period, subject to a per-period limit.

Review Lesson 1
Non-renewable resource

A finite project resource total that is consumed rather than renewed each period.

Review Lesson 1
Doubly constrained resource

A resource with both recurring availability limits and a finite overall supply.

Review Lesson 1
Work Breakdown Structure (WBS)

The organization of project work into deliverables, tasks and smaller work packages.

Review Lesson 1
Organizational Breakdown Structure (OBS)

The organization of departments or people used to assign ownership of project work and costs.

Review Lesson 1
Responsibility Assignment Matrix (RAM)

A matrix connecting tasks or deliverables with the roles of organizational units or individuals.

Review Lesson 1
RACI

Responsible, Accountable, Consulted and Informed: four distinct roles for work, authority and communication.

Review Lesson 1
Responsible

The role performing the task, potentially with assistance.

Review Lesson 1
Accountable

The single final authority for completion and approval of a task or deliverable in the deck's RACI model.

Review Lesson 1
Consulted

A role providing input through two-way communication.

Review Lesson 1
Informed

A role receiving progress or completion updates through one-way communication.

Review Lesson 1
Worker-week

One worker's work for one week; activity worker-weeks equal crew size multiplied by duration in weeks.

Review Lesson 2
Aggregate capacity test

The necessary check W ≤ D × R, comparing total required work with total available period capacity.

Review Lesson 2
Early-start schedule

A schedule placing activities as soon as their dependencies allow, before confirming resource feasibility.

Review Lesson 2
Late-start schedule

A schedule placing activities at their latest allowable starts for the stated network finish.

Review Lesson 2
Lower bound

A minimum that a feasible duration cannot fall below under the stated test; it does not itself construct a feasible schedule.

Review Lesson 2
Cumulative requirements

The total resource quantity required up to a specified date.

Review Lesson 3
Cumulative supply

The total resource quantity supplied up to a specified date.

Review Lesson 3
Resource loading

Assigning required resource amounts to activities over the project baseline to reveal their time-phased demand.

Review Lesson 3
Gantt chart

A time-phased activity view used for planning, baseline tracking, updates and identifying resource requirements.

Review Lesson 3
Time-constrained project

A project whose required finish takes priority and may require additional or reorganized resources.

Review Lesson 4
Resource-constrained project

A project whose resource availability governs the schedule, potentially requiring a later finish.

Review Lesson 4
Mixed-constraint project

A project with both time and resource limits that require explicit trade-offs.

Review Lesson 4
Priority rule

A criterion for ranking eligible activities competing for limited resources, such as smallest slack or shortest duration.

Review Lesson 4
Slack or float

Available timing flexibility; C has four days in the source loading-chart example.

Review Lesson 5
Resource profile

The amount of resource demand in each interval, formed by summing concurrent activity requirements.

Review Lesson 5
Activity splitting

Interrupting and resuming activity work to redistribute its demand, when execution assumptions permit it.

Review Lesson 5
Resource leveling

Adjusting the schedule to respect available resources, potentially changing the finish and controlling sequence.

Review Lesson 6
Resource smoothing

Adjusting activities within float to reduce resource fluctuations while retaining the project duration; some conflicts may remain.

Review Lesson 6
Resource-driven sequencing

An ordering introduced because activities cannot share the available resource pool, as with E before F in the leveled compressor plan.

Review Lesson 6