Planning & Controls · Resource allocation reference
Glossary
Short definitions as the module uses them, each linked to the lesson it comes from.
- Over-allocation
Assigning more work to a resource than it can realistically accomplish in the relevant period.
Review Lesson 1- Renewable resource
A resource whose availability renews each period, subject to a per-period limit.
Review Lesson 1- Non-renewable resource
A finite project resource total that is consumed rather than renewed each period.
Review Lesson 1- Doubly constrained resource
A resource with both recurring availability limits and a finite overall supply.
Review Lesson 1- Work Breakdown Structure (WBS)
The organization of project work into deliverables, tasks and smaller work packages.
Review Lesson 1- Organizational Breakdown Structure (OBS)
The organization of departments or people used to assign ownership of project work and costs.
Review Lesson 1- Responsibility Assignment Matrix (RAM)
A matrix connecting tasks or deliverables with the roles of organizational units or individuals.
Review Lesson 1- RACI
Responsible, Accountable, Consulted and Informed: four distinct roles for work, authority and communication.
Review Lesson 1- Responsible
The role performing the task, potentially with assistance.
Review Lesson 1- Accountable
The single final authority for completion and approval of a task or deliverable in the deck's RACI model.
Review Lesson 1- Consulted
A role providing input through two-way communication.
Review Lesson 1- Informed
A role receiving progress or completion updates through one-way communication.
Review Lesson 1- Worker-week
One worker's work for one week; activity worker-weeks equal crew size multiplied by duration in weeks.
Review Lesson 2- Aggregate capacity test
The necessary check W ≤ D × R, comparing total required work with total available period capacity.
Review Lesson 2- Early-start schedule
A schedule placing activities as soon as their dependencies allow, before confirming resource feasibility.
Review Lesson 2- Late-start schedule
A schedule placing activities at their latest allowable starts for the stated network finish.
Review Lesson 2- Lower bound
A minimum that a feasible duration cannot fall below under the stated test; it does not itself construct a feasible schedule.
Review Lesson 2- Cumulative requirements
The total resource quantity required up to a specified date.
Review Lesson 3- Cumulative supply
The total resource quantity supplied up to a specified date.
Review Lesson 3- Resource loading
Assigning required resource amounts to activities over the project baseline to reveal their time-phased demand.
Review Lesson 3- Gantt chart
A time-phased activity view used for planning, baseline tracking, updates and identifying resource requirements.
Review Lesson 3- Time-constrained project
A project whose required finish takes priority and may require additional or reorganized resources.
Review Lesson 4- Resource-constrained project
A project whose resource availability governs the schedule, potentially requiring a later finish.
Review Lesson 4- Mixed-constraint project
A project with both time and resource limits that require explicit trade-offs.
Review Lesson 4- Priority rule
A criterion for ranking eligible activities competing for limited resources, such as smallest slack or shortest duration.
Review Lesson 4- Slack or float
Available timing flexibility; C has four days in the source loading-chart example.
Review Lesson 5- Resource profile
The amount of resource demand in each interval, formed by summing concurrent activity requirements.
Review Lesson 5- Activity splitting
Interrupting and resuming activity work to redistribute its demand, when execution assumptions permit it.
Review Lesson 5- Resource leveling
Adjusting the schedule to respect available resources, potentially changing the finish and controlling sequence.
Review Lesson 6- Resource smoothing
Adjusting activities within float to reduce resource fluctuations while retaining the project duration; some conflicts may remain.
Review Lesson 6- Resource-driven sequencing
An ordering introduced because activities cannot share the available resource pool, as with E before F in the leveled compressor plan.
Review Lesson 6