Identify resources and assign responsibility

Resource planning connects the work to the people, equipment, materials and funding it needs. Start by distinguishing resource types, then use the WBS, OBS and responsibility matrix to make ownership clear.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

A resource can be available and still be over-allocated

Over-allocation occurs when a resource is assigned more work than it can realistically accomplish. Having a person on the team does not make that person available for two full-time activities at once. The deck connects over-allocation with delays and inefficiency, and introduces schedule adjustments and resource reassignment as ways to respond. Resources include labor, equipment and materials. Before assigning them, establish what is available, in what quantity, and when. Responsibility and capacity answer different questions: knowing who owns a task does not prove that the owner has enough time to complete it.

Key ideaCheck the combined demand from overlapping activities against the resource actually available during that period.

Allocation assigns work; loading adds it across the day

The twelve-slide companion deck gives one engineer eight working hours on Monday. Reviewing drawings needs six hours and inspecting the site needs four. Allocation assigns the engineer to each activity and estimates those hours. Loading adds the assignments in the same period: six plus four is ten hours, two beyond Monday's capacity. Both tasks can have a clear owner and still form an impossible daily assignment. Before confirming the plan, change the timing, the assignment or the available capacity, then check what the revised arrangement allows. The companion does not prescribe which task should move in this example.

Engineer allocation and loading · companion PPTX slide 2
Monday assignmentRequired hours
Review drawings6
Inspect the site4
Total demand10
Available8
Over-allocation2

Three resource types need different checks

A renewable resource becomes available again at the start of each time period. The source uses workers who can work each day but have limited daily hours. A non-renewable resource has a finite total that is consumed rather than renewed for the project, such as a fixed materials budget. A doubly constrained resource has both a limit per period and a limit across the whole project. The source's generator can operate daily, but its fuel supply is finite. These distinctions change the feasibility test. A weekly worker limit must be respected each week. A finite materials allocation must cover total consumption, with enough supply available when it is needed. The generator needs both a workable operating schedule and enough fuel overall.

  • Renewable Availability renews each period; check concurrent demand against that period's capacity.
  • Non-renewable A finite project total; check consumption and the timing of supply.
  • Doubly constrained Both a per-period availability limit and a finite total apply.

Connect what must be done with who will do it

The Work Breakdown Structure organizes deliverables, tasks and work packages. The Organizational Breakdown Structure identifies departments or people. Their intersection links each piece of work to an organizational owner through a Responsibility Assignment Matrix. Budgets can then be associated with the units responsible for the work, supporting accountability and tracking. The source's information-systems example assigns work packages such as establishing a search committee, developing criteria and selecting a consultant to the responsible department. The useful distinction is the work on one dimension and its organizational ownership on the other. Although page 5 attributes work decomposition to the OBS, pages 6 and 7 clarify these different roles.

Work and organizational ownership meet in the responsibility matrix
  1. WBSWhat work must be delivered?
  2. OBSWhich people or units are involved?
  3. RAMWho participates in each work package?

Read the companion deck's construction RACI example

The companion PPTX supplies a second, internally consistent responsibility table. For measuring installed quantities, the foreman performs the work and the site engineer is Accountable. For preparing the cost forecast, the quantity surveyor performs the work and the project manager is Accountable. In each row, the remaining roles clarify consultation and notification. Use this example to practise the RACI legend directly. It does not resolve or replace the contradictory named assignments in the separate PDF illustration. The companion's instruction is to assign one Accountable person to each work item.

Construction RACI example · companion PPTX slide 4
Work itemForemanSite engineerQuantity surveyorProject manager
Measure installed quantitiesRACI
Prepare the cost forecastICRA

Read with careR = Responsible; A = Accountable; C = Consulted; I = Informed.

RACI separates doing, approving and communicating

Responsible performs the work. The notes describe one primary responsible role, potentially assisted by others. Accountable is the final authority who approves the result and ensures its accuracy; the source specifies one Accountable person per task or deliverable. Consulted provides input through two-way communication. Informed receives updates through one-way communication. A responsibility matrix can use a different legend. On page 9, a filled square means notification, a circle means responsible, a star means support and an outlined square means approval. For task 1.2.3, Gain user buy-in, the prose and graphic assign different people to the roles. The prose names Ann as responsible, Dave as support and Sue as approver, while the graphic marks Jim as responsible, Sue as support and Ann for notification. The example therefore cannot establish one consistent named assignment. Its legend remains useful, and support in this chart is not automatically the same as Consulted in RACI.

The four RACI roles in the supplied deck
RoleMeaningCommunication or authority
ResponsiblePerforms the taskPrimary worker, with possible assistance
AccountableApproves and answers for completionOne final accountable authority
ConsultedProvides input and opinionsTwo-way communication
InformedReceives updatesOne-way communication

Read with careRead each matrix's legend. The page 9 symbols include a support role and are not a one-to-one replacement for RACI. Its named assignments also conflict between prose and graphic; use the definitions rather than treating those names as an answer key.

Key takeaways

  • Resource ownership does not establish resource availability.
  • Renewable resources have period limits; non-renewable resources have finite totals.
  • The WBS describes work, the OBS describes organizational roles, and the RAM connects them.
  • RACI distinguishes doing, final accountability, consultation and notification.

Based on the supplied Resource Allocation, Leveling and Smoothing PDF and PPTX companion by Farah Demachkieh, Ph.D. Separate page and slide references appear in source notes; practice and reflections are study-guide additions.