Planning & Controls · Resource allocationSummary

Module summary · 5 min

What to keep from resource allocation

Resource planning joins ownership, the timing of demand and the limits of supply. A good decision makes clear which constraint it protects and verifies the whole revised schedule.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Connect the work, the owner and the available capacity

The WBS describes the work; the OBS describes organizational roles. Their intersection creates a responsibility matrix. In RACI, Responsible does the work, Accountable approves and answers for it, Consulted contributes through two-way communication, and Informed receives updates. A named owner still needs enough time and resources. Renewable resources have availability per period. Non-renewable resources have finite totals, whose supply must also arrive in time. Doubly constrained resources have both kinds of limits. Loading the schedule shows when these resources are required and allows demand to be checked against supply.

Use calculations for the conclusion they actually support

In the worker example, total required work is 101 worker-weeks. Twelve weeks with nine workers provides 108 worker-weeks in aggregate, but early and late schedules both overload individual weeks. The refined source test subtracts eleven worker-weeks of unavoidable idle capacity. It gives a lower bound of approximately 12.44 weeks, not proof that thirteen weeks is achievable. In the finite-resource example, thirty-six required units must be compared with cumulative supply throughout time. In the separate loading-chart example, splitting C reduces peak demand from nine resource units to seven, with the same seventy-two resource-days and twelve-day finish. The different units and time conventions belong to different examples.

Read with careThe worker deck's page 14 has an eight-week label with twelve-week arithmetic. Read the calculation as a twelve-week test and keep the source discrepancy visible.

State the governing constraint before choosing an adjustment

A time-constrained project protects its deadline. A resource-constrained project respects the available pool, even if the finish moves. A mixed-constraint project must address both. The five priority rules use smallest slack, shortest duration, lowest ID, most successors or highest resource demand. They help choose among eligible activities but do not override dependencies or establish an optimal solution. Practical adjustments include moving and splitting work, changing assigned hours, reallocating or adding resources, and authorizing overtime. Each requires a realistic execution assumption and a new check of the full schedule.

Remember the compressor decision

The seven-activity CPM schedule takes twenty days and has a six-compressor limit. It needs seven compressors on days six to nine and eight on days eleven and twelve. Leveling places D on days eleven to fourteen, F on twenty to twenty-one and G on twenty-two. It removes all resource conflicts under the six-compressor ceiling. Smoothing also moves D and then F, but keeps G on day twenty. It leaves E and F demanding eight compressors on days fifteen and sixteen. That schedule needs two extra compressors on each of those days. A retained deadline and a fully resource-feasible plan are different conclusions, so state exactly what the chosen adjustment achieves.

Based on the supplied Resource Allocation, Leveling and Smoothing PDF and PPTX companion by Farah Demachkieh, Ph.D. Separate page and slide references appear in source notes; practice and reflections are study-guide additions.