Planning & Controls · Resource allocationLesson 5

Study explanation · Lesson 05 · 9 min

Build a loading chart and smooth it within float

Follow the six-activity loading-chart example from network dates to a resource profile. Then split C within its available float to reduce the peak from nine resource units to seven while preserving the twelve-day finish.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Start with network dates and resource requirements

The deck's four-step method begins with a network diagram, then a table of activity resource needs, duration, early start, late finish and slack. It next draws the early-start loading chart, then rearranges work within slack to produce a more level profile. The network has A before B and C, B before D, D before E, and both C and E before F. A uses six resources for four days from elapsed time zero. B uses two for one day from time four. C uses two for three days from time four. D uses seven for four days from time five. E uses three for two days from time nine. F uses six for one day from time eleven. The finish is time twelve. C has four days of slack and a late finish of eleven; every other listed activity has zero slack.

Loading-chart activity table from PDF p. 41
ActivityResourcesDurationESLFSlack
A64040
B21450
C234114
D74590
E329110
F6111120

Read with careTime is elapsed project days. An interval from 4 to 5 lasts one day. No hard resource-capacity limit is stated for this example.

Add simultaneous demand to construct the profile

From zero to four, only A is active, requiring six resources. From four to five, B and C together require four. From five to seven, D and C together require nine. From seven to nine, D alone requires seven. E requires three from nine to eleven, followed by F requiring six from eleven to twelve. This early-start profile is reconstructed from the network and table on pages 40 and 41. Page 42's printed chart places D, E and F later, ending at fourteen, which contradicts those inputs. The reconstructed profile has a peak of nine. A peak is not automatically an overload: compare it with an actual availability limit before using that word. This example states no hard capacity line; its objective is to make the profile more level using schedule flexibility.

Initial profile derived from the source activity intervals
Elapsed daysActive workResources
0–4A6
4–5B and C4
5–7C and D9
7–9D7
9–11E3
11–12F6

Split C and preserve the same work

The source keeps the first day of C from time four to five, then pauses C while D runs. Its remaining two days move to time nine to eleven alongside E. C still receives two resources for a total of three working days and finishes at its late finish of eleven. The other activity intervals stay as shown. The revised profile is six from zero to four, four from four to five, seven from five to nine, five from nine to eleven and six from eleven to twelve. The peak falls from nine to seven and the project still ends at twelve. Derived from the source table, both profiles contain seventy-two resource-days: smoothing changes the distribution, not the total work.

Stacked loading charts before and after splitting activity C. Initially C overlaps D and total demand peaks at nine. Moving two days of C to run with E reduces the peak to seven and retains the twelve-day finish.
Initial profile reconstructed from the network and table on PDF pp. 40–41; split-C profile follows p. 43. The printed p. 42 chart uses inconsistent activity dates. C runs from elapsed day 4 to 5 and again from 9 to 11 after smoothing.

Read with careThis illustration assumes C can be interrupted and resumed. Do not split real work without checking continuity, restart costs and its actual dependencies.

Key takeaways

  • A loading chart sums concurrent resource requirements over time.
  • The initial chart peaks at nine where C overlaps D.
  • Splitting C as shown reduces the peak to seven without changing the twelve-day finish.
  • Float is usable scheduling flexibility; interrupted execution also needs to be feasible.

Based on the supplied Resource Allocation, Leveling and Smoothing PDF and PPTX companion by Farah Demachkieh, Ph.D. Separate page and slide references appear in source notes; practice and reflections are study-guide additions.