Start with network dates and resource requirements
The deck's four-step method begins with a network diagram, then a table of activity resource needs, duration, early start, late finish and slack. It next draws the early-start loading chart, then rearranges work within slack to produce a more level profile. The network has A before B and C, B before D, D before E, and both C and E before F. A uses six resources for four days from elapsed time zero. B uses two for one day from time four. C uses two for three days from time four. D uses seven for four days from time five. E uses three for two days from time nine. F uses six for one day from time eleven. The finish is time twelve. C has four days of slack and a late finish of eleven; every other listed activity has zero slack.
| Activity | Resources | Duration | ES | LF | Slack |
|---|---|---|---|---|---|
| A | 6 | 4 | 0 | 4 | 0 |
| B | 2 | 1 | 4 | 5 | 0 |
| C | 2 | 3 | 4 | 11 | 4 |
| D | 7 | 4 | 5 | 9 | 0 |
| E | 3 | 2 | 9 | 11 | 0 |
| F | 6 | 1 | 11 | 12 | 0 |
Read with careTime is elapsed project days. An interval from 4 to 5 lasts one day. No hard resource-capacity limit is stated for this example.
Add simultaneous demand to construct the profile
From zero to four, only A is active, requiring six resources. From four to five, B and C together require four. From five to seven, D and C together require nine. From seven to nine, D alone requires seven. E requires three from nine to eleven, followed by F requiring six from eleven to twelve. This early-start profile is reconstructed from the network and table on pages 40 and 41. Page 42's printed chart places D, E and F later, ending at fourteen, which contradicts those inputs. The reconstructed profile has a peak of nine. A peak is not automatically an overload: compare it with an actual availability limit before using that word. This example states no hard capacity line; its objective is to make the profile more level using schedule flexibility.
| Elapsed days | Active work | Resources |
|---|---|---|
| 0–4 | A | 6 |
| 4–5 | B and C | 4 |
| 5–7 | C and D | 9 |
| 7–9 | D | 7 |
| 9–11 | E | 3 |
| 11–12 | F | 6 |
Split C and preserve the same work
The source keeps the first day of C from time four to five, then pauses C while D runs. Its remaining two days move to time nine to eleven alongside E. C still receives two resources for a total of three working days and finishes at its late finish of eleven. The other activity intervals stay as shown. The revised profile is six from zero to four, four from four to five, seven from five to nine, five from nine to eleven and six from eleven to twelve. The peak falls from nine to seven and the project still ends at twelve. Derived from the source table, both profiles contain seventy-two resource-days: smoothing changes the distribution, not the total work.
Read with careThis illustration assumes C can be interrupted and resumed. Do not split real work without checking continuity, restart costs and its actual dependencies.
Key takeaways
- A loading chart sums concurrent resource requirements over time.
- The initial chart peaks at nine where C overlaps D.
- Splitting C as shown reduces the peak to seven without changing the twelve-day finish.
- Float is usable scheduling flexibility; interrupted execution also needs to be feasible.