Compare leveling and smoothing with six compressors

The seven-activity compressor example begins with a twenty-day critical-path schedule and six overloaded days. Leveling respects the six-compressor limit and finishes in twenty-two days. Smoothing keeps twenty days and leaves two days needing extra capacity.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Choose what the adjustment must protect

Pages 46 and 47 distinguish the two techniques. Smoothing gives priority to the time constraint: activities move within available float while the project duration is kept. It can leave resource conflicts unresolved, requiring additional resources to retain the deadline. Leveling gives priority to available resources: conflicting work is rescheduled to fit capacity, potentially beyond float and beyond the original finish. The source's house example makes the trade-off concrete. A fixed six-month delivery favors smoothing. A fixed pool of workers may require leveling and a later delivery. Although page 20 uses the two terms interchangeably, this guide follows the explicit distinction in the later comparison. Leveling may change duration and the controlling sequence; it does not necessarily extend every project.

The deck's comparison, PDF pp. 46–47
DecisionLevelingSmoothing
PriorityAvailable resourcesRequired finish
MovementMay exceed available floatWithin available float
Resource conflictsResolve under the capacity limitReduce as far as the finish permits
DurationMay extendRetained
Extra resourcesMay not be neededMay be needed for residual conflicts
Critical pathMay changeKept in the source comparison

Build the original twenty-day compressor schedule

The organization has six compressors. A takes three days with six compressors. B follows A for two days with one. C follows B for five days with five. D also follows B, for four days with two. E follows C for nine days with four. F follows both C and D, for two days with four. G follows both E and F, for one day with six. The original critical path is A–B–C–E–G: three plus two plus five plus nine plus one equals twenty days. Using inclusive day labels, A runs on days one to three, B four to five, C six to ten, D six to nine, E eleven to nineteen, F eleven to twelve and G on twenty. The source network gives D eight days of total float and one of free float, and F seven days of both total and free float. Those values show timing flexibility before the resource limit is checked. Critical-path calculation alone does not account for the compressor limit.

Seven-activity compressor example from PDF p. 49
ActivityPredecessorsDaysCompressors
ANone36
BA21
CB55
DB42
EC94
FC and D24
GE and F16

Read with careThese examples use inclusive day labels, unlike the elapsed-day loading chart in Lesson 5. A three-day activity on days 1–3 finishes at elapsed time 3.

Find the six overloaded days

On days six to nine, C needs five compressors and D needs two. Combined demand is seven, one above the limit. On days eleven and twelve, E and F each need four, so their combined demand is eight, two above the limit. These are six conflict days in total. The fact that A–B–C–E–G is the longest precedence path does not make this original schedule executable with six compressors. The team must either change the timing, obtain additional capacity or revisit other project assumptions. A histogram with a capacity line makes these conflicts visible.

Conflict check from the sourceDays 6–9: C + D = 5 + 2 = 7 compressors. Days 11–12: E + F = 4 + 4 = 8. Available each day: 6.

Leveling removes conflicts and moves completion to day twenty-two

First move D to days eleven to fourteen, after C finishes. Demand on days six to nine drops to C's five compressors. D now overlaps E, using two plus four, exactly six. Because F waits for C and D, its earliest start moves to day fifteen. E and F would then require eight compressors on days fifteen and sixteen, so a conflict remains. Delay F again until E completes: F runs on days twenty and twenty-one, and G runs on day twenty-two. The displayed leveled plan has no day requiring more than six compressors. Its duration increases from twenty to twenty-two days. The deck calls A–B–C–E–F–G the new critical path. E before F is a resource-driven sequencing decision in this leveled plan, not a predecessor originally listed for F on page 49.

Key ideaFixing one overlap can move the conflict downstream. Follow successors and check the entire revised profile.

Compare the same work across all three schedules

The twelve-slide companion summarizes the original, smoothed and leveled outcomes in one table. All cover the same activity work. The original profile exceeds six on six days, the smoothed profile exceeds six on two days, and the leveled profile has no demand above six. Their peak and finish commitments show exactly which condition each arrangement satisfies. Its closing question fixes the client deadline at day twenty and permits a short rental. The displayed smoothed plan needs two extra compressors on days fifteen and sixteen. If only the original six are available, the displayed leveled alternative finishes on day twenty-two.

The companion's schedule comparison · PPTX slides 11–12
ScheduleFinishPeak daily demandDays above six
OriginalDay 208 compressors6
SmoothedDay 208 compressors2
LeveledDay 226 compressors0

Smoothing preserves day twenty but needs capacity on two days

For smoothing, D also moves from day six to day eleven. F consequently moves to days fifteen and sixteen while G can still finish on day twenty. The first four conflict days disappear. E and F still need eight compressors together on days fifteen and sixteen. With a limit of six, that twenty-day plan is not fully resource-feasible. Keeping it requires two additional compressors on each of those two days under the displayed arrangement. Smoothing removes four of the six original conflict days; it does not create enough float to remove the final two without extending the project. This is the practical difference between a deadline-preserving adjustment and a plan that respects the original resource ceiling.

Two different commitments from the same source example

Level the resources

  • D on days 11–14; F on 20–21
  • G finishes on day 22
  • Maximum six compressors

Smooth the schedule

  • D on days 11–14; F on 15–16
  • G finishes on day 20
  • Eight compressors needed on days 15–16

Key takeaways

  • The original CPM schedule takes twenty days but exceeds six compressors on six days.
  • Leveling moves D and F, respects six compressors and finishes on day twenty-two.
  • Smoothing retains day twenty but leaves demand of eight on days fifteen and sixteen.
  • The leveled controlling sequence includes a resource-driven E-to-F ordering.

Based on the supplied Resource Allocation, Leveling and Smoothing PDF and PPTX companion by Farah Demachkieh, Ph.D. Separate page and slide references appear in source notes; practice and reflections are study-guide additions.